- The design rules for calculations of builded structures
(In The Netherlands: NEN6702 is used) - The height to be installed - The windregime where to install - The situation Builded area Yes/No - Maximum allowed deflection - The values for safety: - General (fg) - Variable (fv) - Dynamic (fd)
- Factor Cd (Shape Coefficient) : 0,8
- Weight of Unit: 38 kg - Projected area: 0,95 m^2 - Natural Frequency pole: <2,4 Hz 120°`0,5° Example: Thrust Force at Unit without safety factors at 40 m /s: 730 N walltickness min 10mm NOTE:
n70 Pole needs to be at minimum 3 meter long
because of twisting possibillity from the cable. 12
Cable must be properly fixed at the down side pole
to avoid damage caused by twisting of the cable. (See detail)
When mounted on builded structures:
Use vibration absorbers to prevent sound inside.
60 108 125
detail
R20
Use cable gland
M10 (4x)
Home Energy International B.V. Surface treatment: -
Property of Home Energy International B.V.
Drawing: HE 10 06 003 Rev: Reproduction or distribution of information in any form, without written consent of the Minimum Requirements top V100 owner is prohibited! pole Product: ENERGY BALL V100 Tolerances (If not specified): Drawn: HV Date: 19-1-2009 - BREAK SHARP EDGES : 0,2 x 0,2 - Angles: + 0,5 Unit: mm Scale: 1 : 20 Checked: DvW Rev. date: - General tol: NEN-ISO 2768c - Surface finish to: ISO 1302 / ISO 468 Size: A4 Weight: Mat: -