Professional Documents
Culture Documents
NTPC
NTPC
PROJECT REPORT
Summer Training
PROJECT REPORT
ON
Reporting Officer:
Mr. Bimal Shah
(HR-EDC)
FGUTPS, UNCHAHAR
Submitte
d by:
................
B.Tech(FINAL
YEAR)
Contents
1.
Introduction of NTPC
2.
3.
Production of Electicity
4.
5.
H.T.Switch gear
6.
L.T.Switch gear
7.
8.
D.C. System
9.
Switch Yard
10.
11.
12.
13.
14.
Conclusion
INTRODUCTION OF NTPC
Established in 1975, NTPC the largest power company of the country has been
consistently powering the growth of India.
Driven by its vision to lead, it has charted out an ambitious growth plan of
becoming a 40,000 MW plus company by 2012.
1.
2.
3.
Received highest credit rating AAA by CRISIL and LAAA by ICRA for domestic
bond and international rating for Eurobond.
The Unchahar Thermal Power Plant located about 125kms from Lucknow. It is
nearly 80kms from Allahabad. The nearest railway station is Unchahar. The
project lies in the Raibareilly District in U.P.Water source for this plant is Sarda
Sahayak Canal. The climate conditions are quite favourable with greenery all
around.The installed capacity is 5 X 210 MW.
The Uttar Pradesh Vidyut Utpandan Nigam Limited started this project in 1981.
This was fully owned by the UP Government. Our late Prime Minister Smt. Indira
Gandhi laid down the foundation stone on 27 TH June 1981. The project was
started with an installed capacity of 420MW (2*210).
Faced with financial crunch of its affairs, the Nigam was not able to operate the
plan continuously at optimum capacity. Resulting in loss of generation the UPSEB
was not able to pay charges to NTPC for energy bought. Then it was decided to
sell of the project to NTPC to augment and continue generation of electricity at
full level and commence actives the expansion project in the interest of power
development.
PLF in 1990-91 was 5.5% and at the time of take-over in 1992-93, it was around
20%. NTPC is managing the project well and the result is PLF of 54.9% in 199293, 68% in 1993-94 and more there after. In the year 2000-2001 it has achieved
85.5%. PLF in March 2009 is highest at 100.03%.
It supplies the produced electricity to region of Uttar Pradesh. The project is a
coal-based thermal power project and the main constituents for production is
coal, oil and water.
The NTPC has total installed capacity of 30, 144 Mega Watts and has the goal to
reach the capacity of 40000 Mega Watts. Today it has project at the following
places: -
1.
Singrauli
2.
Rihand
3.
Unchahar
4.
Tanda
1.
Ramagundem
2.
Kayamkulam
1.
Korba
2.
Vindhyanehal
3.
Kawas
1.
Farakka
2.
Kahalgaon
3.
Takher
1.
Dadri coal
2.
Auta
3.
Auraiya
4.
Faridabad
PRODUCTION OF ELECTRICITY
bunkers for sale while the cleaned flue gases pass on through ID Fan to be
discharged up the chimney.
Meanwhile the heat released from the coal has been absorbed by the many
kilometres of tubing which line the boiler walls. Inside the tubes is the boiler
feed water which is transformed by the heat into the steam at high pressure
and temperature. The steam super-heated in further tubes (Super Heater) passes
to the turbine where it is discharged through the nozzles on the turbine blades.
Just the energy of the wind turns the sail of the wind-mill, so the energy of the
steam, striking the blades, makes the turbine rotate.
Coupled to the end of the turbine is the rotor of the generator a large
cylindrical magnet, so that when the turbine rotates the rotor turns with it. The
rotor is housed inside the stator having heavy coils of copper bars in which
electricity is produced through the movement of the magnetic field created by
the rotor. The electricity passes from the stator winding to the step-up
transformer which increases its voltage so that it can be transmitted efficiently
over the power lines of the grid.
The steam which has given up its heat energy is changed back into water in the
condenser so that it is ready for re-use. The condenser contains many
kilometres of tubing through which the colder is constantly pumped. The steam
passing around the tubes looses the heat and is rapidly changed back to water.
