You are on page 1of 1

Sheet1

June July August September October November

Item Cost Cost Cost Cost Cost Cost


Project Status 2,200
Permits 19,500
Evans Group 5,000
Larry Paine 750 2,000
Paint & Supplies 2,500 2,500 1,600
Resheathing Materials 1,500
Boom Lift 1,400 1,400 1,400
Paint Labor 4,500 4,500 3,000
Pressure Wash Bldgs 1,200
Roof Contractor Bldg 25,000 25,000 18,500
Alexandra 1,026 2,052 2,052
Irrigation 6,000 6,000 4,000
Electrical Permits 5,200
Josiah Crew 1,993 1,993 1,993
Shoreline & Bob 4,750 4,750 4,750
Pavers 18,000 18,000 12,000
Stonework Labor 2,790 2,790
Termite Bond 2,000 2,000 1,300
Sod & Labor
Electrical Supplies
Electrician 7,041 3,500
Plumbing Supplies
Plumber

2,950 31,926 81,526 74,485 48,543 239,430