Practice Final
Practice Final
Practice Final
Name_________________________
____Multiple Choice ________________________
This exam consists of multiple choice and
discussion problems. The discussion
problems are worth 50% of the exam grade.
The multiple-choice part is worth 50% of the
exam grade. For the multiple-choice part,
record your answers on the orange answer
sheet provided. Each multiple choice
question is worth one point.
1. In MS Project, which button do you
click for subordination?
a. Link
b. Indent
c. Resource assign
d. Resource sheet
2. In MS Project, which button do you
click on to indicate precedence?
a. Link
b. Indent
c. Resource assign
d. Resource sheet
3. In MS Project to view project cost
and duration, you must click on
a. Project on the menu bar,
then project information and
then statistics
b. Tools on the menu bar and
then Project information
underneath
c. Functions on the menu bar
and then project statistics
underneath
4. In MS Project, to see the activity
and phase costs you must
a. Change the table in the
Gantt view to cost
b. Insert a cost column in the
entry table next to the
duration column
c. Print a cost report
d. Any of the above
5. For MS Project to cost your project,
it needs to know
a. resource hourly costs
b. activity fixed costs
________________________________
c. stakeholder charges
d. all of the above
e. a and b only
6. In MS Project, durations of phases
containing one or more subordinate tasks,
can be
a. changed manually by the
user
b. specified only by MS Project
c. none of the above
d. a or b only
7. In MS Project, task information is entered
in which view?
a. Resource sheet
b. PERT chart
c. Gantt chart
d. task sheet
8. . In MS Project, the view that exhibits the
network diagram is the _______.
a. Resource sheet
b. PERT chart
c. Gantt chart
d. task sheet
9. In MS Project, the critical path is _____.
a. exhibited in red
b. not calculated or found
c. exhibited on the PERT chart only
d. replaced with the critical chain
10. MS Project makes the following
assumptions regarding time.
a. 8-hour work days
b. no work on Sat. or Sun.
c. flex work schedule
d. all of the above
e. a and b only
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 1
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 2
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 3
a. INITIAL
c. REPEATABLE
d. MEASURED
e. OPTIMIZING
b. DEFINED
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 4
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 5
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 6
c) efficiency
d) load profile
71. The term that refers to the percentage
of available working time that a worker
actually spends working or a machine is
running is
a) utilization
b) capacity
c) efficiency
d) load profile
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 7
MINIMUM
DUR
2
3
2
4
5
3
7
PRECEDENT
ACTIVITY
A
A
B
B, C
C
D,E,F
CRASH
COST/DAY
$400
$200
$200
$300
$100
$400
$100
Create the critical path for the list of tasks above. Use an activity on node representation. For
each node, determine, the ES, EF, LS, LF and place these at their respective corners of each
node.
2. PERT CRASHING (10 points total)
Crash the PERT chart above assuming you have $1500 to spend and that activities cannot be
shorter than their minimum durations. Note that activity A can only be crashed 1 day, while
activity B can not be crashed at all. Try to achieve the greatest reduction in project duration for
the least amount spent.
3. Earned Value Analysis (15 points total)
A/5
B/6
D/7
C/10
In the above, assume tasks A, B & C all started on 11/20/00. Planned durations are in days and are the
numbers in the boxes shown above. A is 60% complete, B is 70% complete and C is 50% complete. So
far, $1800 has been spent on A, $2000 on B and $4000 on C. The daily costs for A, B and C are $400,
$500, $800, respectively. The budget for A is 5*$400 or $2000. Use todays date to determine BCWS.
Assume 5-day work weeks, with no work being done on Saturday or Sunday. For example, the BCWS for
A is $2000. Determine for A, B and C, BCWP, BCWS, ACWP, CV(=BCWP ACWP), SV(=BCWP
BCWS). Complete the following table.
(10 points)
TASK
BUDGET
%COMP
ACWP
BCWS
BCWP
CV
SV
A
B
C
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 8
TOTALS
(5 points) Is the project behind schedule? Over or under budget? Will the entire project be
delayed?
Formulas:
CV = BCWP ACWP
SV = BCWP BCWS
CI = BCWP/ACWP
SI = BCWP/BCWS
Mean = (a + 4m + b)/6, where a is the
optimistic time, m is the most likely time and
b is the pessimistic time
Variance = (b-a)2/36
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 9
42b
43d
44a
45d
46d
47d
48d
49c
50b
51c
52c
53b
54d
55a
56b
57a
58e
59c
60a
61a
62d
63b
64a
65b
66c
67a
68b
69b
70c
71a
Activity On Critical
Path
Time
Start
Yes
3
1
Slack
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 10
2
3
4
5
6
7
B
C
D
E
F
G
no
Yes
no
no
Yes
Yes
3
5
4
7
11
9
4
4
7
9
9
20
6
8
10
15
19
28
Project Completion
Time
=
Number of
Critical Path(s) =
10
4
16
13
9
20
12
8
19
19
19
28
28
1
weeks
6
0
9
4
0
0
2.
PERT CRASHING
{YOU VERY WELL MAY SEE A PROBLEM LIKE THIS}
3.
TASK
A
B
C
TOTALS
13000
7800
This project is behind schedule and over budget
13000
7300
SV
-600
-800
100
-900
0
-4000
-500
ISQS 5343, PRACTICE EXAM III, CLOSED BOOK, CLOSED NOTES page 11
-5700