You are on page 1of 29

Central Washington University

Outside Plant Communications Distribution


Design Guide
(Revision 1.1)

May 25, 2001

Conley Engineering, Inc.


Consulting Electrical Engineers

TABLE OF CONTENTS

TABLE

OF

CONTENTS

LIST OF FIGURES...............................................................................................II
LIST OF TABLES................................................................................................. II
INTRODUCTION.................................................................................................. 1
DOCUMENT INTENT................................................................................................................... 1
TYPE OF CONSTRUCTION............................................................................................................ 2
NEW CONSTRUCTION
OVERBUILD CONSTRUCTION
BASIC CONSTRUCTION

DESIGNER QUALIFICATIONS AND DESIGN STANDARDS.........................................4


DESIGNER QUALIFICATIONS......................................................................................................... 4
DESIGN STANDARDS.................................................................................................................. 4
REFERENCES , STANDARDS , AND CODES
MANUFACTURERS
DEVIATION FROM STANDARDS

DESIGN CONSIDERATIONS..................................................................................7
OVERVIEW.............................................................................................................................. 7
TELECOMMUNICATIONS OUTSIDE PLANT MASTER PLAN
DEFINITION OF TERMS
PATHWAY SYSTEM..................................................................................................................... 9
GENERAL DESIGN CONSIDERATIONS
UNDERGROUND CABLE VAULTS (UCVS)
DUCTS (CONDUIT )
DUCTBANKS
COMMUNICATIONS MEDIA......................................................................................................... 19
GENERAL DESIGN CONSIDERATIONS
GROUNDING AND BONDING
MEDIA TYPES
TERMINATION
LABELING AND ADMINISTRATION
ENTRANCE FACILITIES.............................................................................................................. 23
GENERAL DESIGN CONSIDERATIONS
GROUNDING AND BONDING

APPENDICES.................................................................................................... 24
APPENDIX 1 CONSTRUCTION DRAWINGS..................................................................................24
APPENDIX 2 BIBLIOGRAPHY AND REFERENCES..........................................................................25

2016 Conley Engineering, Inc.

FIGURES AND TABLES

LIST

OF

FIGURE
FIGURE
FIGURE
FIGURE
FIGURE
FIGURE

LIST

1
2
3
4
5
6

OF

TABLE
TABLE
TABLE
TABLE

1
2
3
4

FIGURES

TWO-LEVEL HIERARCHICAL STAR TOPOLOGY.....................................7


TYPICAL UCV DETAIL......................................................................10
SPLAYED DUCT ENTRY/EXIT............................................................11
CORRECT AND INCORRECT DUCT ENTRY/EXIT FROM A UCV..............11
DUCT ENTRANCES IN A UCV...........................................................15
TYPICAL 4X4 DUCTBANK DETAILS...................................................18

TABLES

REFERENCES, STANDARDS, AND CODES.............................................5


DEFINITION OF TERMS.......................................................................8
DUCT TYPES AND USAGE.................................................................13
DUCTBANK MINIMUM SEPARATIONS.................................................16

2016 Conley Engineering, Inc.

ii

INTRODUCTION

INTRODUCTION
The purpose of this document is to provide CWU staff, as well as consulting
architects, engineers, and designers working for CWU with a guide for the
design of outside plant (OSP) communications distribution systems that
accurately reflect CWU and industry standards in effect as of this publication.
This document was originally produced (in 1999) based on industry standards
and practices, as well as the telecommunications practices in use at that
time at CWU. Under the current revision, it has been updated to reflect the
methods, materials and standards that have been used to for providing
telecommunications services to the existing Residence Hall facilities. The
updated document also reflects changes in industry practice as of this
publication.
Outside plant communications distribution systems designed for CWU are
expected to support and integrate voice, data, and video communications
with common media (fiber optic and unshielded twisted pair (UTP) copper
cable).
In general, it is the responsibility of the outside plant communications
distribution designer to coordinate with the other designers on a project
(architecture, electrical, mechanical, etc.) to ensure that other systems are
both compatible with and complementary to the communications cabling
system. CWUs design philosophy is that it is critical to coordinate between
disciplines during the design phase of a project, rather than attempting to
make adjustments in the field during construction.

DOCUMENT INTENT
This document addresses outside plant communications distribution system
design as it relates to:

Pathway System underground cable vaults (UCVs), ductbanks, ducts


(conduits), etc.
Communications Media fiber and UTP copper media.
Building Entrance Facilities

This document is not intended to serve as a Master Specification nor for


stand-alone use on design build projects it is to be used in conjunction with
the CWU Outside Plant Communications Distribution System Master
Specification. This document should serve as a guide for making standards
compliant design decisions which, in due course, will be reflected in a system
specification based upon the CWU Outside Plant Communications Distribution
System Master Specification. In addition to specifications for a
telecommunications project, plan drawings and schematic diagrams will also
need to be produced by the designer. The drawings should conform to the
guidelines contained in this document.

2016 Conley Engineering, Inc.

INTRODUCTION
In addition, this document is not intended to replace or detract from the
Customer-Owned Outside Plant Design Manual (CO-OSP) produced and
distributed by BICSI. 1 Rather, this document is to be used in conjunction with
the CO-OSP in order to reinforce selected CO-OSP content as well as highlight
any differences between CO-OSP and CWU standards.

TYPE

OF

CONSTRUCTION

Throughout this document, reference will be made to three types of


construction: new, overbuild and basic construction. Construction of a new
outside plant communications distribution system as well as the addition to
and/or modification of an existing outside plant communications distribution
system are considered to be included in these construction projects.
Tradeoffs between design standards and practicality will many times be
dependent upon the type of construction. Different design approaches may
be warranted given differing types of construction.
Where the type of construction is applicable to the current discussion, a
superscripted circular number, such as this
CONSTRUCTION REFERENCE

, will make reference next to the text. This


This is an example of a reference
number refers to a comment in a special
to the text at the left
Construction Reference box to the right of
the text (see the example at right).
The three types of construction are defined below. These definitions are
applicable to the purposes of this document only.
NEW CONSTRUCTION

New construction is defined as construction that results in a new (or new


portion of an existing) outside plant communications distribution system.
For the most part, new pathway will be constructed and new
communications media will be installed in the pathway. A recent CWU
project with components that typify this type of construction is:

Electrical Utility Upgrade Phase 1 (1999-2001)

OVERBUILD CONSTRUCTION

Overbuild construction is defined as construction which may include


demolition and/or abandonment of existing pathway and communications
media, reuse of existing pathway for installation of new communications
media, and the addition of new pathway and/or media to existing pathway
and/or media. Common terms referring to this type of construction
include expansion, renovation, remodel, addition, and retrofit, among
others.

