PENDING WORK DATE -14/01/2011

Fermentation & Liquification Section


1- Ball valve handle are not fitted thin slope line to premasher
2- Air blower pump (MU-911A&B) discharge presser indicator not installed
06- Fermenter no.1(R-311), 3(R-313), beer well, and pre-fermenter no.1 CIP nozzles not working
7- Fermenter no.1(R-311) agitator(A311) not working
8- All sms dummies leakages O ring required
09 - Recycle stream collection tank (FT-202) not installed
10- Pre-fermenter A transfer pump coupling break
11- ILT pump coupling not installed
13- Oil not be filling in nutrient dosing tank agitator
Evaporation section
01-LT523 butterfly valve handle not fitted
02-LT512 (VLS1) butterfly valve handle not given
04-PG5414 process water supply to evaporation section not given
05-Evaporation cooling tower fan motor not working properly
06-Steam condensate tank transfer pump 512A&B installed under capacity
07-VLS504 Side glass not fitted
08-All pumps sealing water line having leakages in evaporation section
09-Caustic and nitric acid lines are not provided to CIP tank
10-P516 (vacuum pump A) seal leak
11-Soft water to both vacuum pumps flow meter to be change cause by under capacity
12-All Falling film effects given support not properly fitted
13- H508 Preheater vapourline from effect 2nd butterfly handle not fitted
14 - VLS 5 Condensate pot side glass broken

DISTILLATION SECTION
01-PRC RS collection tank bottom pump emergency switch damage
03-Distillation drain water sump pump (P-472) pressure gauge not fitted
05-Analyser bottom LT (401) display damage
. 06-FOC FO decanter(S-471) Foundation nut bolts not installed
07-Flash tank (T-401) diaframe valve wheel not fitted
08-Simmering all reflux flowmeter isolation butterfly valve handle not fitted
09-All condenser foundation not properly tighted

Modification
01-(H-508) preheater thin slop inlet and outlet line RTD required for understanding preheater scaling problem
in evaporation section
02-Flowmeter required for process condensate recycles to liquefaction section to make the actual
Slurry preparation
03-Flote valve required to maintain the pump sealing water tank level in liquefaction and evaporation section
04-FOC Cooler after decanter sample point remaining
05-RC-PCV TA cut line to connect Rota meter
06- All fermenter PHE does not having SMS at inlet line