ACTION POINTS AS PER TRANSCO MEETING

22-FEB-2024
Action points for TE/ TRANSCO

1. Earlier agreed DTS standardization to be followed.

2. Pile design approval issuance – by 23-Feb-24

3. Test pile location approval by TE – by 23-Feb-24

4. LAP approval to start test pile from 26-Feb-24 – NW-233555

5. Maximo competency approval for electrical – NC20799

6. Maximo competency approval for mechanical – NC20838

7. Maximo competency approval for Civil – NC20886

8. Structural design approval (DTS-313, dated 8-Feb-24)

9. Shoring calculation Approval by TE……..

10. Dewatering calculation approval by TE…….

11. SCMS integration resolution with Toshiba ……

12. LVAC vendor approval by TE……..

Action points for EAC

1. Shoring MS to submit by 24-Feb-24

2. Waterproofing vendor submission by 23-Feb-24

3. Waterproofing shop drawing submission – After structural drawing (313) approval.

4. Dewatering MS submission by 24-Feb-24.

5. Trail mix report to be obtained by EAC – 23-Feb-24

6. EAC to arrange meeting with Siemens for the transformer FAT. EAC to send meeting email confirmation.

7. ABB 11kV switchgear – EAC will come with the proposal within next week.

8. EAC planning to start the test pile by 26-Feb-24. EAC to make all necessary equipment arrangements.