(A)
SR. NO.
1
ITEMS IN PLINTH
Excavation in black
cotton soil
UNIT PER
100 cft
1 cum
100 cft
1 cum
100 sft
1 sqm
(B)
SR. NO.
CONCRETE ITEMS
P.C.C. (1 : 4 : 8)
P.C.C. (1 : 3 : 6)
R.C.C. (1 : 2 : 4)
R.C.C. (1 : 1 : 3)
UNIT PER
100 cft
1 cum
100 cft
1 cum
100 cft
1 cum
100 cft
1 cum
(C)
SR. NO.
1
2
CONCRETE BLOCKS
UNIT PER
(12 x 4
35
35
50
50
Nos.
Nos.
Nos.
Nos.
(D)
SR. NO.
U.C.R. masonry
in C.M. 1:6
in C.M. 1:6
in C.M. 1:4
UNIT PER
100 cft
1 cum
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
(E)
SR. NO.
PLASTERING ITEMS
UNIT PER
b) In C.M. 1 : 5
c) In C.M. 1 : 6
Sanla finish plaster 20 mm () thick
a) In C.M. 1 : 4
b) In C.M. 1 : 5
c) In C.M. 1 : 6
Sanla faced plaster
Single coat 15 to 20 mm thick
a) In C.M. 1 : 4
b) In C.M. 1 : 5
c) In C.M. 1 : 6
Sanla faced plaster
Double coat 15 to 20 mm thick
a) In C.M. 1 : 4
b) In C.M. 1 : 5
c) In C.M. 1 : 6
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
(F)
SR. NO.
1
2
3
4
5
I.P.S. flooring
UNIT PER
100 cft
1 cum
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
100 sft
1 sqm
(G)
SR. NO.
1
WATER PROOFING
Brickbat coba W/P
in W.C. bath, toilet etc.
UNIT PER
100 sft
1 sqm
2
3
100 sft
1 sqm
100 sft
1 sqm
SR.
MATERIAL REQUIRED
UNIT
Plywood 12 m thick of
Size 2.44 x 1.22 m
(8-0 x 4-0)
Silver oak battern of
Size 75 mm x 40 mm
232 sqm
(3 x 1 )
232 sqm
2500 sft
40 mm thick (1 )
232 sqm
2500 sft
2500 sft
3
Wooden props
2500 sft
a) For beams
232 sqm
2500 sft
b) For slab
232 sqm
5
2500 sft
232 sqm
2500 sft
232 sqm
2500 sft
Wire nails
232 sqm
8
2500 sft
Shuttering oil
232 sqm
9
M.S. clamps
(Shikanja)
2500 sft
232 sqm
SR. NO.
ITEMS
CONSUMPTION OF STEEL
on built-up area
Footing
0.55 kg/sqm
Columns up to plinth
2.15 kg/sqm
Tie beam
1.15 kg/sqm
4.80 kg/sqm
5
6
Slab
Beam
7.0 kg/sqm
7.5 kg/sqm
Chajja/loft/lintel
0.55 kg/sqm
0.55 kg/sqm
TOTAL
24.25
kg/sqm
PROXIMATE QUANTITIES OF VARIOUS ITEMS PER SQ. M. / SQ. FT. OF BUILT-UP AREA.
APPROX. QTY.
PER
SR. NO.
ITEM
1
2
3
Excavation
R.C.C. below plinth
R.C.C. above plinth
SQ. M.
0.31 cum
0.046 cum
0.290 cum
Internal Masonry
0.7 sqm
External Masonry
0.9 sqm
Internal Plaster/Paint
3.2 sqm
7
8
External Plaster/Paint
Oil Paint
2.5 sqm
0.62 sqm
SQ. FT.
LOOSE SOIL
150 cft
1.5 cum
LOOSE MURUM
RUBBLE
150 cft
1.50 cum
90 cft
0.26 cum
CEMENT
9 bags
3.18 bags
12 bags
4.24 bags
17 bags
6.00 bags
22 bags
7.77 bags
CEMENT
11 bags
1 bags
1 bags
1 bags
CEMENT
4.50
1.60
2.50
0.27
1.50
0.16
1.00
0.11
1.00
0.11
1.00
0.11
bags
bags
bags
bags
bags
bags
bags
bags
bags
bags
bags
bags
CEMENT
SAND
60 cft
0.60 cum
60 cft
0.60 cum
60 cft
0.60 cum
60 cft
0.60 cum
SAND
3.75 cft
0.11 cum
3.75 cft
0.11 cum
SAND
40 cft
0.40 cum
20 cft
0.06 cum
15 cft
0.05 cum
8 cft
0.25 cum
11 cft
0.03 cum
8 cft
0.25 cum
SAND
METAL 25 mm METAL 20 mm
(1)
()
65 cft
20 cft
0.65 cum
0.20 cum
65 cft
20 cft
0.65 cum
0.20 cum
65 cft
0.65 cum
65 cft
0.65 cum
SHINGLE
2.50 cft
0.07 cum
2.50 cft
0.07 cum
RUBBLE
METAL 12
mm ()
20 cft
0.20 cum
20 cft
0.20 cum
METAL 12 mm
()