The CO-OSP is probably the first widely distributed industry reference text for the design of standards
compliant outside plant communications distribution systems.
2016 Conley Engineering, Inc.

INTRODUCTION
BASIC CONSTRUCTION

Basic construction is defined as construction that includes reuse of


existing distribution pathway for the installation of new communications
media. Demolition of existing communications media may be involved as
well. In general, basic construction is focused on the installation of new
communications media with no (or very minor) modifications made to the
existing pathway system. Recent CWU projects with components that
typify this type of construction are:

Campus Fiber Optic Backbone (FOB) (1999-2001)


Residential Network (RESNET) (1999-2001)

2016 Conley Engineering, Inc.

DESIGNER QUALIFICATIONS AND DESIGN STANDARDS

DESIGNER QUALIFICATIONS

AND

DESIGN STANDARDS

DESIGNER QUALIFICATIONS
It is required that all outside plant communications distribution system
designs executed on the behalf of CWU be designed by a Registered
Communications Distribution Designer (RCDD) as certified by BICSI 2. This
means that the design project shall be managed under the direct supervision
of an RCDD on the consultants staff. Project related communications
between CWU and the consultant shall be mainly through the RCDD.
In addition to the RCDD certification, it is desirable that the RCDD have the
following qualifications:
Professional Engineer (P.E.) in the electrical engineering field
RCDD/LAN certification from BICSI
MCSE certification from Microsoft Corporation 3
In addition, the RCDD shall have the following qualifications:

The RCDD shall demonstrate a minimum of 5 years of experience in the


design of outside plant communications distribution systems. Experience
not directly related to the design of outside plant communications
distribution systems, such as sales and/or marketing, project
management, or installation experience, is not acceptable.
The RCDD shall demonstrate that he/she has designed or has had
personal design oversight of a minimum of five projects similar in size and
construction cost to the current CWU project.
The RCDD shall not be affiliated with any manufacturer associated with
the communications distribution system industry.
The RCDD shall be completely familiar and conversant with the standards
listed below.

DESIGN STANDARDS
REFERENCES, STANDARDS,

AND

CODES

CWU standards are based upon the Customer-Owned Outside Plant Design
Manual (CO-OSP) produced by BICSI, the Telecommunications Distribution
Methods Manual (TDMM) also produced by BICSI, ANSI/TIA/EIA and ISO/IEC
standards, and NEC codes, among others.
It is required that the Designer be thoroughly familiar with the content and
intent of these references, standards, and codes and that the Designer be
2

BICSI, 8610 Hidden River Pkwy, Tampa, FL 33637-1000 USA, Tampa, FL 33612-6415; 1-800-242-7405;
www.bicsi.org
3
Microsoft Corporation, One Microsoft Way, Redmond, WA 98052-6399, (425) 882-8080;
www.microsoft.com/mcse
2016 Conley Engineering, Inc.

DESIGNER QUALIFICATIONS AND DESIGN STANDARDS


capable of applying the content and intent of these references, standards,
and codes to all outside plant communications system designs executed on
the behalf of CWU.
Listed in the table below are references, standards, and codes applicable to
outside plant communications systems design. If questions arise as to which
reference, standard, or code should apply in a given situation, the more
stringent shall prevail. As each of these documents are modified over time,
the latest edition and addenda to each of these documents is considered to
be definitive.
TABLE 1 REFERENCES, STANDARDS,
Standard/Reference
BICSI CO-OSP
BICSI TDMM
BICSI TCIM
TIA/EIA - 758
TIA/EIA - 568
TIA/EIA - 569
TIA/EIA - 606
TIA/EIA - 607
TIA/EIA - 455
TIA/EIA - 526
IEEE 802.3 (series)
NEC
NESC
L&I
OSHA Codes

AND

CODES

Name/Description
BICSI Customer-Owned Outside Plant Design Manual
BICSI Telecommunications Distribution Methods
Manual
BICSI Telecommunications Cabling Installation Manual
Customer-Owned Outside Plant Telecommunications
Cabling Standard
Commercial Building Telecommunications Cabling
Standard
Commercial Building Standard for Telecommunication
Pathways and Spaces
The Administration Standard for the
Telecommunications Infrastructure of Commercial
Buildings
Commercial Building Grounding and Bonding
Requirements for Telecommunications
Fiber Optic Test Standards
Optical Fiber Systems Test Procedures
Local Area Network Ethernet Standard, including the
IEEE 802.3z Gigabit Ethernet Standard
National Electric Code, NFPA
National Electrical Safety Code, IEEE
Department of Labor and Industries, Electrical Section,
RCW 19.28, WAC 296-46 and WAC 296-401A, Interim
Printing
Occupational Safety and Health Administration, Code
of Federal Regulations (CFR) Parts 1910 - General
Industry, and 1926 - Construction Industry, et al.

Also of use to the Designer are the references listed in Appendix 2


Bibliography and References.
MANUFACTURERS

In addition to the standards listed above, CWU has selected several


manufacturers of communications cabling infrastructure products. These
manufacturers and their products are identified in the CWU Communications
Distribution System Master Specification. The outside plant communications
distribution designer is required to incorporate only these manufacturers into
2016 Conley Engineering, Inc.

DESIGNER QUALIFICATIONS AND DESIGN STANDARDS


the design, and to design a communications distribution system that will be
suitable for the use of products from these manufacturers.
DEVIATION

FROM

STANDARDS

It is not the intent of CWU to rigidly impose standards on every aspect of an


outside plant communications system design. Each design is unique and
each design may be subject to situations in which deviations from the
standards are warranted.
If the Designer feels that deviation from a given standard is warranted, the
Designer shall submit a written deviation request to CWU. The request will,
at a minimum, indicate the standard from which there is a proposed
deviation, the substitution being proposed in place of the standard, the
reason the request is being made, and an explanation of the justifications
(economic, technical or otherwise) for the deviation. The Designer may,
upon written approval from CWU, incorporate the design deviation into the
overall design. CWU approval is required on a project-by-project basis. The
Designer should not assume that a deviation approval for one project means
that the deviation will necessarily be approved for a subsequent project.

