Name: Srinivasa Rao P

Team: MMR PRO

.© Nihilent 2008
Work Done
1. Provider User Login (Sprint1)
• ESD – 10th Jun 2009
• EED - 15th Jun 2009
• ASD - 10th Jun 2009
• AED – 17th Jun 2009
• Estimated hrs – 32
• Actual hrs - 42
• % Effort Variance – 31.2
• % Schedule Variance – 40
• Defect count - 2
– PRIORITY
» High - 2
» Medium - 0
» Low – 0
– SEVERITY
» Crash/ Block - 0
» Major - 0
» Minor - 0
Quality (scale of 1 to 10) – 9
Productivity (scale of 1 to 10) - 9

.© Nihilent 2008
Work Done
2. Admin Login (Sprint2)
• ESD – 6th July 2009
• EED - 9th Jun 2009
• ASD - 6th Jun 2009
• AED - 9th Jun 2009
• Estimated hrs – 32
• Actual hrs - 32
• % Effort Variance – 0
• % Schedule Variance – 0
• Defects count - 2
– PRIORITY
» High - 1
» Medium - 1
» Low – 0
– SEVERITY
» Crash/ Block - 0
» Major - 1
» Minor – 1
Quality (scale of 1 to 10) – 9
Productivity (scale of 1 to 10) - 10

.© Nihilent 2008
Work Done
3. Manage Broadcast Fax(Sprint 3)
• ESD – 04thAug 2009
• EED - 13thAug 2009
• ASD - 04thAug 2009
• AED - 14th Aug 2009
• Estimated hrs – 40
• Actual hrs - 48
• % Effort Variance – 20
• % Schedule Variance –11.1
• Defects count - 25
– PRIORITY
» High - 7
» Medium - 11
» Low – 7
– SEVERITY
» Crash/ Block - 1
» Major - 10
» Minor – 14
Quality (scale of 1 to 10) – 8
Productivity (scale of 1 to 10) - 8

.© Nihilent 2008
Work Done
4. Manage Broadcast Fax(Sprint4)
• ESD – 11th Sept 2009
• EED - 14th Sept 2009
• ASD - 11th Sept 2009
• AED - 14th Sept 2009
• Estimated hrs – 32
• Actual hrs - 32
• % Effort Variance – 0
• % Schedule Variance –0
• Defects count - 21
– PRIORITY
» High - 5
» Medium - 11
» Low – 5
– SEVERITY
» Crash/ Block - 0
» Major - 7
» Minor – 14
Quality (scale of 1 to 10) – 8
Productivity (scale of 1 to 10) - 9

.© Nihilent 2008
Overall Quality and Productivity
Quality (scale of 1 to 10) - 8

Productivity (scale of 1 to 10) - 9

.© Nihilent 2008
Back-up
Backup 1 – Srikanth Purma
Backup 2 – Varsha Mulay

.© Nihilent 2008
Other Activities
1. New Joinee Formalities: KT given to Mr. Jaswant and Mr. Rushikesh
 Functional KT and Document Repository sharing
 MMR PRO Envorment setup.( Installaion and Configuration required softwares.)
 Archtecture and Appfuse framework explanation
 Manage User usecase code work through.
 Req. raised for Mantis and SVN credentials given.

2. Training Conducted: On Appfuse for MMR and MMR PRO New joinees.

3. Build Management : Dev. Testing, System Testing ,UAT Testing EQA Testing

4. Credential Management: I have created credentials for Test Env, Dev Env and UAT Env

5. Configuration Management: Installation and configuration done for Testing team

6. EQA : MMR PRO Env. Set up for EQA


 Functional KT to EQA team
 MMR_PRO_NEW_EQA blank schema created for EQA testing
 Manage Practice show stopper problem resolved

7. Deployment issues handled: For System testing, UAT and EQA

.© Nihilent 2008
Team Lead Activities

1. The following teams handled by me:


1. Client comments incorporation
1. Vivek
2. Chandrakanth
3. Sheetal and
4. My self

2. System Testing and UAT Bug fixing


1. Abhishek
2. Vijay
3. Amit
4. Jitendra
5. Pallavi
6. Varsha and
7. Priya