But the two lots of water (i.e. boiler feed water & cooling water) must NEVER
MIX. The cooling water is drawn from the river, but the boiler feed water must be
absolutely pure, far purer than the water we drink, if it is not to damage the
boiler tubes. Chemistry at the power station is largely the chemistry of water.
To condense the large quantities of steam, huge and continuous volume of
cooling water is essential. In most of the power stations the same water is to be
used over and over again. So the heat which the water extracts from the steam
in the condenser is removed by pumping the water out to the cooling towers.
The cooling towers are simply concrete shells acting as huge chimneys
creating a draught (natural/mechanically assisted by fans) of air. The water is
sprayed out at the top of towers and as it falls into the pond beneath it is cooled
by the upward draught of air. The cold water in the pond is then circulated by
pumps to the condensers. Inevitably, however, some of the water is drawn
upwards as vapours by the draught and it is this which forms the familiar white
clouds which emerge from the towers seen sometimes.
Why bother to change steam from the turbine back into water if it has to be
heated up again immediately? The answer lies in the law of physics which states
that the boiling point of water is related to pressure. The lower the pressure, the
lower the temperature at which water boils. The turbine designer want as low
boiling point of water as possible because he can only utilize the energy of the
steam when the steam changes back into water he can get NO more work out
of it. So a condenser is built, which by rapidly changing the steam back into
water creates a vacuum. This vacuum results in a much lower boiling point
which, in turns, means he can continue getting work out of the steam well below
100 degree Celsius at which it would normally change into water.
H.T.SWITCH GEAR
For low voltage circuits fuses may be used to isolate the faulty circuit. For
voltage higher than 3.3 kV isolation is achieved by circuit breaker.
1.
After occurrence of fault the switchgears must isolate the faulty circuit as
quickly as possible i.e. keeping the delay to minimum.
2.
It should not operate when an over current flows under healthy condition.
Circuit breaker consists of a fix contact and sliding contact into which moves
a moving contact. The end of moving contact it attached to a handle that can
be manually operated or may operate automatically with the help of
mechanism that has a trip coil energized by secondary of CT. Under normal
condition the secondary of CT is not energized sufficiently to trip the coil but
under false condition the coil is energized fully to operate the trip coil and the
circuit breaker is operated.
1.
2.
The arc interruption process of air- based circuit breaker is based on the natural
deionization of gases by cooling action. The arc is resilient and can be stretched,
and has a resistance, which can be increased both by length and confinement.
Hence the arc resistance is increased by stretching the arc and as the resistance
increases to higher value, the short circuit current drops to zero and arc is
extinguished.
Reducing the phase difference between the system voltage and the short circuit
current assure that when the are current is interrupt at its zero value, the
recovery voltage has very low value at its not allowed to reach 2-3 times the
value of the system peak voltage, a phenomenon that occurs in most cases,
when arc current is interrupted at low power factor.
2.
SERVICE AUXILIARIES- the service auxiliaries are those whose loss would
not affect output.
GENERATOR
SPECIFICATIONS-
KVA
247000
Pf
0.85
Volts of stator
15750
Amperes of stator
9050
Volts of rotor
310
Amperes of rotor
2600
Rpm
3000
Hz
50
Phase
Connection
YY
Coolant
Gas pressure
3.5kg/cm-sq.
Insulation class
EXCITATION SYSTEM-
1.
2.
BRUSHLESS EXCITATION SYSTEM The generators in stage -2(U-3, U4& &U- 5) have this excitation system. It has two exciters, one is main
exciter and other is pilot exciter.
GENERATOR PROTECTION-
1.
2.
3.
4.
5.
6.
7.
TRANSFORMER
TYPE PF TRANSFORMERS
3.
4.
SPECIFICATIONS
KV
15.75/242
MVA
250
Phase
Hz
50
Connections
Y-D 11
Type of cooling
OFAF/ONAF/ONAN
250/150/100
Rated LV (MVA)
250/150/100
242
15.75
597.14/358.29/238.86
9175.15/5505.09/3670.66
50
55
KVA
1150
Phase
Hz
50
Type of cooling
ONAF/ONAN
6600
250
105.9
2655.8
50
55
Potential Transformer
KVA
1000
Phase
Hz
50
Type of Cooling
ONAN
433
87.53
133.5
50
55
D.C SYSTEM
INTRODUCTION:
CHARGING EQUIPMENTS:
The battery charging equipment comprises of trickle charger, quick charger, battery panel, main
distribution board and switch control and signaling board.