2016 Conley Engineering, Inc.

DESIGN CONSIDERATIONS

DESIGN CONSIDERATIONS

OVERVIEW
This section highlights design considerations of particular importance to
CWU. It also discusses differing CWU standards given the type of
construction (new, overbuild, or basic) for a particular project, as well as CWU
standards that may differ from the standards listed previously in Table 1.
TELECOMMUNICATIONS OUTSIDE PLANT MASTER PLAN

Each design performed on the behalf of CWU shall conform to and integrate
with the CWU Telecommunications Pathway Outside Plant Master Plan. This
plan provides a 10-year strategy for the use and expansion of the
underground telecommunications pathways on the CWU campus.
The Master Plan calls for the campus to be subdivided into nine areas called
Building Clusters. Each building within a cluster is connected with
telecommunications pathway to a building within the cluster that will serve
as the Building Cluster Hub. The Building Cluster Hubs are in turn connected
with telecommunications pathway to the Communications Center. This
configuration is based upon a TIA/EIA standard two-level hierarchical star
topology such as that shown in Figure 1, below.
FIGURE 1 TWO-LEVEL HIERARCHICAL STAR TOPOLOGY

Comm
Center

Building
Cluster
Hub

Building

Building

Building
Cluster
Hub

Building

Building

Building

Building
Cluster
Hub

Building

Building

Building

Building

Please refer to the Master Plan Overview drawing in the CWU


Telecommunications Pathway Outside Plant Master Plan for more detail.
DEFINITION

OF

TERMS

The table below defines and clarifies common terms that will be used
throughout this section it is expected that the Designer is already familiar
with these terms.

2016 Conley Engineering, Inc.

DESIGN CONSIDERATIONS
TABLE 2 DEFINITION
Term
Backbone
Backfill

Base

Bedding

Building Cluster
Building Cluster Hub
Communications
Center

Duct
Ductbank
Entrance Facility
(EF)

Underground Cable
Vault
(UCV)

Manholes

Handholes/Pullholes

OF

TERMS

Definition
Pathway or cable between buildings.
Earth material used specifically for filling and grading
excavations back to a finished state. Backfill is placed on
top of the bedding surrounding encased ductbanks and
direct-buried conduits.
Earth materials used specifically to level and grade an
excavations subgrade for the subsequent placement of
encased ductbanks, direct-buried conduit, and UCVs.
Base material is placed on top of the subgrade and
beneath the bedding surrounding encased ductbanks,
conduits, or UCVs.
Earth material used specifically for filling excavations.
Bedding is placed around encased ductbank, conduits, or
UCVs. Bedding is placed on top of the Base (if a Base
exists) and beneath the backfill.
A group of buildings connected via pathway in a star
topology to a Building Cluster Hub (see below).
A building that serves as a pathway hub for the buildings
in its Building Cluster.
A centralized building on the CWU campus that serves as a
pathway hub for the Building Cluster Hubs. The
Communications Center, Building Cluster Hubs, and
individual buildings are connected together with pathway
in a two-level hierarchical star topology as shown in Figure
1.
A single enclosed raceway (conduit) used for the routing of
cables.
An arrangement of multiple ducts, usually in tiers.
The interface between the premises (in-building)
communications distribution system and the outside plant
communications distribution system and services (such as
the public telephone network or inter-building (campus)
backbone cabling.)
The EF consists of protection hardware, connecting
hardware and cable and equipment necessary to connect
premises distribution to outside plant distribution.
An underground cable vault (part of an underground duct
system) used to facilitate placing, connectorizing, and
maintaining telecommunications cables and associated
equipment. UCV collectively refers to manholes,
handholes, and pullholes.
A large underground cable vault in which it is expected
that a person can completely enter to perform work.
A small underground cable vault in which it is expected
that a person cannot completely enter to perform work.
Handholes/pullholes are used for the placement of cable
only. Splicing and/or equipment are not permitted in

Many of these definitions are excerpted or modified from original definitions from: BICSI, Customer-Owned
Outside Plant Design Manual; BICSI, Telecommunications Distribution Methods (TDMM) Manual; and TIA/EIA
758, Customer-Owned Outside Plant Telecommunications Cabling Standard
2016 Conley Engineering, Inc.

DESIGN CONSIDERATIONS
handholes/pullholes.

2016 Conley Engineering, Inc.

DESIGN CONSIDERATIONS

PATHWAY SYSTEM
The pathway system (underground cable vaults, ducts, and ductbanks) is the
foundational component of the outside plant communications distribution
system. A pathway system designed with foresight provides for ease of
administration, maintenance, future expansion, and replacement of cabling
as technology changes. A well-designed pathway system contributes more
to reducing the total cost of ownership of an outside plant communications
distribution system than does any other single component.
This section describes design considerations for the pathway system that are
of particular concern to CWU. The Designer is expected to refer to the TIA/EIA
standards and the BICSI CO-OSP and TDMM for other and more specific
design criteria and detail.
GENERAL DESIGN CONSIDERATIONS

As discussed previously, the design of pathway shall conform to the TIA/EIA


standard two-level hierarchical star topology as defined in the CWU
Telecommunications Pathway Outside Plant Master Plan.
Prior to design, the Designer is expected to meet with CWU and review
CWUs requirements for the project. Items to review should include proposed
pathway routing, aesthetic requirements, long range plans that CWU has
regarding new and existing buildings, paved areas, opens spaces, etc. which
could be affected by the design, and any unique requirements specific to the
project.

CONSTRUCTION REFERENCE
This list is primarily applicable to
New and Overbuild Construction.
However, items 1 and 2 are
applicable to Basic Construction as
well.

After the requirements review, a thorough and detailed field investigation


shall be conducted. The field survey shall include, but should not be limited
to:
1. A thorough review of existing records and a comparison of these records
against actual field conditions.
2. Notation of the condition, suitability, and diagrams showing the locations
of existing pathway, UCVs, and building entrances likely to be used
during the course of the project.
3. Documentation of where the telecommunications pathway will require
coordination with pathway used for other utilities.
4. Investigate adverse ground conditions and obstructions (such as
buildings, trees, etc.) and any significant changes in grade along the
proposed pathway.
5. Notation of the existing paving types and the type of material used as a
base below the paving along the proposed route.
2016 Conley Engineering, Inc.

