You are on page 1of 2

2 Room doors iron 20,000 40,000

1 toilet door 23,000


1 trip of sharp sand 12,500
1050pes of blocks 120 126,000
18 bags of cements (for Screeding /tailing & blocks work) 3500/3450 62,250
Total water (for blacks/tailing & Screeding 3,500
Total block work labour 48,200
Fence excavation 8,000
2 length of y 7 for slabs 3,400 8,500
Labour for carpenter/iron & slab casting 6,000
N337,950
Sister Juliet Work Summary
Tailing Work

23 Square meters of wall tails 1,700 39,100


2 Parks of tails gum 700 1,400
Tailor’s Labour 11,700
N52,200
Plumbing

Total plumbing materials with the additional 335,680


Transport (for plumbing & tiles 8,000
Plumbers labour (fittings & surrounding 45,000
N388,680
N388,680
Screeding

4 drums if 20 liters of Screeding paint 3,100 12,400


1 small drum of 4 liters of Screeding paint 1,000
11 kg of acrylic gum 1,300 14,300
86.6 labour per meter (86.6m) 300 26,000
N53,700
Electrical fittings

Total materials (wires & fittings) 155,200


Electrical Labour 25,000
N180,200
Other Expenditures

2 key cylinders 800 1,600


2 Labors for cleaning of compound (different occasions) 3,500
I gave aluminum man the sum of 7000
1 New key for the kitchen 3,000
Cleaning of soak away & covering 2,000
½ bag of cement (for chamber & soak way covering) 1,800
N18,900

Total income - N 500, 000

Total Expenses - N 1,031,630

Balance Deficit - N 531, 630

Thanks.