You are on page 1of 1

TENTATIVE DATES FOR DGA OF EQUIPMENTS

EQUIPMENT ICT-01 BUS REACTOR LINE REACTOR-01 LINE REACTOR-02


DATE OF COMMISSIONING 24-01-2011 21-01-2011 24-01-2011 21-01-2011
ONE DAY AFTER COMMISSIONING 25-01-2011 22-01-2011 25-01-2011 22-01-2011
ONE WEEK AFTER COMMISSIONING 31-01-2011 28-01-2011 31-01-2011 28-01-2011
FIFTEEN DAYS AFTER COMMISSIONING 8/2/2011 5/2/2011 8/2/2011 5/2/2011
ONE MONTH AFTER COMMISSIONING 24-02-2011 21-02-2011 24-02-2011 21-02-2011
THREE MONTHS AFTER COMMISSIONING 24-04-2011 21-04-2011 24-04-2011 21-04-2011
SIX MONTHS AFTER COMMISSIONING 24-07-2011 21-07-2011 24-07-2011 21-07-2011

NOTE:
1. IF ANYOUTAGE PERIOD THEN OUTAGE HAS TO BE CONSIDERED WHILE SENDING THE OIL SAMPLE TO CIOTL
2. IF THE EQUIPMENT FEEDS THE FAULT THEN DGA HAS TO BE PERFORMED

You might also like