You are on page 1of 3

B.

L Kashyap & Sons Ltd


Project : Royal Meenakshi Mall

BACK FILLING QUANTITIES

Depth /
S.No Date Description Length Breadth Quantity BLK SYN Remarks
Height
A WEST
Grid A-D 8.528 1.300 1.350 14.967
Grid D-H 7.710 1.450 1.350 15.092
Grid H-N 7.709 2.100 1.350 21.855
Grid N-Q 5.980 1.800 1.350 14.531
Grid Q-S 5.980 1.500 1.350 12.110
Grid S-X 6.325 1.089 1.350 9.299
25/05/2009 Grid X - AA 5.460 1.400 1.350 10.319
1 to
30/05/2009 Grid AA - AD 11.155 0.985 1.350 14.833
Grid AD - AF 6.610 0.890 1.350 7.942
Grid AF - AH 6.610 0.990 1.350 8.834
Grid AH - AK 6.610 1.300 1.350 11.601
Grid AK - AN 6.610 1.600 1.350 14.278
Grid AN - AX 7.265 1.800 1.350 17.654
Grid AV- BA 6.536 2.200 1.350 19.412
Grid A-D 8.528 2.400 1.950 39.911
Grid D-H 7.710 2.650 1.950 39.841
Grid H-N 7.709 1.900 1.950 28.562
Grid N-Q 5.980 2.250 1.950 26.237
Grid Q-S 5.980 1.900 1.950 22.156
Grid S-X 6.325 1.900 1.950 23.434
01/06/2009 Grid X - AA 5.460 2.300 1.950 24.488
2 to
06/06/2009 Grid AA - AD 11.155 2.300 1.950 50.030
Grid AD - AF 6.610 2.300 1.950 29.646
Grid AF - AH 6.610 1.950 1.950 25.135
Grid AH - AK 6.610 1.925 1.950 24.812
Grid AK - AN 6.610 1.895 1.950 24.426
Grid AN - AX 7.265 2.000 1.950 28.334
Grid AV- BA 6.536 2.200 1.950 28.039
Grid A-D 8.528 2.325 2.500 49.569
Grid D-H 7.710 2.225 2.500 42.887
Grid H-N 7.709 2.200 2.500 42.400
Grid N-Q 5.980 2.600 2.500 38.870
Grid Q-S 5.980 2.425 2.500 36.254
Grid S-X 6.325 2.350 2.500 37.159
08/06/2009 Grid X - AA 5.460 2.500 2.500 34.125
3 to
13/06/2009 Grid AA - AD 11.155 2.350 2.500 65.536
Grid AD - AF 6.610 2.625 2.500 43.378
Grid AF - AH 6.610 2.400 2.500 39.660
Grid AH - AK 6.610 2.650 2.500 43.791
Grid AK - AN 6.610 2.800 2.500 46.270
Grid AN - AX 7.265 2.965 2.500 53.852
Grid AV- BA 6.536 2.900 2.500 47.386
Grid A-D 8.528 3.125 2.000 53.300
Grid D-H 7.710 2.900 2.000 44.718
Grid H-N 7.709 2.800 2.000 43.170
Grid N-Q 5.980 3.025 2.000 36.179
Grid Q-S 5.980 3.100 2.000 37.076
Grid S-X 6.325 3.250 2.000 41.113
15/06/2009 Grid X - AA 5.460 3.000 2.000 32.760
4 to
20/06/2009 Grid AA - AD 11.155 2.995 2.000 66.818
Grid AD - AF 6.610 3.300 2.000 43.626
Grid AF - AH 6.610 3.215 2.000 42.502
Grid AH - AK 6.610 2.950 2.000 38.999
Grid AK - AN 6.610 3.500 2.000 46.270
Grid AN - AX 7.265 3.000 2.000 43.590
Grid AV- BA 6.536 3.485 2.000 45.556
B SOUTH
1 GRID Junction Of BB&BA - 48 5.710 1.700 1.850 17.958
22/06/2009
to
27/06/2009
B.L Kashyap & Sons Ltd
Project : Royal Meenakshi Mall

