What is Business Planning and Project Management
View Answer
Answer: (a)
View Answer
Answer: (d)
View Answer
Answer: (b)
View Answer
Answer: (c)
View Answer
Answer: (d)
View Answer
Answer: (d)
Q7. If you add staff, the schedule may shorten & costs will
increase.
a. True
b. False
View Answer
Answer: (a)
View Answer
Answer: (a)
View Answer
Answer: (a)
Q10. In the ___ stage, the project manager along with the team
members draft the outline of the project.
a. Initial stage
b. Final stage
c. Preparation stage
d. None of the above
View Answer
Answer: (c)
Q11. We need to monitor each project as such and make a
program to manage them as a group to take the ___ and be
prepared to manage diversity is called ___
a. All are valid
b. Disadvantages, P3M
c. Advantages, P3M
d. Advantages, P2M
View Answer
Answer: (d)
View Answer
Answer: (a)
View Answer
Answer: (d)
Q14. The review process is not training plan-oriented.
a. True
b. False
View Answer
Answer: (b)
View Answer
Answer: (b)
View Answer
Answer: (b)
Q17. The Key Personnel for each area and list them in the
person column of the project ___
a. Datalist
b. Worksheet
c. Project assignment worksheet
d. Assignment
View Answer
Answer: (c)
View Answer
Answer: (a)
View Answer
Answer: (c)
Qs 20. WBS does not show dependencies.
a. True
b. False
View Answer
Answer: (a)
View Answer
Answer: (a)
View Answer
Answer: (d)
Q23. ___ Specify the objective, products, logistics, roles,
responsibilities, and time frame.
a. Review
b. Quality
c. Agenda for quality review
d. Schedule quality review
View Answer
Answer: (c)
Q24. To check the deviation from the baseline during the Re-
Plan stage schedule ___ is used.
a. Gantt Chart
b. Cost workbook
c. All of the above
d. None of the above
View Answer
Answer: (c)
View Answer
Answer: (d)
Q26. Project state reviews and the decisions taken and actions
planned need to be approved by the ___ management.
a. Top
b. Middle
c. Lower
d. None of the above
View Answer
Answer: (a)
View Answer
Answer: (c)
View Answer
Answer: (a)
Q29. ___ Need to know the information on all projects regarding
progress, problems, resources usage, costs, and project goals.
a. Upper managers
b. Top mgmt.
c. Clerk
d. Executive
View Answer
Answer: (a)
View Answer
Answer: (a)
View Answer
Answer: (d)
Q32. CFT-Cross-functional teams for each project are useful to
find that for each project who will be in charge of the project
and POR-Plan of Record should be prepared for the process and
tools used in the project.
a. True
b. False
View Answer
Answer: (a)
View Answer
Answer: (c)
View Answer
Answer: (a)
Q35. The information is constantly subjected to ___. Many times
Automated systems of quality control of key input data
connected with the project will help in reducing the risk of
over-runs beyond the control of the team.
a. Scientific and analytic processing
b. Scientific processing
c. Calculations
d. All of the above
View Answer
Answer: (a)
Q36. Every project will not have a huge information inflow that
has sorted, classified, distributed, analyzed for the purpose of
decision making and actions taken.
a. Correct
b. Incorrect
View Answer
Answer: (b)
Q37. ISO 9000 And ISO 9000: 2000 are certification standards
mostly for firms where the products have drawings, materials
that are purchased, processes that can be seen, inspected
corrected, and products that can be measured.
a. True
b. False
View Answer
Answer: (a)
Q38. ___ is a process of finding out as to what are the inputs
required, who will do it, how much it costs and how long it will
take.
a. Development Process
b. Project Development Process
c. Life Cycle
d. All of the above
View Answer
Answer: (b)
View Answer
Answer: (d)
View Answer
Answer: (b)
Q41. An amount of time between a predecessor and a successor
task is called ___ and the amount of time between successor
tasks can overlap with its predecessor task called ___
a. Lead time, Lag time
b. Lag time, Lead-time
c. Elapsed time, schedule slippage
d. All of the above
View Answer
Answer: (b)
View Answer
Answer: (b)
View Answer
Answer: (a)
Q45. The project manager and his team committed to any one
project will have to depend upon the various functionaries in
the administrative functions like ___.
a. Human resources
b. Finance
c. Purchase & legal
d. All of the above
View Answer
Answer: (d)
View Answer
Answer: (c)
View Answer
Answer: (c)
View Answer
Answer: (a)
View Answer
Answer: (c)
Q50. The main concept is that a project has a ___ responsible for
all activities. They ___ are derived for a specific set of objectives.
a. Team, time schedules.
b. Member, quality
c. Member cost
d. Team, quality
View Answer
Answer: (a)