Professional Documents
Culture Documents
Detailed Estimate
1 od89795/2022_2023
mobilisation including transportation of all necessary plant, machinery and labour to site for conducting
field boring and sampling and demobilisation after completing the work
1 1.000
PRICE
setting up boring equipment at each bore hole location including carrying all necessary plant, equipment
and materials of boring and field test and collection of samples at each bore hole.
5 5.000
3 od89797/2022_2023
Boring through soil, conducting standard penetration tests and collection of samples up to a depth of
10m.
5 5.000
4 od92090/2022_2023
Boring with rotary power drilling equipment's in all types of soil having N value less than 50 excluding
hard rock soft rock, or medium rock for strata for next 10m up to 20m Including conducting necessary
S.P.T and recovery of un disturbed soil samples at 5m.intervals
1 8.500 8.500
5 od92108/2022_2023
Boring through all classes of rock excluding hard rocks having 'N' value grater than 50 using tungsten
carbide drilling bit in land.
1 3.000 3.000
6 od89799/2022_2023
conducting laboratory test on collected samples, preparation and submission of geotechnical report each
and every detail of location, borehole profiles and cross sections, description of soil strata, etc. along with
Kerala Water Authority
recommendation for foundation (2nos)
PRICE
1 1.000 1.000
Total 137578.00
Centage @ 0.0%