BACK FILLING QUANTITIES

Depth /
S.No Date Description Length Breadth Quantity BLK SYN Remarks
Height
22/06/2009 GRID 48 - 51 6.735 1.500 1.850 18.690
to GRID 51 - 54 6.625 1.400 1.850 17.159
27/06/2009 GRID 54 - 62 8.000 1.980 1.850 29.304
GRID 62 - 67 5.560 1.560 1.850 16.046
2 GRID Junction Of BB&BA - 48 5.710 1.625 2.350 21.805
29/06/2009 GRID 48 - 51 6.735 1.910 2.350 30.230
to GRID 51 - 54 6.625 1.425 2.350 22.185
04/07/2009 GRID 54 - 62 8.000 1.650 2.350 31.020
GRID 62 - 67 5.560 1.850 2.350 24.172
3 GRID Junction Of BB&BA - 48 5.710 2.355 2.000 26.894
06/07/2009 GRID 48 - 51 6.735 2.178 2.000 29.338
to GRID 51 - 54 6.625 2.500 2.000 33.125
11/07/2009 GRID 54 - 62 8.000 2.200 2.000 35.200
GRID 62 - 67 5.560 1.985 2.000 22.073
4 GRID Junction Of BB&BA - 48 5.710 2.625 1.850 27.729
13/07/2009 GRID 48 - 51 6.735 2.356 1.850 29.355
to GRID 51 - 54 6.625 2.589 1.850 31.731
18/07/2009 GRID 54 - 62 8.000 2.450 1.850 36.260
GRID 62 - 67 5.560 2.900 1.850 29.829
5 GRID Junction Of BB&BA - 48 5.710 3.500 1.200 20.453
20/07/2009 GRID 48 - 51 6.735 2.985 1.200 24.246
to GRID 51 - 54 6.625 3.000 1.200 25.838
25/07/2009 GRID 54 - 62 8.000 3.250 1.200 28.320
GRID 62 - 67 5.560 2.950 1.200 19.682
C SOUTH - EAST
1 GRID 1 - 2 7.725 1.650 1.350 17.207
GRID 2 - 8 9.645 1.900 1.350 24.739
GRID 8 - 11 9.020 2.500 1.350 30.443
GRID 11 - 14 8.935 2.800 1.350 33.774
27/07/2009 GRID 14 - 19 9.005 1.250 1.350 15.196
to
01/08/2009 GRID 19 - 24 10.030 1.900 1.350 25.727
GRID 24 - 28 9.105 2.200 1.350 27.042
GRID 28 - 32 11.135 2.800 1.350 42.090
GRID 32 - 38 9.335 2.600 1.350 32.766
GRID 38 - 42 6.495 1.895 1.350 16.616
2 GRID 1 - 2 7.725 1.925 1.950 28.998
GRID 2 - 8 9.645 1.675 1.950 31.503
GRID 8 - 11 9.020 1.800 1.950 31.660
GRID 11 - 14 8.935 1.990 1.950 34.672
03/08/2009 GRID 14 - 19 9.005 1.990 1.950 34.944
to
08/08/2009 GRID 19 - 24 10.030 1.875 1.950 36.672
GRID 24 - 28 9.105 1.675 1.950 29.739
GRID 28 - 32 11.135 1.560 1.950 33.873
GRID 32 - 38 9.335 1.920 1.950 34.950
GRID 38 - 42 6.495 1.990 1.950 25.204
3 GRID 1 - 2 7.725 2.900 2.500 56.006
GRID 2 - 8 9.645 2.600 2.500 62.693
GRID 8 - 11 9.020 2.500 2.500 56.375
GRID 11 - 14 8.935 2.980 2.500 66.566
10/08/2009 GRID 14 - 19 9.005 2.500 2.500 56.281
to
15/08/2009 GRID 19 - 24 10.030 2.960 2.500 74.222
GRID 24 - 28 9.105 2.980 2.500 67.832
GRID 28 - 32 11.135 2.725 2.500 75.857
GRID 32 - 38 9.335 2.560 2.500 59.744
GRID 38 - 42 6.495 2.400 2.500 38.970
4 GRID 1 - 2 7.725 3.000 2.000 46.350
GRID 2 - 8 9.645 3.250 2.000 62.693
GRID 8 - 11 9.020 3.098 2.000 55.888
GRID 11 - 14 8.935 2.980 2.000 53.253
17/08/2009
to
22/08/2009
B.L Kashyap & Sons Ltd
Project : Royal Meenakshi Mall

BACK FILLING QUANTITIES

Depth /
S.No Date Description Length Breadth Quantity BLK SYN Remarks
Height
17/08/2009 GRID 14 - 19 9.005 2.890 2.000 52.049
to
22/08/2009 GRID 19 - 24 10.030 3.000 2.000 60.180
GRID 24 - 28 9.105 2.990 2.000 54.448
GRID 28 - 32 11.135 3.025 2.000 67.367
GRID 32 - 38 9.335 3.250 2.000 60.678
GRID 38 - 42 6.495 2.985 2.000 38.775
5 GRID 1 - 2 7.725 3.500 1.450 39.204
GRID 2 - 8 9.645 3.200 1.450 44.753
GRID 8 - 11 9.020 3.600 1.450 47.084
GRID 11 - 14 8.935 3.245 1.450 42.041
24/08/2009 GRID 14 - 19 9.005 3.425 1.450 44.721
to
29/08/2009 GRID 19 - 24 10.030 3.289 1.450 47.834
GRID 24 - 28 9.105 3.900 1.450 51.489
GRID 28 - 32 11.135 3.450 1.450 55.703
GRID 32 - 38 9.335 3.680 1.450 49.812
GRID 38 - 42 6.495 3.780 1.450 35.599
31/08/2009
D EASTto South East corner to S T P
a 05/09/2009 wall near grid R 8.130 3.600 1.850 54.146
31/08/2009
to South East corner to S T P
b 05/09/2009 wall near grid R 8.130 3.750 2.350 71.646
07/09/2009
to South East corner to S T P
c 12/09/2009 wall near grid R 8.130 4.200 2.000 68.292
07/09/2009
to South East corner to S T P
d 12/09/2009 wall near grid R 8.130 4.540 1.850 68.284
07/09/2009
to South East corner to S T P
e 12/09/2009 wall near grid R 8.130 6.359 1.200 62.038
Total Back Filling Quantity 5029.922
UP TO RA-11 CERTIFIED 3772.440
THIS BILL QTY 1257.482