CHARGING EQUATION:
1.
DISCHARGING PROCESS
2.
CHARGING PROCESS
BATTERY CHARGER:
2.
TRICKLE CHARGER:
This charger is fed from three-phase ac supply and gives a dc-stabilized output at rated full load
current. The variation of the dc output voltage is limited to +/- 1% for 0 to 100% load variation and
simultaneously ac voltage variation of +/- 10% of frequency variation of +/- 5% from 50 Hz.
The rectification is obtained through full bridge controlled silicon rectifier. Stack comprising of these
SCR and three diode with the surge suppression RC network connected across each SCR and diode.
SWITCH YARD
As we know that electrical energy cant be stored like cells, so what we generate
should be consumed instantaneously. But as the load is not constants therefore
we generate electricity according to need i.e. the generation depends upon load.
The yard is the places from where the electricity is send outside. It has both
outdoor and indoor equipments.
OUTDOOR EQUIPMENTS
1.
BUS BAR
2.
LIGHTENING ARRESTER
3.
WAVE TRAP
4.
BREAKER
5.
6.
CORONA RING
7.
EARTHING ROD
8.
CURRENT TRANSFORMER
9.
POTENTIAL TRANSFORMER
10.
LIGHTENING MASK
11.
LIGHTENING MOOSE
INDOOR EQUIPMENTS
1.
RELAYS
2.
CONTROL PANELS
CIRCUIT BREAKER:
The code for circuit breaker is 52. An electric power system needs some form of switchgear
in order to operate it safely & efficiently under both normal and abnormal conditions.
1.
It extinguishes the arc drawn between the contacts when circuit breaker
opens.
2.
Compressed air
2.
3.
4.
Sulphur hexafluorides
MAKE
TYPE
RATED VOLTAGE
245 KV
1050 KV
25 - 40KA
50HZ
2000 A TO 4000 A
220 V DC
220 V DC
LIGHTING ARRESTER:
It saves the transformer and reactor from over voltage and over currents. We
have to use the lightning arrester both in primary and secondary of transformer
and in reactors.
A meter is provided which indicates the surface leakage and internal grading
current of arrester.
1.
2.
In case of red we first de-energize the arrester and then do the operation.
The code of earthling switch is 5, 6, 7.The work of this equipment comes into
picture when we want to shut down the supply for maintenance purpose. This
help to neutralize the system from induced voltage from extra high voltage.
This induced power is up to 2KV in case of 400 KV lines.
MAKE
S & S POWER
TYPE
MADRAS
VOLTAGE
245 KV
CURRENT
10 KA
415 VOLTS
220 VOLTS
BUS BAR:
1.
.
Current Transformer Diagram
Application:
1.
They are commonly used in metering and protective relaying in the electrical power
industry where they facilitate the safe measurement of large currents, often in the
presence of high voltages.
2.
The current transformer safely isolates measurement and control circuitry from the
high voltages typically present on the circuit being measured.
3.
Current transformers are used extensively for measuring current and monitoring the
operation of the power grid. The CT is typically described by its current ratio from
primary to secondary. Often, multiple CTs are installed as a "stack" for various uses
(for example, protection devices and revenue metering may use separate CTs).
Similarly potential transformers are used for measuring voltage and monitoring the
operation of the power grid.
4.
The device has at least four terminals, a high-voltage terminal for connection to
the high voltage signal, a ground terminal and at least one set of secondary
terminals for connection to the instrumentation or protective relay. CVTs are
typically single-phase devices used for measuring voltages in excess of one
hundred kilovolts where the use of voltage transformers would be uneconomical.
The total number of bays is 22. Out of which we have 3 spare bays.
Bay 1
Bay 2
Bay 3
Bay 4
Bay 6
Bay 7
Bay 8
Bay 9
Bay 10
Bay 11
Bay 12
Bay 13
210 MW Generators -3
Bay 14
Bay 16
210 Mw Generators - 3
Bay 17
Bay 19
Bay 20
Bay 21
Bay 22
Introduction: -
NTPC Unchahar gets its coal supply mainly from Bihar. Now coal is also coming
from Australia, as coal produced in India is of low grade and ash content is more.
