Actual Expected
EXPECTED Retention Expenditure up Balance to be Expected Expenditure of Expected Expected Expenditure
SL.NO. PARTICULARS PROJECT Bills Raised Expenditure of Expenditure of
COST Money to September, paid October, 2010 November, December, 2010 of January, 2010
2010 2010
1 LAND & PRELIMINARY 76.53 52.92 52.92 23.61 5.51 6.10 6.50 5.50
EPC
2 INFRASTRUCTURE WORKS 156.15 145.06 7.25 137.81 18.34 - 3.00 3.50 11.84
MAIN CIVIL WORKS (HYDRO
3 MECHANICAL) 247.65 204.18 6.32 197.86 49.79 6.40 3.60 21.82 17.97
403.80 349.24 13.57 335.67 68.13 6.40 6.60 25.32 29.81