Daily Report 20-09-11
Daily Report 20-09-11
Project: 44MW Urjankur Shree Tatya Saheb Kore Warna Power Company Ltd, Warna EPC Contractor: M/s Walchand Nagar Industries Ltd, Electrical Contractor: M/s IKE Electric Ltd, Pune Date: 20-09-2011
Sl.No
Description
Status
% of Work Complete d
50% 50% 20% 50% 10% 10%
constrai n if any
Material availability
Remarks
1. 2. 3. 4. 5. 6.
DG Set Power Cable terminations DG Set Earthing PCC Panel Power Cable Terminations Boiler Vertical Cable Tray Laying Boiler Horizontal Cable Tray WTP Earth Flat Lying
Under Progress Under Progress Under Progress Under Progress Under Progress Under Progress