The coal being filled in the wagons of the rail reaches plant. The purpose of this
plant is to convey the coal to the bunker in the size not larger than 20mm.It
handles and transports the coal to the bunker from the wagons by passing
through various conveyors, transfer points, crusher houses, etc.
Type of coal: -
In Bottom Open Bottom Release (BOBR) technology the wagons are opened
from side. Pressure is applied by the compressor to open the bottom gates of
the wagon so that the coal gets released over the track hopper and wagon
get unloaded quickly.
The Wagon tippler turns back the wagon at 135-degree angle and the
structure of the wagon tippler is to be very heavy. Upper side of the wagon is
fixed with the many angles for supporting the wagon. When the wagon is
fixed on the Platform then whole platform is turned back and the coal fall
down in the wagon tippler hopper. The unloading time of the Rack is 6hours.
Here the type of the rack is Box C / Box N type.
1.
2.
Vibrating Feeder: The vibrating feeder is used for falling the coal
on the conveyer through Wagon tippler Hoper. Before Wagon tippler Hoper
and Vibrating Feeder the gate is providing to control the flow of the coal.
3.
4.
.
2. PADDLE FEEDER: - They have been installed on conveyors below the
manual
unloading track hopper. There are 6 nos. of paddle feeders, 3 on
each conveyer. 3 Paddle Feeders of each conveyer move to and fro within a
limiting range. The rotating part of the paddle feeder is called as plough
wheel. Plough wheel has 6 blades. By the rotation of the plough wheel, the
coal of the track hopper gets accumulated between the blades and is
discharged on the conveyor below it. The main components of paddle feeder
are:
1.
2.
3.
End limit switch (left or right)-It provides the limiting motion of the
paddle feeders.
4.
5.
1.
2.
Many protecting device provide to the Conveyer--a -Zero Speed Switch, b -Pull Cord Switch, c - Belt Sway Switch
1.
Zero Speed Switch: - The Zero Speed Switch prevents the Conveyer
from over load run. When the conveyer is over loaded, the speed of the
conveyer is reduced and Zero Speed Switch is operated and stops the
conveyer. This device is provided at Head End of the Conveyer. The Zero
Speed Switch is a Centrifugal Switch.
2.
3.
Belt Sway Switch: The Belt Sway Switch also protects the conveyer.
This device is provided on both side of the conveyer. When the conveyer
leaves its way the switch is operated and the conveyer stops. This is also
an automatic protecting device.
5.
1.
rotated and coal moves up and down and collides and hence breaks. The
Rotary Breaker is H.T. 170KW
6.6KV Motor
2.
6.
7.
8.
9.
1.
Stacker: - The Stack is a position (1). When the rack comes, the
excessive coal is send to the stacker through the conveyer from Secondary
Crusher house. The coals are stacked at the Secondary Crusher Coal Heap.
The coal falls down from the stacker through Boom Conveyer.
2.
Reclaimer: The Reclaimer is position (2). When the rack is
not coming and there is a shortage of coal, then reclaiming is to be started
and the coal is lifted from the Secondary Crush Coal Heap and feeded to
the bunker.
3.
Boom Conveyer: The Boom conveyer is a Bi-directional
conveyer. It moves clockwise & anticlockwise direction. In stacking
position, it is moving in clockwise direction and in the reclaiming position
its moving in anticlockwise direction. They are provided with Center Chute
and End Chute on the both end.
4.
Boom hoist: The Boom hoist is a link of the Super Structure.
The hoist is moved up and down. For controlling the up & down position,
limit switch is provided.
5.
Slew drive: The Slew Drive moves at 180-degree. When the
coal is stored on both the side of the track of travel, then the Slew Drive
moves and lifts or fall the coal from Boom Conveyer. For control the
rotation of Slew Drive, the limit switch is provided.
6.
Bucket wheel: - The Bucket Wheel is used when there is a
requirement of the coal. It is a rotary device. It is always rotated in
anticlockwise. In the Reclaiming position, the Center Chute is to be up and
End Chute of the Boom Conveyer is fixed on the conveyer. The Bucket
Wheel rotates; when the Bucket of the wheel is full with coal and the
wheel is rotated the coal fall down on the Boom conveyer and the coal is
send to the Super Structure.
