KRB II - Bill 04
Ch. 0+00 to Ch. 4+500
1 Required restrained length at start point

2 Crossing at OCH - Assume existing levels at culvert and levels given by RDA for
proposed culvert are final. Add note "Details to be reviewed by RDA"
Ch.4+500 to Ch.6+600
1 Ceywater to indicate 'crossing of 400 DI not identified' at TP detail TP-21.
2 TP-22 - details sent by maga to be corrected from 1000 to 900 dia.
3 Railway crossing - details of micro tunelling not available.
4 Suez requested realign pipe from LHS to RHS from Ch. 4+930 to Ch. 5+100.
Relocate connection at Ch.5+460 to a downstream location to avoid deep
5
excavation.
Ch.6+600 to Ch.16+300
1 Awaiting details of new TP to update connection details at CH 7+140
2 Peralanda railway crossing details on hold.
3 Realign pipe to LHS from Ch7+470 to 8+375
4 Connection at 8+375 to be relocated upstream.
5 TP-37 - Mismatch of details sent by Maga.
6 TP- 51 - Realign pipeline
7 TP- 55 - Realign pipeline
8 TP-56 - Mismatch of details sent by Maga.
TP-60 - Mismatch of details sent by Maga. realign pipe line as per plan view send
9
by MAGA.
10 TP-62 - Realign pipe line away from 160mm
11 Plan views will be revised by to CH. 14+450 as discussed.