10

DESIGN CONSIDERATIONS
6. Notation of the most desirable locations for new underground cable vaults
(UCVs) and ductbank routes, as well as any alternative locations and
routes.
Detailed design should commence only after the field survey has been
conducted and reviewed by CWU.
The discussion below focuses on specific design considerations for the major
components of the pathway system: UCVs, ducts, and ductbanks.
UNDERGROUND CABLE VAULTS (UCVS)

UCVs provide accessible space in an outside plant pathway system for the
pulling, placing, and splicing of cables, as well as for maintenance and
operations equipment. UCVs are also used to segment the pathway system
into lengths compatible with standard reel lengths for outside plant cable and
to conform to maximum pathway lengths as defined in the TIA/EIA standards.
Underground cable vaults consist of manholes and handholes/pullholes (see
Table 2, above). UCVs are also sometimes referred to as maintenance holes.
Typically, manholes are installed for main ductbanks (i.e. ductbanks used for
routing large portions of the telecommunications system backbone), and
handholes/pullholes are installed for subsidiary ductbanks (i.e. ductbanks
serving small clusters of buildings or a single building).
FIGURE 2 TYPICAL UCV DETAIL
MANHOLE COVER WITH "COMMUNICATIONS" EMBOSSED IN CASTING.
STENCIL MANHOLE NUMBER IN 3" LETTERS ON COVER

RESTORE FINISHED GRADE TO EXISTING


CONDITION (TURF, CONCRETE, OR ASPHALT).
FOR TURF AREAS, PROVIDE NEW SOD.

IMPORTED BACKFILL
(95% COMPACTED)

UNDISTURBED EARTH

GROUT ENVELOPE
(TYPICAL)

4'-0"

CONDUIT
( TYPICAL )
CONDUIT END BELL
FLUSH MOUNTED
(TYPICAL)

6" TO 1'-0"

GRAVEL
EXCAVATION BOTTOM
(SMOOTH TO +/- 1")

MINIMUM 6"

4'-8"

MINIMUM 6"

The quantity of duct entrances in a UCV should be sized for both immediate
and future requirements. Adequate capacity for future duct entrances will
mitigate the need for future wall breakouts. Additionally, UCVs configured for
splayed duct entrances (rather than center entrances) are preferred. Splayed
duct entry facilitates racking and minimizes bending of the communications
2016 Conley Engineering, Inc.

11

DESIGN CONSIDERATIONS
cable. An example of splayed duct entry/exit is shown in the figure below.
FIGURE 3 SPLAYED DUCT ENTRY/EXIT
UC V

4 " C O N D U IT
(T Y P IC A L )

P L A N V IE W

When designing duct entry and exit from a UCV, it is desirable to have ducts
enter and exist from opposite ends of the UCV. If possible, ducts entering
the sidewalls of a UCV should be avoided, given that sidewall entry may
reduce overall racking space, may cause minimum cable bend radii to be
exceeded, can complicate (or hinder) future cable maintenance, and can
increase construction costs during cable installation.
However, CWU recognizes that sidewall duct entry may be necessary or even
desirable at times. If sidewall duct entry is necessary, the Designer shall
ensure that ducts enter and exit at diagonally opposite corners rather than at
endwall or sidewall midpoints. The Designer is to ensure that the design of
the endwall and sidewall duct entry in a UCV will in no way hinder the proper
installation and maintenance of the cable using the ducts. Refer to the Figure
below for more detail regarding this requirement.
FIGURE 4 CORRECT

C O M M U N IC A T I O N S

AND INCORRECT

DUCT ENTRY/EXIT

C O M M U N IC A T IO N S

FROM A

UCV

4 " C O N D U IT
(T Y P IC A L )
UC V
(T Y P IC A L )

C O R R E C T (P R E F E R R E D )

C O R R E C T (A C C E P T A B L E )

C O M M U N IC A T I O N S

C O M M U N IC A T IO N S

C O M M U N IC A T IO N S

IN C O R R E C T

IN C O R R E C T

IN C O R R E C T

2016 Conley Engineering, Inc.

12

DESIGN CONSIDERATIONS
Other important design considerations for UCVs are:

A UCV shall not be shared between telecommunications and any other


utility (such as electrical). In no instance are joint-use UCVs permissible.
All UCVs should be equipped with provisions for grounding and bonding,
struts for racking, pulling eyes, and a sump.
In general, powered devices shall not be installed in UCVs.
Top slabs for UCVs shall be flush with the ground.

Design considerations unique to each type of UCV (manholes and


handholes/pullholes) are discussed
CONSTRUCTION REFERENCE
below.
The following discussion of
manholes and handhole/pullholes is
primarily applicable to New and
Overbuild Construction.

MANHOLES

Manholes are used for pulling, placing, and splicing cables, and for
providing accessible space for cable maintenance and operation
equipment.
Ductbank depth, obstructions, and other utility pathways may necessitate
placement of a manhole below normal depth. If this is the case, the roof
of the manhole shall be placed at normal depth and riser extensions shall
be used to increase the depth of the manhole. By doing so, the need for a
deep collar (neck) will be eliminated. Additionally, lighting and ventilation
can be maintained at a normal level. If a deep collar is unavoidable and
the depth of the collar will exceed 24 inches, the Designer shall obtain
written permission from CWU and ensure that the collar is equipped with
permanent galvanized steps (rungs).
Diamond plate hinged or removable covers are not acceptable for
manholes.
For reference purposes, a typical manhole size is 5 wide x 8 long x 7
high (exterior dimensions). Actual size may be as much as a foot or more
larger in any direction.
HANDHOLES/PULLHOLES

Handholes/pullholes are used to facilitate cable placement in a pathway


system. Handholes should not be used in place of manholes or for
splicing cables.
The primary use of a handhole/pullhole is to segment the pathway
system. A handhole should be used if it is shown that a manhole is not
required and if one or more of the following conditions exist:

When the bends in a section of duct will exceed 180-degrees (see


Ducts, below).
When the length of the section of duct will exceed the TIA/EIA standard

2016 Conley Engineering, Inc.

13

DESIGN CONSIDERATIONS
maximum length (see Ducts, below).
For reference purposes, a handhole/pullhole is defined to be an
underground cable vault sized 4 wide x 4 long x 4 high (exterior
dimensions) or smaller.
DUCTS (CONDUIT)

CWU has standardized on 4 conduits for telecommunications ducts, with the


following two exceptions:

Ducts containing cables that serve the Blue Light Emergency Telephones
shall be 1 conduit.

Ducts containing fiber optic cabling serving the power distribution system
metering equipment shall be 1 conduit.
The type of conduit to be used is dependent upon the application as shown in
the following table.
TABLE 3 DUCT TYPES
Conduit Type
Schedule 40 PVC
Schedule 80 PVC
Rigid Galvanized
Steel
PVC Coated Steel

AND

USAGE
Usage
Encased in concrete
Direct-buried
Exposed
Direct-buried, Transitions at building
entrances

If the design utilizes any existing pathway, the existing ducts must be proven
during design in order to ensure that the selected pathway is clear and
serviceable. Proving the ducts prior to construction will not only aid the
Designer in selecting the appropriate pathway for use, it will also minimize
unexpected (and costly) problems or delays during construction. Acceptable
proving methods are, in order of preference:

Pushing/pulling a test mandrel through the duct


Blowing/pushing/pulling a ball through the duct
Pulling on a previously installed pull cord and observing free movement on
both ends. This method does not prove that a duct is adequate for a
given number of cables, however it does suggest that the duct is probably
not completely obstructed.

