You are on page 1of 2

PRE-COMMISSIONING:Pre Commissioning activities A

GENERAL :
Checked level all the equipment and tightend their foundation bolts.
Checked all the motor wiring.
Checked and ensure that all the pipe lines and ducting are supported properly.
Checked all the strainer and valves for its operation.
Spiral agitators inserted in smoke tube
B BOILER :

Connection checked according to P&I digram.


Checked and tighten all the man holes and hand holes.
All flange joint bolts on boiler and steam line checked for mechanical fitness.
Checked and fixed the door ropes properly.
Checked all the mountings and fittings, they are fitted with proper gaskets at their

respective locations.
C.FEED WATER SYSTEM:

Done the Flushing of feed water pipelines.


Mobrey level switch is set the water level extra low, working satisfactory-OK
.Mobery level switches are set for ON, OFF operation of FW Pumps.
The strainers at pump suction are cleaned.

D. ELECTRICAL SYSTEM:

Loop testing of all the instruments and no load test of motor done.
Checked proper earth wires have been connected to all the motors and for

control panel.
Checked for the separate instrument earthing and power earthing connection to

control panel.
Checked the connection of PT, LT & TE (Flue gas).
Checked the voltage for 3 power supply.
Started the drives and checked for its correct rotation.
Set the OLR of all Motors as per their current ratting.
Checked the Trouble free operation of Mobrey (level controller).

E. FLUE GAS CIRCUIT :

Checked the chimney and duct connections and made sure that they are airtight.

Checked Economizer man holes nut bolts tightened


Checked refractory dimensions as per refractory drawing.
Checked the functioning of various dampers provided in the ducting.
All necessary bolts provided on ducting checked for mechanical
Fitness.

You might also like