Professional Documents
Culture Documents
Air Force Handbook 32-1282 VOLUME 1 1 JULY 1999
Air Force Handbook 32-1282 VOLUME 1 1 JULY 1999
FIELD GUIDE FOR INSPECTION, EVALUATION, AND MAINTENANCE CRITERIA FOR ELECTRICAL SUBSTATIONS AND SWITCHGEAR DEPARTMENT OF THE AIR FORCE
THIS PUBLICATION CONTAINS COPYRIGHTED MATERIAL
AFH 32-1282V1
AIR FORCE HANDBOOK 32-1282V1 1 JULY 1999 Civil Engineering Field Guide for Inspection, Evaluation and Maintenance Criteria for Electrical Substations and Switchgear
This handbook summarizes procedures and guidance to Air Force electricians for the inspection, evaluation, and maintenance of substations, switchgear, and associated devices. It will also assist maintenance engineers and quality assurance evaluators in specifying and inspecting contractor performance.
Contents
Chapter 1 Overview of the Guide 1-1 Scope............................................................. 1-2 1-3 1-4 1 Table 1-1 Table 1-2 Equipment covered in this handbook.... Equipment covered in AFH 32-1282V2 1 8
Supplementary Information ........................... 8 Basis for Developing Field Procedures ......... 9 Preinspection Procedures ............................. 10
OPR: HQ AFCESA/CEOM (Capt Thomas E. Wahl) Certified by: HQ AFCESA/CEO (Col William R. Pearson) Pages 110/Distribution F
THIS PUBLICATION CONTAINS COPYRIGHTED MATERIAL
AFH 32-1282V1
Index
AFH 32-1282V1
Chapter 2. General Substation Guidance 2-1 Use of Substation One-Line Diagrams.......... 16 2-2 Operating Information.................................... 20 Table 2-1 Table 2-2 Chapter 3. Substation Support Elements 3-1 Substation Tests............................................ 23 Table 3-1 Table 3-2 3-2 Substation Support Elements EPM Reports . 26 Table 3-3 Table 3-4 Table 3-5 Table 3-6
Installation electrical one-line diagram deficiencies....................... Safety electrical one-line diagram features........................................... Recommended maintenance based in IR temperature rises ................... Maximum acceptable ground resistances ..................................... Substation support elements general data ................................... EPM column headings.......................... Substation support element readings or test values ................... Substation support element checks......
21 22 24 25 26 29 29 30
ii
AFH 32-1282V1
Index
Chapter 4. Circuit Breaker Performance 4-1 Circuit Breaker Basics ................................... 4-2 Circuit Breaker Conducting Contacts and Arc Extinguishing Processes .......................... 4-3 Circuit Breaker Operating Mechanisms......... 4-4 Circuit Breaker Elementary Diagrams ........... 4-5 Circuit Breaker Nameplates........................... 31 Table 4-1 32 35 Table 4-2 40 43 Table 4-3 Table 4-4 Chapter 5. Circuit Breaker Testing 5-1 De-Energized Circuit Breaker General Tests 5-2 48 Table 5-1
AFH 32-1282V1
32 36
Low-voltage circuit breaker minimum nameplate information.................... 43 Medium and high voltage circuit breaker minimum nameplate information .... 45 Circuit breaker insulation-resistance test values ............................................. 49
De-Energized Tests Specific to the Circuit Breaker Type ............................................ 52 Chapter 6. Circuit Breaker Evaluations 6-1 Circuit Breaker EPM Reports ........................ 53 6-2 High-Voltage SF6 or Oil Insulated Circuit Table 6-1 Breakers.................................................. 54 Table 6-2 Table 6-3 Table 6-4 6-3 6-4 Medium-Voltage Vacuum or Air Insulated Metal-Clad Switchgear Circuit Breakers . 56 Table 6-5 Low-Voltage Circuit Breakers ........................ 60 Table 6-6
Circuit breaker general data ................. Circuit breaker readings or test values . External high-voltage circuit breaker checks ............................................ Internal high-voltage circuit breaker tank procedures and checks .......... Medium-voltage metal clad switchgear circuit breaker checks..................... Low-voltage circuit breaker checks.......