7.
Travel: It is a slip ring induction motor driven system. The
Super Structure moves on it. The normal speed of the Travel is 10 meter /
minute. It moves on its track from one end to other end.
10.
11.
12.
BUNKER: - Here the coal is collected from the tipper and stored. The
capacity of the bunker for Stage-I is 4800MT & Stage-II is 8700MT
DRIVE
(CONVEYOR)
RATINGS (KW)
TYPE-F.L
MCC-1
1
CON1/A/B/C/D
75
NR-3 134A
CON2A/B (P)
125
BKR 228A
CON2A/B (S)
75
NR-3 143A
CON10A/B
125
BKR 228A
PLOUGH WHEEL
22
NR-34A
LONG TRAVEL
5.5
RV-11A
PCRD
2.2
NR-5A
SPEED CONTROL
0.25
RV-0.6
10
B/F-1, (PCH)
22
NR-2,37A
22
NR-2 37A
SF-2 100A
MCC-2
11
B/F-2 (PCH)
12
SUSPENDED MAG.
SF-1 63A
13
LIGHTING BOARD
SF-3 250A
14
DE-1 (SCH)
FSU-2 250A
15
MAG.SEP.(SCR)
SF-2 63A
16
VIB.SCREEN-1,
2(SCH)
37
NR-3 64A
17
CON-3A/B
160
BKR 269
18
CON-4A/B
55
NR-3 96A
19
B/F-4 (SCH)
22
NR-2 37A
MCC-3
20
CBMS-3 TP-8
63A
21
TT-1
63A
22
DE-4(BUNKER)
63A
23
DE-3(BUNKER)
250A
24
CON5A/B
110
BKR 195A
25
CON6A/B
125
BKR 228
26
CON7A/B
90
159A
27
CON8A/B(P)
160
BKR 269
28
CON8A/B(S)
75
BKR 134
29
CON9A/B
90
159A
30
CON12
125
BKR 228A
31
BEETLE
1,2
32
BAGOB TRIPLER-1,2 71
RV-126A
33
VIB.FEEDERS
1,2,3,4
SF-63A
CHARGER 55
STAGE 2
RV-98A
Equipment
Conv14
Conv15
KW
2*95
2*140
Conv16
2*115
Conv17
65
Conv18
160
Conv19
115
Conv20
315
Conv21
140
Conv22
140
Conv23
2*110
Conv24
110
Conv25
110
Conv26
2*115
R.B
160
Crusher
450
STAGE-2
S.No.
Type-F.L
CON14A/B
2*95
161
CON15A/B
2*140
237
CON16A/B
2*115
195
CON17A/B
65
115
CON18A/B
160
269
CON19A/B
115
195
CON20A/B (HT)
315
34
CON21A/B
140
237
CON22
140
237
10
CON23
2*110
182
11
CON24A/B
110
182
12
CON25A/B
110
182
13
CON26
2*115
195
14
R.B
160
269
15
CRUSHER (HT)
450
54
16
35
17
47
18
PADDLE FEEDER
7,8,9,10
45
80
19
S/R-2 BOOM
CONVEYOR
75
127
20
S/R-2 BUCKET
WHEEL
75
127
21
S/R-2 SLEW/TRAVEL
MOTOR 7.5(DC)
22
VGF 1,2,3,4
37
65
23
SWP 1A/B
115
195
24
SWP 2A/B
32
25
SUMP-PUMP
15
TERMS
FULL FORM
CBMS
ILMS
PF
Paddle feeder
TT
Transfer tower
TP
Transfer point
MD
Metal detector
SM
Suspended magnet
RB
Rotary breaker
VGF
RPG
CR
Crusher rotary
RH
Reclaim hopper
VS
Vibrating screen
BF
Belt feeder
FG
Flap gate
TC
Telescopic chute
WT
Wagon tippler
PH
Pent house
PCH
SCH
S/R
Stacker/Reclaimer
CO
Conveyor
CHP
TH
Track hopper
MCC
LCS
PCS
BSS
ZSS
VF
Vibrating feeder
VF.
