Electrical Erection Work Daily report

Project: 44MW Urjankur Shree Tatya Saheb Kore Warna Power Company Ltd, Warna EPC Contractor: M/s Walchand Nagar Industries Ltd, Electrical Contractor: M/s IKE Electric Ltd, Pune Date: 20-09-2011

Sl.No

Description

Status

% of Work Complete d
50% 50% 20% 50% 10% 10%

constrai n if any

Material availability

Remarks

1. 2. 3. 4. 5. 6.

DG Set Power Cable terminations DG Set Earthing PCC Panel Power Cable Terminations Boiler Vertical Cable Tray Laying Boiler Horizontal Cable Tray WTP Earth Flat Lying

Under Progress Under Progress Under Progress Under Progress Under Progress Under Progress

Nil Nil Nil Nil Nil Nil

Available Available Available Available Available Available

Total Man power: - 48


1.

DG Set Adaptor Box Fixing Work is Completed. Level.

2. Power Cable Re-Dressing is on Progress in Cellar Room 0 Mtr