53 54 55 56 59 60
iii
AFH 32-1282V1
Index
AFH 32-1282V1
Chapter 7. Interrupter Switch Installations 7-1 Interrupter Switch Basics............................... 63 Table 7-1 Table 7-2 Table 7-3 Table 7-4 Interrupter Switch Operating Features .......... 67 Interrupter Switch De-Energized Device Tests ....................................................... 71 Table 7-5 7-4 Interrupter Switch EPM Reports .................... 72 Table 7-6 Table 7-7 Chapter 8. Switchgear and Switchboard Assemblies 8-1 Assembly Performance ................................. 74 Table 8-1 Table 8-2 8-2 De-Energized Assembly Tests ...................... 81 Table 8-3 8-3 Energized Assembly Tests ............................ 81 8-4 Assembly EPM Reports................................. 82 Table 8-4 Table 8-5 7-2 7-3
Interrupter switch ratings ...................... Fuse ratings .......................................... Interrupter switch minimum nameplate information...................................... Fuse minimum nameplate information.. Interrupter switch test requirements ..... Interrupter switch general data ............. Interrupter switch checks ...................... Industry classification for assemblies ... MC/MEI switchgear major differences .. Assembly test requirements ................. Assembly general data ......................... Assembly checks ..................................
64 65 66 67 72 72 73 79 80 81 83 84
iv
AFH 32-1282V1
Index
AFH 32-1282V1
Chapter 9. Battery Installation 9-1 Battery Installation Basics ............................. 85 9-2 Battery Installation Readings and Tests........ 89 Table 9-1 Table 9-2 Table 9-3 Table 9-4 9-3 Battery Installation EPM Reports .................. 93 Table 9-5 Table 9-6 Table 9-7 Table 9-8 Chapter 10. Protective Sensing, Processing, and Action Devices 10-1 Device Performance ...................................... 97 10-2 Device Testing............................................... 99 Table 10-1 Table 10-2 10-3 Installation-Wide Operating Systems ............ 102 10-4 Protective Sensing, Processing, and Action Device EPM Reports.................... 102 Table 10-3 Table 10-4
Battery installation readings.................. 90 Capacity test procedures ...................... 92 Battery capacity degradation ................ 92 Integrity test procedures ....................... 93 Battery installation general data ........... 94 Lead-acid battery installation corrective actions ............................................ 95 Nickel-cadmium battery installation corrective actions ........................... 96 Battery installation checks .................... 96
Relay tests ............................................ 100 Relay pickup parameters ...................... 101 Device general data .............................. 102 Instrument, metering and protective relay general checks ............................... 105
AFH 32-1282V1
AFH 32-1282V1
Acknowledgment
The Air Force wishes to express their sincere appreciation to the many companies and their representatives who kindly cooperated in supplying CAD illustration inputs and pictures for use in this handbook. Inputs used for CAD illustration inputs were supplied by Siemens Energy and Automation, Inc.; Square D Company/Groupe Schneider; and Westinghouse/Cutler Hammer. Some pictures were supplied by Keller & Gannon. The Air Force expresses particular appreciation to Williams Learning Network (formerly NUS Training Corporation) whose training videos were used to provide the rest of the pictures. NOTE: Product and manufacturer names are included in this handbook for the purposes of illustration and do not carry the specific endorsement of the Air Force.
vi
AFH 32-1282V1
AFH 32-1282V1
CHAPTER 1. OVERVIEW OF THE GUIDE 1-1. Scope. The condition of electrical power apparatus found in substations is crucial to the successful operation of all electrical power systems. Switchgear and related equipment are significant components of the systems. This handbook identifies field procedures which allow early detection of equipment degradation and other defects which will adversely affect reliability. Appropriate corrective actions can then be accomplished. a. General Categories of Substation Equipment. Table 1-1 lists the general categories of substation equipment covered in this Air Force maintenance handbook. Figures 1-1, 1-2, 1-3, 1-4, 1-5, and 1-6 have been provided to remind the technician of similar and differing features of various circuit breaker and switchgear types. Substation equipment categories discussed in AFH 32-1282V2 (Field Guide for Inspection, Evaluation, and Maintenance Criteria for Electrical Transformers) are listed in Table 1-2. Table 1-1. Equipment covered in this handbook
Substation support elements providing area safety Transmission/distribution power-line switching ! Circuit breakers ! Load interrupter switches Power-line switching unit/assembly necessary sub-elements ! Switchgear/switchboard assemblies ! Battery installations ! Protective sensing, processing, and action devices 1
AFH 32-1282V1
AFH 32-1282V1
1. 2. 3. 4. 5. 6. 7.
