Mr. Surinder Duggal ZTE MR (ALUMs)/Mr. connectivity issue Harman Jindal still not resolved (Quality RCOM) Mr. Surinder Duggal (ALUMs)/Mr. Harman Jindal (Quality RCOM) Mr. Surinder Duggal (ALUMs)
Top 10
Site wise audit is planned to analyze the impact on Quality and Drop rate 15-Oct-11 from inter circle operators and there by optimizing the same.
Carrier up gradation (4-6 with additional Hardware) is in progress for 21 sites with high utilization.
RON
30-Sep-11
KPI TCR CSSR MANDI RFER RF cong TCR CSSR SHIMLA RFER RF cong
Current KPI Aug 98.47 98.95 1.84 0.39 98.88 99.22 1.76 0.18
Target Sept 30 98.90 99.00 1.65 0.30 99.00 99.40 1.58 0.02
Target Oct 30 99.20 99.50 1.30 0.10 99.30 99.60 1.30 0.02
Slide 1
Focus to optimize CDMA network post 75 LUT sites shutdown in next two months.
31-Oct-11
Minimizing the repeated outages by improving Utilities, Transmission and 31-Oct-11 Fiber presentations.