School of Vocational Engineering, Health and Sciences

RMIT University
CIVE1206: Roads and Transport Tutorial
Date:

Week:

Student ID

Signature

Last Name

First Name

13

Problem 1:
Table 1 given in page 2 shows the calculated cut and fill areas at different stations along a
proposed route. The distance between the stations is 100 m. The shrinkage factor for the soil
at the site was determined to be 15%. The agreed Free Haul Distance (FHD) is 200m and the
Limit of Profitable Haul (LPH) was determined to be 500 meter. Based on the given
information, answer the following questions:
a) Complete the calculations (gray coloured cells in Table 1 given in page 2) required to
develop the mass-haul diagram.
b) Plot the mass-haul diagram.
c) On the plotted mass-haul diagram, show the free-haul distance between Station 0 and
a point at 750m from Station 0. Also determine the volume of material between the
above two points that can be hauled free of cost.
d) On the plotted mass-haul diagram, show the profitable haul distance between Station
0 and a point at 750m from Station 0. Also determine the quantity of material that can
be profitably hauled between the above two points.
e) Determine the amount of materials that needs to be wasted and borrowed between
Station 0 and a point at 750m from Station 0.

Page 1 of 5

Station

Distance
from
Station
No. 0 (m)

End Area (m )
Cut

Fil

100

0.5

200

300

400

500

600

700

800

900

10

1000

10

Mass
diagram
Adjusted ordinate
3
Fill
(m )

Volume (m )
Cut

Fill

Page 2 of 5

Page 3 of 5

Page 4 of 5

Page 5 of 5