Interrupters Bushings Control cabinet Pressure gauges and operation counter Current transformers Steel base Base legs
7
Figure 1-1 High-voltage SF6-gas-insulated circuit breakers
2
AFH 32-1282V1
AFH 32-1282V1
1 2 3
4 5
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11.
Compressor Pull rod Control panel Mechanism Reservoir Bushing Oil level indicator Oil vent Tank Mechanism housing Local control
6 7 8
9 10 11
AFH 32-1282V1
AFH 32-1282V1
8 9
10
6 5 4
1. 2. 3. 4. 5. 6. 7. 8. 9. 10.
Relays Switches Instruments/meters Compartment barriers Circuit breaker wheels Circuit breaker rails Drawout circuit breaker Circuit breaker mechanism Barriers Automatic shutters
3 2 1
AFH 32-1282V1
AFH 32-1282V1
2 3 6
7 8 4 9 2 5
Switch operator Padlock location Inspection window Main door Door stop Safety barrier Door interlock Switch interlock Barriers Switch position indicator Padlock location Key interlocks Operating handle Nameplates
13 12 14 10 11 12
7 1
AFH 32-1282V1
AFH 32-1282V1
12 13
19
6
18
5 9
4 10
1. 2. 3. 4. 5. 6. 7.
3 1 2 Finger clusters Extension rail Levering arm Moving contacts Stationary contacts Molded base Arcing contact spring
16
11
15
14
17
11.Pole unit 12.Interface barriers 13.Secondary disconnect contacts 14. Levering device arm
15. Main disconnect contacts 16. Sensors 17. Drawout circuit breaker 18. Switchgear 19. Rail mounted lifter
AFH 32-1282V1
AFH 32-1282V1
9 1
1. Main circuit breaker 2. Group-mounted circuit breakers 3. Vertical bus behind 4. Hinged wiring access panels 5. Side access panel 6. Removable cover plates 7. Ventilation grille 8. Blank filler plates 9. Warning and manufacturers labels
8 6 4 2
AFH 32-1282V1
AFH 32-1282V1
The maintenance technician should be familiar with and have available Air Force electrical design, maintenance, and safety manuals. a. Design. Refer to the installation requirements of AFMAN 32-1180(I) (Electrical Power Supply and Distribution) which provides Air Force policy and guidance for design criteria and standards for electrical power supply and distribution systems.
b. Maintenance. Refer to AFMAN 32-1280(I) (Facilities Engineering, Electrical Exterior Facilities) which amplifies the maintenance and repair guidance of this handbook. 8
AFH 32-1282V1
AFH 32-1282V1
c. Safety. Refer to AFMAN 32-1185 (Electrical Safe Practices) which provides safety standards for the work being done. Maintenance work should be done only by workers in accordance with the electrical work classifications of AFMAN 32-1185, including AFSC 3E011 equivalent (helper), AFSC 3E031 equivalent (apprentice), AFSC 3E051 equivalent (journeyman), or AFSC 3E071 equivalent (craftsman). AFH 32-1285 (Electrical Worker Safety Field Guide) should be available to you to use in the field. This handbook is intended as summary guidelines and procedures. Actual maintenance/repair program requirements should be adjusted as appropriate for your specific electrical apparatus. a. Handbook Information. This handbook covers generic apparatus performance, test data, and generally applicable component element checks. Use this handbook as a reminder of general maintenance requirements. (1) Performance. Each component of major electrical apparatus performs essentially a simple operation. Complexity in maintenance is caused by the large and varied types of electrical components in the apparatus. This handbook provides figures and pictures to illustrate the most important of these components. (2) capability. Tests. Electrical equipment must be tested to ensure its continuing operating
AFH 32-1282V1
AFH 32-1282V1
(a) Test Descriptions. Descriptions of the most commonly used tests are included in this handbook. Acceptable values of the tests are provided when possible. Reference to the manufacturers literature may be required for other tests. (b) Comparisons for Trends. All tests/readings should be compared to previous values (acceptance, maintenance, or repair). This will assist in recognizing trends that indicate a need for more frequent testing. Permanent changes to equipment/devices that are overloaded, misapplied, or inadequate for the duty to which they are subjected may be required. (3) Component Element Checks. Tables are included in this handbook which outline the most important components to be checked. Additional information on these components can be found in AFMAN 32-1280(I) and the manufacturers literature. b. Locally Developed Field Procedures. Each facility should maintain a copy of all applicable documents related to the installation, operation, and maintenance of electrical systems. Locally developed EPM procedures are essential to proper maintenance.