It is left to the Designer to select the appropriate method for proving a given
duct. The proving method should be selected only after determining the
quantity and size of the communications media to be placed in the duct and
after reviewing the condition of the duct in the field.
DUCT LENGTH

The length of each ductbank segment should be as long as possible


(without exceeding the TIA/EIA maximum distance, see below) in order to
minimize the use of intermediary UCVs, cable splices, and labor during
installation of the communications media. In general, longer contiguous
2016 Conley Engineering, Inc.

14

DESIGN CONSIDERATIONS
ducts equate to lower construction costs.
The maximum duct length (between
UCVs and/or buildings) permissible
according to the TIA/EIA 758 standard
is 600 ft. Duct sections exceeding this
distance will require the installation of
intermediate UCVs.

CONSTRUCTION REFERENCE
This requirement may be waived
at times for New and Overbuild
Construction given the following
conditions: the duct run is straight;
the Designer can demonstrate that
the pulling tension of a typical
communications cable making use
of the duct will not be exceeded
during installation.

The requirements of TIA/EIA 569A, Figure C.5-2 should be met when


calculating maximum section
lengths.

In addition, as the number of bends in a pathway increases, the maximum


length of the pathway will decrease, due to cable pulling tension
constraints. Longer runs will therefore tolerate fewer bends. In general,
the Designer should base the pathway system design on an initial
segment length budget of approximately 300 feet, and designed in as
straight a line as possible.
BENDS

The Designer shall ensure that bends consist of a single arc of a


minimum15-foot radius. If a smaller radius is absolutely necessary, the
radius shall be no less than 10 times the internal diameter of the duct. An
individual bend shall not exceed 90 degrees.
Factory manufactured conduit bends should be used wherever possible.
The use of 90-degree elbows or condulets (LBs) is not permissible.
In order to minimize the sidewall pressure exerted on cable sheaths at
bend points, the Designer should ensure that bends with the most severe
radii occur at the beginning (feed end) of a duct section, rather than in the
middle or at the pulling end.
A duct section may have no more than
CONSTRUCTION REFERENCE
the equivalent of two 90-degree bends (a
This requirement may be waived
total of 180 degrees) between pull
for Basic Construction. Older

points. The 180-degree maximum shall


existing pathway may, at times,
exceed this rule. The Designer
include kicks and offsets.
In addition,
should note on the Construction
two 90-degree bends separated by less
Documents where such conditions
exist.
than 10 feet are not permissible. Where
it is not possible to construct a section of
duct within the 180-degree bend maximum, intermediary UCVs must be
installed.
DUCT ENTRANCES IN UCV S

OR

BUILDINGS

Duct entrances in a UCV should be as perpendicular as possible. Where


2016 Conley Engineering, Inc.

15

DESIGN CONSIDERATIONS
this is not possible, the Designer should ensure that the Contractor
installs a smooth inner radius of grout between the UCV and the conduit
bell, as shown in the figure below:
FIGURE 5 DUCT ENTRANCES

IN A

UCV

PULLHOLE
WALL

PULLHOLE
WALL

BELL

BELL

NON SHRINK
GROUT

NON SHRINK
GROUT

CONCRETE ENCASEMENT

HORIZONTAL CONCRETE
ENCASED DUCT
PENETRATION INTO A UCV

PULLHOLE
WALL
SMOOTH
INNER-RADIUS
OF GROUT
BELL
NON SHRINK
GROUT

GROUT ENVELOPE
( 12" MINIMUM DEPTH )

HORIZONTAL DUCT
PENETRATION INTO A UCV

GROUT ENVELOPE
( 12" MINIMUM DEPTH )

ANGLED DUCT
PENETRATION INTO A UCV

Ducts should ideally enter UCV end walls at a point approximately halfway
between the floor and the roof. However, where the total number of ducts
penetrating a UCV (or building entrance) is significantly less than the
capacity of the UCV (or building entrance), the ducts should enter at the
lower level in order to ensure that upper space is reserved for future duct
entrances.
The Designer shall ensure that the relative position of a duct (with respect
to the side walls) is consistent as it enters and exits a UCV. Additionally, a
duct exiting a UCV in a given position should enter the next UCV in the
same relative position.
Ducts that enter from a horizontal orientation should immediately off-load
into a horizontal raceway system.
Concrete encased ducts entering a
CONSTRUCTION REFERENCE
building shall transition to PVC coated
If in some extreme case, CWU
allows ductbank to be constructed
rigid steel using one 10 stick of conduit .
without concrete encasement, the
The purpose of the PVC coated rigid steel
transition to PVC coated rigid steel
should occur a minimum of 10
is to reduce the chance of shear damage
prior to the building.
due to settling on either side of the
junction between the ductbank and the
building footing. If (in the opinion of a structural engineer) rigid steel is
unnecessary, then this requirement could be waived, following the
deviation request process described above.
DUCTBANKS

Ductbank consists of an arrangement of multiple ducts constructed in tiers.


Typical ductbank arrangements are 2, 3, and 4 ducts wide by 2, 3, or 4 ducts
high.
CWU has standardized on ductbanks
constructed of PVC conduits encased in
concrete, with full-length reinforcement and
formed sides.
2016 Conley Engineering, Inc.

CONSTRUCTION REFERENCE
Ducts used for Blue Light

Emergency Telephones are not


subject to this requirement.

16

DESIGN CONSIDERATIONS
In general, direct-buried conduit ductbanks are not permissible, unless
extenuating circumstances warrant. Should the use of direct-buried PVC
conduit ductbank be warranted, the Designer should ensure that all PVC
bends are encased in concrete.
Where ductbank passes under paved surfaces capable of supporting motor
vehicle traffic, conduit should transition to PVC coated rigid steel a minimum
of 10 outside the footprint of the paved surface.
The quantity of ducts to install within a ductbank will vary greatly depending
upon the application. However, with the increasing migration from copper
cable to fiber optic cable on the CWU campus, it is expected that the
requirement for duct space will decrease over time.
In keeping with this expectation and with the recommendations made in the
CWU Telecommunications Pathway Outside Plant Master Plan, typical
ductbank configurations are shown below. It should be noted that these
typical configurations should serve as a guideline only. The quantity of ducts
in a duct bank should meet the needs of the application at hand and provide
for future expansion capability.

