Professional Documents
Culture Documents
Functional Matrix
Functional
Organization
Projectfullymanaged
byfunctionalmanagers
ProjectMatrix
ProjectTeam
Balanced Matrix
Organization
Projectfullymanagedby
projectteammanager
Director of
Doctoral Program
Accounting
Department Chair
Larry
Zelda
Diane
Marketing
Department Chair
Curly
Bob
Barby
Finance Department
Chair
Moe
Gloria
Leslie
Became
Still
Study Data
Classification of 547 respondents (64% response rate)
30% project managers or directors of project mgt programs
16% top management (president, vice president, etc.)
26% managers in functional areas (e.g., marketing)
18% specialists working on projects
Industries included in studies
14% pharmaceutical products
10% aerospace
10% computer and data processing products
others: telecommunications, medical instruments, glass products,
software development, petrochemical products, houseware goods
Organizational structures:
13% (71): Functional organizations
26% (142): Functional matrix
16.5% (90): Balanced matrix
28.5% (156): Project matrix
16% (87): Project team
Controlling
Cost
Ave (SD)
Meeting
S chedule
Ave (SD)
Technical
Performance
Ave (SD)
Overall
Results
Ave (SD)
Functional
Organization
71
1.76 (.83)
1.77 (.83)
2.30 (.77)
1.96 (.84)
Functional Matrix
142
1.91 (.77)
2.00 (.85)
2.37 (.73)
2.21 (.75)
Balanced Matrix
90
2.39 (.73)
2.15 (.82)
2.64 (.61)
2.52 (.61)
Project Matrix
156
2.64 (.76)
2.30 (.79)
2.67 (.57)
2.54 (.66)
Project Team
87
2.22 (.82)
2.32 (.80)
2.64 (.61)
2.52 (.70)
Total Sample
546
2.12 (.79)
2.14 (.83)
2.53 (.66)
2.38 (.70)
10.38*
6.94*
7.42*
11.45*
Organizational Structure
F-statistic
Scheffe Results
*Statistically significant at a p<0.01 level
Summary of Results
Project structure significantly related to project success
New development projects that used traditional functional organization
had lowest level of success in controlling cost, meeting schedule,
achieving technical performance, and overall results
Projects using either a functional organization or a functional matrix had
a significantly lower success rate than the other three structures
Projects using either a project matrix or a project team were more
successful in meeting their schedules than the balanced matrix
Project matrix was better able to control costs than project team
Overall, the most successful projects used a balanced matrix, project
team, or--especially--project matrix
WHAT a company
communicates.....
HOW a company
communicates.....
How is knowledge
transferred?
Personality Compatibility
Subcontractor
Personality
Corporate
Personality
Project
Individual
Personality
Subcontracting Issues
What part of project will be subcontracted?
n What type of bidding process will be used? What type of
contract?
n Should you use a separate RFB (Request for Bids) for
each task or use one RFB for all tasks?
n What is the impact on expected duration of project?
n Use a pre-qualification list?
n Incentives? Bonus for finishing early? Penalties for
finishing after stated due date?
What is impact of risk on expected project cost?
n
Client reimburses contractor for all audited costs of project (labor, plant,
& materials) plus additional fee (that may be fixed sum or percent of costs
incurred)
Units Contract
u
B=1
Firm 2
$5 M
$7 M
Project Cost
$105 M
$95 M
(inefficient producer)
What is result if Cost Plus Contract (B = 0) used?
n
n
n
WAC 236-48-093: A contract shall be awarded to the lowest responsible and responsive
bidder based upon, but not limited to, the following criteria where applicable and only
that which can be reasonably determined:
1) The price and effect of term discounts...price may be determined by life cycle costing if
so indicated in the invitation to bid
2) The conformity of the goods and/or services bid with invitation for bid or request for
quotation specifications depicting the quality and the purposes for which they are
required.
3) The ability, capacity, and skill of the bidder to perform the contract or provide the
services required.
4) The character, integrity, reputation, judgement, experience, and efficiency of the
bidder.
5) Whether the bidder can perform the contract with the time specified.
6) The quality of performance on previous contracts for purchased goods or services.
7) The previous and existing compliance by the bidder with the laws relating to the
contract for goods and services.
8) Servicing resources, capability, and capacity.
Precedence Networks
Networks represent immediate precedence relationships
among tasks (also known as work packages or activities)
and milestones identified by the WBS
Milestones (tasks that take no time and cost $0 but indicate
significant events in the life of the project)
Two types of networks: Activity-on-Node (AON)
Activity-on-Arc (AOA)
All networks: must have only one (1) starting and one (1)
ending point
Start
End
Precedence Diagramming
Standard precedence network (either AOA or AON) assumes that a successor
task cannot start until the predecessor(s) task(s) have been completed.
