Work Done
1. Provider User Login (Sprint1)
• ESD – 10th Jun 2009
• EED - 15th Jun 2009
• ASD - 10th Jun 2009
• AED – 17th Jun 2009
• Estimated hrs – 32
• Actual hrs - 42
• % Effort Variance – 31.2
• % Schedule Variance – 40
• Defect count - 2
– PRIORITY
» High - 2
» Medium - 0
» Low – 0
– SEVERITY
» Crash/ Block - 0
» Major - 0
» Minor - 0
Quality (scale of 1 to 10) – 9
Productivity (scale of 1 to 10) - 9
.© Nihilent 2008
Work Done
2. Admin Login (Sprint2)
• ESD – 6th July 2009
• EED - 9th Jun 2009
• ASD - 6th Jun 2009
• AED - 9th Jun 2009
• Estimated hrs – 32
• Actual hrs - 32
• % Effort Variance – 0
• % Schedule Variance – 0
• Defects count - 2
– PRIORITY
» High - 1
» Medium - 1
» Low – 0
– SEVERITY
» Crash/ Block - 0
» Major - 1
» Minor – 1
Quality (scale of 1 to 10) – 9
Productivity (scale of 1 to 10) - 10
.© Nihilent 2008
Work Done
3. Manage Broadcast Fax(Sprint 3)
• ESD – 04thAug 2009
• EED - 13thAug 2009
• ASD - 04thAug 2009
• AED - 14th Aug 2009
• Estimated hrs – 40
• Actual hrs - 48
• % Effort Variance – 20
• % Schedule Variance –11.1
• Defects count - 25
– PRIORITY
» High - 7
» Medium - 11
» Low – 7
– SEVERITY
» Crash/ Block - 1
» Major - 10
» Minor – 14
Quality (scale of 1 to 10) – 8
Productivity (scale of 1 to 10) - 8
.© Nihilent 2008
Work Done
4. Manage Broadcast Fax(Sprint4)
• ESD – 11th Sept 2009
• EED - 14th Sept 2009
• ASD - 11th Sept 2009
• AED - 14th Sept 2009
• Estimated hrs – 32
• Actual hrs - 32
• % Effort Variance – 0
• % Schedule Variance –0
• Defects count - 21
– PRIORITY
» High - 5
» Medium - 11
» Low – 5
– SEVERITY
» Crash/ Block - 0
» Major - 7
» Minor – 14
Quality (scale of 1 to 10) – 8
Productivity (scale of 1 to 10) - 9
.© Nihilent 2008
Overall Quality and Productivity
Quality (scale of 1 to 10) - 8
.© Nihilent 2008
Back-up
Backup 1 – Srikanth Purma
Backup 2 – Varsha Mulay
.© Nihilent 2008
Other Activities
1. New Joinee Formalities: KT given to Mr. Jaswant and Mr. Rushikesh
Functional KT and Document Repository sharing
MMR PRO Envorment setup.( Installaion and Configuration required softwares.)
Archtecture and Appfuse framework explanation
Manage User usecase code work through.
Req. raised for Mantis and SVN credentials given.
2. Training Conducted: On Appfuse for MMR and MMR PRO New joinees.
3. Build Management : Dev. Testing, System Testing ,UAT Testing EQA Testing
4. Credential Management: I have created credentials for Test Env, Dev Env and UAT Env
.© Nihilent 2008
Team Lead Activities
.© Nihilent 2008
Thank You
.© Nihilent 2008