Buildings up to 100,000 sq. ft.: 2 ducts


Buildings 100,000 sq. ft. to 300,000 sq. ft.: 4 ducts
Buildings larger than 300,000 sq. ft.: 6 ducts
Buildings serving as a Building Cluster Hub: 6 ducts
Pathway between Building Cluster Hubs and the Communications Center:
4 ducts

Unless specifically noted above, a typical ductbank will contain four ducts,
arranged 2 wide x 2 high.
In general, ductbank used for
CONSTRUCTION REFERENCE
telecommunications pathway should not be
This may not be possible for
Overbuild Construction.
shared with other utilities. Budgetary
constraints, space limitations, and various
obstructions can make this difficult to achieve at times. Should shared
ductbank be a necessity (rare situations requiring a deviation request), the
Designer should ensure that adequate separation exists between duct used
for telecommunications and duct used for other utilities. Refer to the table
below for minimum separation distances.
TABLE 4 DUCTBANK MINIMUM SEPARATIONS
Structure
Power or other
duct
Pipes (gas, oil,
water, etc.)
5

Minimum Separations5
Refer to the latest edition of the NEC/NESC (at the time
of this writing: 3 inches if in concrete, 12 inches if in
well tamped earth)
Refer to the latest edition of the NEC/NESC (at the time
of this writing: 12 inches if parallel, 6 inches if crossing)

Measured from outside to outside

2016 Conley Engineering, Inc.

17

DESIGN CONSIDERATIONS
Should future circumstances warrant, CWU might desire to convert concreteencased communications ductbank (not direct-buried ductbank) into
electrical power ductbank. The Designer should therefore ensure that
communications ductbank specifications (conduit spacing, reinforcement,
grounding requirements, etc.) conform to NEC requirements for power
ductbank.
If building ducts are constructed concurrently with and in the same duct bank
with a main duct run, place building ducts (subsidiary/lateral ducts) on top of
the ducts for the main run. This is economically advantageous, makes the
building ducts more accessible, and affords some top protection for the main
ducts.
Drain slope should exist at all points of the ductbank to allow drainage and
prevent the accumulation of water. A drain slope of per foot is desirable if
possible. If not possible due to inadequate natural slope or long duct runs, a
drain slope of 3 per 100 feet is acceptable. If no other option exists, provide
a drain slope by sloping the first half of the ductbank up towards the
midpoint, and then down from the midpoint to the end (sometimes referred
to as a center crown). Drain slope requirements shall be identified in the
Contract Documents they shall not be left up to the discretion of the
Contractor.
Details for a typical four-conduit ductbank (2 wide x 2 high) are shown in the
figure below:

2016 Conley Engineering, Inc.

18

DESIGN CONSIDERATIONS
FIGURE 6 TYPICAL 4X4 DUCTBANK DETAILS

RESTORE FINISHED GRADE TO EXISTING CONDITION.


FOR TURF AREAS, PROVIDE 4" TOPSOIL AND NEW SOD.
IF EXISTING GRADE IS ASPHALT OR CONCRETE,
SAWCUT EXISTING GRADE A MINIMUM 6" WIDER
THAN TRENCH WIDTH

6"

6" WIDE METALLIC WARNING TAPE


IF EXISTING GRADE IS TURF OR EARTH,
USE IMPORTED EARTH BACKFILL (95% COMPACTED).
IF EXISTING GRADE IS ASPHALT OR CONCRETE,
USE GRAVEL BACKFILL
MINIMUM 18"

UNDISTURBED EARTH

CONCRETE DUCTBANK
(SEE DETAIL)
1'-7"
IMPORTED BEDDING
(90% COMPACTED)

4"

SAND BASE
TRENCH BOTTOM
(SMOOTH TO +/- 1")

6"

1'-7"

#2 GROUND WIRE

6"

TRENCH AND ENCASEMENT DETAIL


CONCRETE ENCASED DUCTBANK
SECTION VIEW (END)

#5 REBAR (LONGITUDINAL), CONTINUOUS ALONG FULL


LENGTH OF DUCTBANK, TYPICAL OF 4. PROVIDE
INTERMEDIATE BARS ALONG TOP, BOTTOM, AND SIDES
FOR EVERY 3 CONDUITS HIGH AND 3 CONDUITS WIDE.
MAINTAIN 1'-6" O.C. FOR INTERMEDIATE BARS. DOWEL
REBAR 6" INTO UCV AND FOUNDATION WALLS AND
GROUT WITH EPOXY GROUT.

3 1/2"

4 1/2"

#5 REBAR HOOPS AT CONSTRUCTION


JOINTS AND AT 60" O.C.

3"
4" CONDUIT (4 1/2" O.D.)
(TYPICAL - SIZE, NUMBER,
AND ARRANGEMENT
MAY VARY)

4 1/2"

3 1/2"

CONDUIT SPACERS
5-0"' O.C. (TYPICAL)

7 1/2"
3 1/2"

RESTORE FINISHED GRADE TO EXISTING CONDITION.


FOR TURF AREAS, PROVIDE 4" TOPSOIL AND NEW SOD.

4 1/2"

7 1/2"
3"

4 1/2"

3 1/2"

DUCTBANK DETAIL
CONCRETE ENCASED DUCTBANK
SECTION VIEW (END)

6"
6" WIDE METALLIC
WARNING TAPE
IF EXISTING GRADE IS
TURF OR EARTH, USE
IMPORTED EARTH BACKFILL
(95% COMPACTED).
IF EXISTING GRADE IS
ASPHALT OR CONCRETE,
USE GRAVEL BACKFILL

MINIMUM 18"

3 1/2"

4 1/2"

CONDUIT SPACERS
5'-0" O.C. (TYPICAL)

3"

GRAVEL BEDDING
(TYPICAL)

1'-7"

4 1/2"

4" CONDUIT (4 1/2" O.D.)


(TYPICAL - SIZE, NUMBER
AND ARRANGEMENT
MAY VARY)

2"
4"

SAND BASE
TRENCH BOTTOM
(SMOOTH TO +/- 1")

CONDUIT
COUPLER
(TYPICAL)
6" VERTICAL STAGGER

3'-0" MINIMUM CONDUIT STUB

#5 REBAR HOOPS AT CONSTRUCTION


JOINTS AND AT 5'-0" O.C.

#5 REBAR (LONGITUDINAL), CONTINUOUS ALONG FULL


LENGTH OF DUCTBANK, (TYPICAL OF 2). PROVIDE
INTERMEDIATE BARS ALONG TOP, BOTTOM, AND SIDES
FOR EVERY 3 CONDUITS HIGH AND 3 CONDUITS WIDE.
MAINTAIN 1"-6" O.C. FOR INTERMEDIATE BARS. DOWEL
REBAR 6" INTO UCV AND FOUNDATION WALLS AND
GROUT WITH EPOXY GROUT.