Alternative relationships can be specified in many software packages:
Finish-to-start (FS = ): Job B cannot start until days after Job A is
finished
Start-to-start (SS = ): Job B cannot start until days after Job A has
started
Finish-to-finish (FF = ): Job B cannot finish until days after Job A
is finished
Start-to-finish (SF = ): Job B cannot finish until days after Job A
has started
Task A
7 months
Task B
3 months
Start
End
Task C
11 months
ESB=7
LFB=11
Task A
7 months
Task B
3 months
ESEnd=11
LFEnd=11
Start
End
Task C
11 months
ESC=0
LFC=11
Task A
2
Task B
7d
3d
Fri 12/29/00
Tue 1/2/01
S tart
1
0d
End
Task C
4
11d
0d
Wed 1/3/01
Wed 1/3/01
TaskA
14wks
ES START=0
LF START=0
START
ES B=
LFB=
TaskB
9wks
ES C=
LFC=
TaskC
20wks
ES F =
LFF =
ES D=
LFD=
TaskD
12wks
TaskF
9 wks
ES E=
LFE=
TaskE
6 wks
ES END=
LFEND=
END
Path
1
2
3
4
5
Tasks
START-A-D-F-END
START-A-D-E-END
START-B-D-F-END
START-B-D-E-END
START-C-E-END
Expected
Duration (wks)
35
32
30
27
26
LA T EST
Task or
Milestone
Duration
( ti )
S tart Time
(ES i)
Finish Time
S tart Time
Finish Time
(LFi)
START
0
14
9
20
12
6
9
0
0
0
0
0
14
26
26
35
0
14
9
20
26
32
35
35
0
0
5
9
14
29
26
35
0
14
14
29
26
35
35
35
A
B
C
D
E
F
END
Task or
Milestone
Duration
( ti )
Earliest
Start Time
(ES i)
START
0
14
9
20
12
6
9
0
0
0
0
0
14
26
26
35
A
B
C
D
E
F
END
Lastest
Finish Time
(LFi)
0
14
14
29
26
35
35
35
Total Slack
(TSi)
Critical
Task?
Yes
Yes
5
9
No
No
Yes
3
0
No
Yes
Yes
= LFi - ESi - ti
= ESi,min - ESi - ti
= LFi - LFi,max - ti
Minimize END
subject to
STARTj FINISHi
STARTj 0
Gantt Chart
February
ID
Task Name
Start
Task A
Task B
Task C
Task D
Task E
Task F
Task G
Task H
10
Task J
11
End
March
21 24 27
April
10 13 16 19 22 25 28 31
May
12 15 18 21 24 27 30
12 15 18
3/1
Workers[5]
Workers[7]
Workers[3]
Workers[12]
Workers[2]
Workers
Workers[2]
Workers[5]
Workers[6]
5/10
Project Budgeting
The budget is the link between the functional units and the project
Should be presented in terms of measurable outputs
Budgeted tasks should relate to work packages in WBS and
organizational units responsible for their execution
Should clearly indicate project milestones
Establishes goals, schedules, and assigns resources (workers,
organizational units, etc.)
Should be viewed as a communication device
Serves as a baseline for progress monitoring & control
Update on rolling horizon basis
May be prepared for different levels of aggregation
(strategic,
tactical, short-range)
and constraints
TaskA
14wks
ES START=0
LF START=0
START
ES B=0
LFB=14
TaskB
9wks
ES C=0
LFC=29
TaskC
20wks
ES F =26
LFF =35
ES D=14
LFD=26
TaskD
12wks
TaskF
9 wks
ES E =26
LFE=35
TaskE
6 wks
ES END=35
LFEND=35
END
A
B
C
D
E
F
END
Duration
(tj)
0
14
9
20
12
6
9
0
Early Start
Time (ESj)
No. of
No. of
Latest Start Resource A Resource B
Time (LSj)
work ers
work ers
Material
Costs
0
0
0
0
340
800
1,140
0
0
14
26
5
9
14
29
4
3
0
1
12
14
8
0
$
$
$
$
125
200
560
$
$
$
$
8,800
9,600
4,800
400
$
$
$
$
8,925
9,600
5,000
960
26
35
26
35
4
-
10
-
90
7,600
-
7,690
-
19665
Week
2
10
11
12
800
8800
9600
800
8800
9600
800
8800
9600
800
8800
9600
800
8800
9600
800
8800
9600
800
8800
9600
800
8800
9600
800
800
800
9600
9600
9600
19200
38865
19200
58065
19200
77265
19200
96465
19200
115665
19200
134865
19200
154065
19200
173265
10400
183665
10400
194065
10400
204465
Week
10
11
12
1140
800
800
800
800
8925
800
8800
800
8800
800
8800
800
8800
9600
800
8800
9600
800
8800
9600
800
8800
9600
1140
1140
800
1940
800
2740
800
3540
9725
13265
9600
22865
9600
32465
9600
42065
19200
61265
19200
80465
19200
99665
19200
118865
Cumulative Costs
450000
400000
300000
Range of
feasible budgets
250000
200000
150000
100000
50000
Week
Early Start Schedule
33
31
29
27
25
23
21
19
17
15
13
11
0
1
Cumulative Cost
350000
15000
10000
5000
Week
Early Start Schedule
33
31
29
27
25
23
21
19
17
15
13
11
0
1
Weekly Costs
20000
M1
TaskA
2mos
TaskD
8mos
Receive payment
of $3000
TaskC
4mos
START
END
TaskB
8mos
TaskE
3mos
M2
Receive payment
of $3000
LSB=4
LSC=12
TaskA
4wks
TaskB
8wks
TaskC
5wks
2units
Start
LSD=6
LSE=12
LSF=14
TaskD
6wks
TaskE
2wks
TaskF
3wks
30units
End
Demand:
32
10
11
12
30
30
Choose the option that minimizes inventory cost = order cost + holding
cost of raw materials