Vibrating fan
200acrs
13km
13.5km
2800 M.T
5400M.T
400*12=4800 M.T
730*12=8760 M.T
12000 M.T
970acrs
280acrs
Coal import
CCI, BCCL
Water source
Power export
INTRODUCTION: --
Water is required in plant for many purposes like for formation of steam, for
removal of ash, for safety during fire, etc. But the water required for the
formation of steam should be perfectly devoid of minerals because if minerals
are present in the steam and the steam strike the blades of the turbine, then due
to being high in pressure it produces scars or holes on the turbine blades.
1.
Carbon filter
Water taken from the river is first sent to the
carbon filter for the removal of carbon contents in the water.
2.
3.
4.
Mixed bed exchanger And then water is sent to the chamber of mixed
bed exchanger where the remaining ions are removed. This is the last
stage of purification.
COAL CYCLE
C.H.P Plant
Boiler section
1.
Bunker
R.C Feeder
Pulverization mill
2.
Pulverization mill:
to the action of oxygen .Two Types of mill are used in the plant.
1.
Ball mail:
suction. A large drum partly filled with steel balls, is used in this mill .The
drum is rotated slowly while coal is fed in to it .The ball pulverize the coal
by crushing. This type of mill is used in stage-1.
2.
Contact mail:
elements and the primary air fan are mounted on a single shaft. The flow
of air carries coal to the primary stage where it is reduced to a fine
granular state by impact with a series of hammers. This type of mill is
used in stage-2.
WATER CYCLE
D.M Plant
Hot well
C.E.P Pump
1, 2, 3
Derater
Boiler Feed Pump
Heater 5, 6
Feed Regulating station
Boiler Drum.
1. DERATER:
1.
2.
3.
3. ECONOMISER:
2.
Flux gases coming out of the boilers carry lot of heat. An
economizer extracts a part of this heat from the flue gases and uses it for
heating the feed water.
4. DRAFTS SYSTEM:
3.
In forced draft system the fan is installed near the base of the boiler
furnace. This fan forces air through the furnace, economizer, air preheater
and chimney.
4.
In an induced draft system, the fan is installed near the base of
Chimney.
STEAM CYCLE
Boiler Drum
Ring Header
Boiler Drum (Steam chamber)
Super
Heater
H.P Turbine
Repeater
I.P Turbine
L.P Turbine
condenser
1.
BOILER:
Boiler drum consists two chambers water chamber, steam
chamber. Before Entering in super heater the steam is going in to boiler
drum, where the boiler drum filtered the moisture and stored in to water
chamber.
2.
SUPER HEATER:
The function of super heater is to remove the last
traces of moisture from the saturated steam leaving the tube boiler. The
temperature is approx.530 oC.
3.
TURBINE:
Steam turbine converts the heat energy in to mechanical
energy and drives the alternator. The velocity attained during expansions
depends on initial and final heat content of the steam. Turbine having
number of stages in which the pressure drops takes place.
Conclusion
Acknowledgements
First of all I would like to thank Shri Munish Jauhari, Honourable DGM
(EMD),NTPC Unchahar who led the entire team of FGUTP for functioning of
each department in a modernized and techno-commercial atmosphere to make
the project touch such peaking performance.
I would give our special thanks to Mr. Bimal Shah (HR-EDC) and Mr.A.K.Singh (Sr
Engg), for giving his very kind permission to undergo the training programme
under the able guidance of NTPC engineers. We would thank Mr .M V Sathe
(Supdt
Engg.),
Mr.
K.K.Singh
(HT
Switchgear),Mr.K.M.Gupta(HT
Switchgear),Mr.J.K.Sahu (LT Switchgear), Mr.H.Mukherjee (Motor Maintenance),
Mr.Rakesh(Supdt.,Switchyard) & Mr.Verma(CHP) under whose able guidance I
completed my training. All these people were of immense importance regarding
the knowledge and supports for the well furnished equipments. Special gratitude
towards Mr.Ranjeet Prasad Singh who provided us the best moral support which I
was in need for.
I greatly acknowledge the help and the mental strength provided by our entire
family for encouraging me and providing me knowledge & guidance related with
every deptt. of NTPC, FGTUP.
At last I conclude by thanking all the employees of NTPC, FGTUP (both executives
& workers) who helped me in making our training a boon for me.
Mayur
Btech Final Year, Electrical Engineering
Motilal Nehru National Institute of Technology,Allahabad.