TRENCH AND ENCASEMENT DETAIL


CONCRETE ENCASED DUCTBANK
SECTION VIEW (SIDE)

2016 Conley Engineering, Inc.

19

DESIGN CONSIDERATIONS

COMMUNICATIONS MEDIA
The communications industry is now witnessing a convergence of
technologies. Voice, data, and video are all capable of utilizing the same
type of communications media (i.e. singlemode fiber). Additionally, these
technologies are also beginning to converge into a single technology capable
of combining voice, data, and video signals into a common signal transmitted
down a single path.
Accordingly, and as discussed in the CWU Telecommunications Pathway
Outside Plant Master Plan, CWU has standardized on singlemode fiber optic
media as the media of choice for all future, voice, data, and video backbone
systems. Copper media (for voice and various signaling systems) as well as
multimode fiber optic media (for existing data network equipment and
various building and power metering systems) will continue to be installed
and used, but will be used less extensively as time progresses.
As the voice, data, and video systems begin to make use of the singlemode
fiber on campus, existing copper and multimode fiber media can be removed.
Additionally, singlemode fiber media is significantly smaller than the copper
media used on campus. These two factors combined will tend to ease the
shortage of duct space on campus.
This section defines design considerations for outside plant communications
media (cable and connecting hardware) that are of particular concern to
CWU. The Designer is expected to refer to the TIA/EIA standards and the
BICSI CO-OSP and TDMM for other and more specific design criteria and
detail.
GENERAL DESIGN CONSIDERATIONS

Following is a list of general items to consider when selecting a


communications media system:

Direct-buried cable and aerial cable should not be used. If extenuating


circumstances require the use of these cable types, the Designer must
obtain approval from CWU in writing prior to finalizing the Construction
Documents.
Fiber optic cable shall not be spliced.
CONSTRUCTION REFERENCE
The CWU Telecommunications Pathway
This may not be possible for
Overbuild and Basic Construction if
Outside Plant Master Plan has been
the Designer must make use of the
designed to minimize the amount of fiber
existing fiber optic outside plant
cable.
splices necessary in the outside plant.
Where cables are to be pulled through UCVs without splicing, the duct
selected for cable installation shall be at the same elevation as it enters
and exits the UCV. Changes in duct selections, especially in elevations,
should be avoided to ensure that no damage occurs to the cable sheaths
and that pulling tensions are kept as low as possible.

2016 Conley Engineering, Inc.

20

DESIGN CONSIDERATIONS
Ducts are to be assigned during the course of design, not during
construction. Duct assignments must be approved by CWU prior to the
release of Construction Documents.
If a multiple ducts are available for use, the bottom ducts should be used
first in order to facilitate future cable placement.
Communications cabling entering a building should be routed so as not to
block or obstruct the planned usage or expansion of any other building
that occupies or will occupy the space.
For long cable runs, the longest cable reel lengths obtainable shall be
used. Splices should not be used except where cable reel lengths are
exceeded. If splices are used, the Designer should ensure that:
1. The cable ends to be spliced have permanent slack loops with
sufficient length that the cable can be removed from the UCV and
reach a satisfactory work surface for splice activities.
2. The splice location (UCV or EF) should have enough space for storing
slack cable after the splice is completed.
50-foot service loops (cable slack) shall be provided for each end of a
cable terminating in a building.
Service loops (cable slack) shall be provided for fiber optic cabling that
enters a building in the UCV nearest the building entrance. The length of
cable in the service loop shall be sufficient that if a cable break occurs
between the UCV and the building, sufficient slack cable would be
available in the UCV to reterminate the fiber optic cabling at the existing
patch panel, without the use of a splice.
Communications backbone cables serving
CONSTRUCTION REFERENCE
different systems (i.e. voice, data, video)
For New Construction, use
shall be segregated6. Segregation can
different ducts for cables serving
different systems. For Overbuild
occur by using different ducts (the most
and Basic construction, the use of
desirable solution), or it may occur by
innerduct is an acceptable
alternative although inductive
using separate innerducts within the
interference (see below) may be an
same duct.
issue. Sharing of ducts can
produce undesirable inductive
interference, can damage the
facilities by subjecting the cable to
abrasion and tensional stress if the
facilities are pulled in at different
times, and may present
coordination problems between the
various trades involved.

Duct fill shall conform to the TIA/EIA standards and the NEC.
For copper media, indoor dry splice enclosures shall be installed prior to
terminating the copper cable on building entrance protectors.
Cables are to be tagged (labeled) at locations near where they enter a
UCV from a duct and near where they enter a duct to leave a UCV.

GROUNDING

AND

BONDING

CWU has standardized on considering all locations exposed for grounding,


bonding, and electrical protection purposes. Cables with an outer metallic
6

Segregation is desirable in order to ensure that when maintenance work is performed on a backbone cable
serving a specific system, work on the cable will not disrupt the functionality of the backbone cables serving
other systems
2016 Conley Engineering, Inc.

21

DESIGN CONSIDERATIONS
sheath shall be bonded at each UCV. Bond all other cables with dielectric
components whenever a splice is made.
When a splice occurs in a UCV, metallic sheath components in the cable(s)
and splice enclosures must be bonded to the UCV grounding system.
Additionally, cable shield bond continuity shall be maintained. Bonds should
be made with #6 AWG solid copper wire not more than 20 long. If over 20,
the conductor must be sized according to NEC requirements.
Cables should be grounded as close to the entrance of the buildings as
possible.
INNERDUCT

The use of innerduct for subducting purposes is strongly encouraged


(although it may not be applicable to every situation). CWU has standardized
on three configurations for subducting a 4-inch conduit with innerduct:

Three 1 innerducts
Two 1 and one 1 innerduct
Four 1 innerducts

It is left to the Designer to select the most appropriate configuration for


subducting based upon the conditions of the duct and the application.
Innerduct shall not be filled with cable beyond 50% capacity.
MEDIA TYPES

CWU recognizes three types of communications media for the campus


backbone system:

Category 3 UTP (copper) used for voice, analog signaling, and various
metering applications
Singlemode Fiber Optic used for data, video, and increasingly, voice
applications
62.5/125 m Multimode Fiber Optic used primarily for data applications
and various metering applications.