7.00 cft
0.20 cum
7.00 cft
0.20 cum
STONE
STONE
GRIT
DUST
5.50 cft
2.50 cft
0.16 cum
0.07 cum
5.50 cft
2.50 cft
0.16 cum
0.07 cum
BRICKS
23X10X7 cm
BRICKS
23X15X9
cm
BRICKS
23X10X7
cm
125 cft
1.25 cum
1000 Nos.
110 Nos.
400 Nos.
45 Nos.
475 Nos.
50 Nos.
145 Nos.
16 Nos.
SANLA
(30 Kg bag)
1.50 bags
0.16 bag
1.20 bags
0.13 bag
1.00 bags
0.11 bag
2.4 bags
0.26 bag
1.90 bags
0.21 bag
1.60 bags
0.17 bag
11.0 cft
0.03 cum
11.0 cft
0.03 cum
11.0 cft
0.03 cum
18 cft
0.06 cum
18 cft
0.06 cum
18 cft
0.06 cum
2.25 bags
17.0 cft
0.24 bag
1.8 bags
0.19 bag
1.5 bags
0.16 bag
0.05 cum
17.0 cft
0.05 cum
17.0 cft
0.05 cum
3.75 bags
28.0 cft
0.41 bag
3.0 bags
0.32 bag
2.5 bags
0.27 bag
0.09 cum
28.0 cft
0.09 cum
28.0 cft
0.09 cum
CEMENT
SAND
1.0 bags
1.11 bags
2.0 bags
0.65 bags
16 cft
0.05 cum
2 cft
0.01 cum
2.0 bags
0.60
0.07
0.60
0.07
0.60
0.07
0.60
0.07
0.60
0.07
0.60
0.07
bag
bag
bag
bag
bag
bag
bag
bag
bag
bag
bag
bag
LIME
(30 kg/bag)
2.0 bags
0.2 bags
150 Nos.
16 Nos.
125 Nos.
14 Nos.
WHITE
CEMENT
5 kg
0.55 kg
2 kg
0.65 kg
16 cft
43 Nos.
2 kg
0.22 bags
0.05 cum
5 Nos.
0.221 kg
0.75 bags
18 cft
0.08 bags
1.25 bags
0.13 bags
2.50 bags
0.27 bags
3.5 bags
0.38 bags
3.5 bags
0.38 bags
0.06 cum
16 cft
0.05 cum
16 cft
0.05 cum
16 cft
0.05 cum
CEMENT
6.0 bags
0.65 bags
2.0 bags
0.2
2.0
0.2
2.0
0.2
bags
bags
bags
bags
bags
TILES
40 Nos.
4 Nos.
150 Nos.
16 Nos.
required tukda
required tukda
420 Nos.
45 Nos.
SAND
30 cft
0.09 cum
BRICKBAT
30 cft
0.09 cum
LIME
(30 kg/bag)
2 kg
0.22 kg
4.0 bags
0.43 bags
5.0 bags
0.50 bags
30 cft
0.09 cum
45 cft
0.14 cum
30 cft
0.09 cum
30 cft
0.09 cum
1.20 bags
0.13 bag
APPROXIMATE
QUANTITY OF
MATERIAL
REQUIRED
0.02
50 Nos. Sheets
0.22
50 sheets of
plywood x 65
50 Nos. Sheets
3250 rft
50 sheets of
plywood x
19.82
2500 sft x
0.24
232 sqm x
0.79
600 rft
beam bottom
x 0.5
183 rft
beam bottom
x 1.65
2500 sft x
0.16
232 sqm x
1.72
300 Nos.
2500 x 0.4
1000 rft
232 x 1.31
305 rm
2500 x 0.16
400 Nos.
232 x 1.72
400 Nos.
2500 x 0.020
50 kg
232 x 0.22
50 kg
2500 x 0.006
15 litres
232 x 0.065
15 litres
2500 x 0.08
200 Nos.
232 x 0.86
200 Nos.
NSUMPTION OF STEEL
on built-up area
990 rm
600 rft
183 rm
300 Nos.
400 Nos.
400 Nos.
125 kg
13.5 kg
25 kg
2.07 kg
0.05kg/sft
0.20kg/sft
0.10kg/sft
0.45kg/sft
0.65kg/sft
0.70kg/sft
0.05kg/sft
0.05kg/sft
2.25kg/sft
PROX. QTY.
PER
. M.
APPROX. QTY.
PER
SR. NO.
SQ. FT.
1.00 cft
0.15 cft
0.95 cft
ITEM
SQ. M.
9 Flooring
a) MM tile
b) skirting
SQ. FT.
0.75 sqm
0.82 rm
0.75 sft
0.25 rft
0.7 sft
c) W.C. / Bath
0.05 sqm
0.05 sft
0.9 sft
d) Dado
0.20 sqm
0.20 sft
3.2 sft
10 Waterproofing
0.30 sqm
0.30 sft
2.5 sft
0.62 sft
11 Door Frames
12 Windows
0.17 sqm
0.14 sqm
0.17 sft
0.14 sft
BRICKS
23X10X7
cm
145 Nos.
16 Nos.