As discussed above, CWU has standardized on singlemode fiber for its voice,
data, and video applications. However, copper and multimode fiber media
will still be in use for some time.
The type and quantity of communications media to install will vary greatly
depending upon the application. In keeping with the recommendations made
in the CWU Telecommunications Pathway Outside Plant Master Plan, typical
communications media configurations are shown below. It should be noted
that these typical configurations should serve as a guideline only. The type
and quantity of communications media shall be determined on a case-bycase basis by the Designer, ensuring that it meets the needs of the
application at hand and provides for future expansion capability.

2016 Conley Engineering, Inc.

22

DESIGN CONSIDERATIONS
BETWEEN BUILDING CLUSTER HUBS
BUILDINGS

Singlemode Fiber:

Multimode Fiber:
Copper:

12-Strands (4 Data,
4 Video, 4 Spare)

BETWEEN

THE

Hybrid fiber cable is permitted in


Residence Halls only. CWU uses 12
SM/12MM hybrid fiber optic cable
for these applications.

AND THE

COMMUNICATIONS CENTER

48-Strands
24-Strands
0-Pairs

COMPUTER CENTER

Singlemode Fiber:
Multimode Fiber:
Copper:

CONSTRUCTION REFERENCE

24-Strands (4 Data, 2 Access Control, 4 Fire Alarm, 2


HVAC Control, 2 Power Metering, 10 Spare)
25-Pairs

BETWEEN BUILDING CLUSTER HUBS

Singlemode Fiber:
Multimode Fiber:
Copper:

AND

AND THE

COMMUNICATIONS CENTER

96-Strands
48-Strands
0-Pairs

TERMINATION

Separate fiber patch panels shall be


provided for multimode and singlemode
fiber optic cabling. Fiber optic media shall
be terminated on separate fiber patch
panels depending upon fiber type.

CONSTRUCTION REFERENCE
For Residence Halls served by

hybrid fiber: A single patch panel


may be used to terminate both
types of fiber in the hybrid cable
separate fiber patch panels are not
required in this case.

Copper media shall always be terminated on building entrance protectors.


LABELING

AND

ADMINISTRATION

It is the responsibility of the Designer to ensure that the Construction


Documents clearly define the labeling requirements and that the Contractor
properly labels all outside plant media during construction. Inadequate or
incomplete labeling is not acceptable. Refer to the Master Specification
Section 16741 - Outside Plant Communications Circuits for more information.

2016 Conley Engineering, Inc.

23

DESIGN CONSIDERATIONS

ENTRANCE FACILITIES
This section defines design considerations for entrance facilities that are of
particular concern to CWU and specific to the outside plant communications
distribution system.
The Designer is expected to refer to the TIA/EIA standards and the BICSI COOSP and TDMM for other and more specific design criteria and detail. In
addition, the Designer is expected to reference the CWU Inside Plant
Communications Distribution Design Guide for more detail regarding the
design of telecommunications spaces, including entrance facilities and
equipment rooms.
GENERAL DESIGN CONSIDERATIONS

Following is a list of general items to consider when designing pathway and


communications media into a building entrance facility:

In general, a structural engineer should approve all structural changes or


penetrations into a building.
The entrance facility shall not be more than 50 from the actual entrance
into the building. In order to comply with NEC requirements, not more
than 50 of an outside plant cable can be exposed between the entrance
conduit stub and the cable termination point. If more than 50 is required,
the cable7 must be routed in rigid metallic conduit. Fire-rated tape wrap is
not acceptable.
Ducts entering a building shall transition to PVC coated rigid steel conduit
a minimum of 10 feet prior to entering the building.
Ducts shall enter the entrance facility parallel to the backboard to be
used. Ducts shall not enter perpendicular to the backboard surface, which
could cause cables to be bent sharply.
Below grade ducts should extend 4 above finished floor.
Building entrance protectors (primary protectors) should be provided for
all OSP copper cables and should support both primary (overvoltage) and
secondary (overcurrent) protection.

GROUNDING

AND

BONDING

CWU has standardized on considering all locations exposed for grounding,


bonding, and electrical protection purposes.
The ground terminal for building entrance protectors should be bonded
directly to the electrical power ground.

Some types of fiber media are now indoor/outdoor rated and are therefore not subject to this
requirement.
2016 Conley Engineering, Inc.

24

APPENDICES

APPENDICES

APPENDIX 1 CONSTRUCTION DRAWINGS


Construction drawings should be thoroughly and accurately marked. Listed
below are items that should be included on construction drawings, dependent
upon the type of project8:

Routing of the pathway system, including ductbanks and UCVs.


Physical locations of obstructions, including UCVs, ductbanks, buildings,
roads, poles, existing underground utilities.
Duct configurations indicating duct sizes and types between UCVs and
between UCVs and buildings.
Duct contents indicating cable assignments.
UCV and building cable racking diagrams (elevations) indicating the
positions of all existing and new cables and splice enclosures.
Backboard/entrance facility elevations within buildings.
Pair sizes, gauges, and types of copper cables.
Strand counts and types of optical fibers.
Drain slope requirements
Labeling
Phasing (if required)
Staging

Much of the following list was excerpted from RUS Bulletin 1751F-644 Underground Plant Construction

2016 Conley Engineering, Inc.

25

APPENDICES

APPENDIX 2 BIBLIOGRAPHY

AND

REFERENCES

AMP, Planning & Installation Guide


BICSI, Customer-Owned Outside Plant Design Manual
BICSI, Telecommunications Distribution Methods Manual
CWU, Telecommunications Pathway Outside Plant Master Plan
CWU, Outside Plant Communications Distribution System Master
Specification
CWU, Premises Communications Distribution System Master Specification
CWU, Premises Communications Distribution Design Guide
IEEE, National Electrical Safety Code (NESC), 1997 Edition
NEC, National Electrical Code (NEC), 1999 Edition
OSHA, Code of Federal Regulations (CFR) Parts 1910 - General Industry, and
1926 - Construction Industry, et al
RUS, Bulletin 1751F-643 Underground Plant Design, 1998
RUS, Bulletin 1751-644 Underground Plant Construction, 1998
RUS, Bulletin 1751-815 Electrical Protection of Outside Plant, 1998
Siecor, Siecor Standard Recommended Procedures for Installation, 1998
TIA/EIA 758, Customer-Owned Outside Plant Telecommunications Cabling
Standard
TIA/EIA 568A, Commercial Building Telecommunications Cabling Standard
TIA/EIA 569A, Commercial Building Standards for Telecommunications
Pathways and Spaces
TIA/EIA 606, Administration Standards for the Telecommunications
Infrastructure of Commercial Buildings
TIA/EIA 607, Commercial Building Grounding and Bonding Requirements for
Telecommunications

2016 Conley Engineering, Inc.

26

You might also like