10
AFH 32-1282V1
AFH 32-1282V1
(1) Documentation Maintenance. The Base Civil Engineer (BCE) should ensure all documentation is maintained for each specific item of electrical apparatus which makes up the facility electrical power systems. (a) Available From Design/Construction Files. The available data may include all of the inspection and testing procedures for the facility, copies of previous reports, single-line diagrams, schematic diagrams, electrical equipment plans, records of complete nameplate data, and manufacturers service manuals and instructions. (b) Locally Prepared. Prepare local EPM forms as necessary for installed equipment. Each item of apparatus should be shown on an equipment location plan. (See Paragraphs 3-2, 5-1, 6-1, 7-4, 8-4, 9-3, and 10-4). Provide unique apparatus designations along with a locally prepared safety electrical one-line diagram and equipment location plan. Table 2-2 summarizes the minimum recommended features of a safety electrical one-line diagram. (2) Specific Assembling of Data: Assemble the following data, if available, for each specific item of apparatus. ! ! ! Locally prepared forms. As-built drawings for electric equipment layouts and elevations. Trend analysis data which should include: (a) Installation acceptance data test results. (b) Previous EPM reports including any previous systematic evaluations.
11
AFH 32-1282V1
AFH 32-1282V1
Manufacturers service manuals including practices and procedures for: (a) Installation. (b) Disassembly/assembly (interconnection). (c) Wiring diagrams, schematics, bills of materials (d) Operation (set-up and adjustment) (e) Maintenance (including parts list and recommended spares) (f) Software programs. (g) Troubleshooting guidance. (3) Systematic Evaluation of Apparatus Condition. Electric apparatus should receive a systematic evaluation of its condition after an EPM which indicates repairs were necessary beyond normal expected maintenance. The systematic evaluation should include: ! Reasons for the required repairs. ! Work required to complete the repairs. ! Assessment of the remaining service life. ! Determination of the need for a more frequent EPM. c. Safety Requirements. Working on or near normally energized lines or parts requires observance of rules applying to safe working distances, work methods related to whether the line has been de-energized or left hot, and recognition of work hazards which require more than one worker for safety. Workers must be qualified for the work and use approved work methods and equipment. Refer to the requirements of AFH 32-1285 as amplified by AFMAN 32-1185. Always include a tailgate meeting to address existing site conditions and the procedures to be followed. Work will be done de-energized unless energized line work is specifically authorized. 12
AFH 32-1282V1
AFH 32-1282V1
(1) De-Energized Electrical Line Work. Follow the safe clearance (lockout/tagout) procedures given in AFH 32-1285. Remember lines are considered energized if the de-energized systems have not been provided with proper protective grounding. The safe clearance may require a job hazard analysis. (2) Energized Electrical Line Work. Work on energized lines and equipment only when authorized by the electrical supervisor/foreman/lead electrician (per local organization) based on the need to support a critical mission, to prevent injury to persons, or to protect property. Insulating means must be provided to isolate workers from a source of potential difference. A job hazard analysis is required for energized line work. (See AFH 32-1285). d. Understanding Maintenance Frequencies. Frequency of maintenance should be locally adjusted based on the application of the equipment. See additional guidance in NFPA 70B (Electrical Equipment Maintenance). Adjust the frequency of inspection based on the criticality of the apparatus, the severity of the loading conditions, and an environment where unusual service conditions stress the equipment. Generally, usual service conditions extend only to elevations of not more than 3,300 feet (1 kilometer) and ambient temperatures of no more than 30 to 40 degrees C. Check with the manufacturer for other than normal service conditions. e. Inspection Materials/Devices. Basic items needed for an EPM include the following: ! A facility electrical truck ! Available documentation. ! EPM forms. ! Directions as to any input or approval needed from the appropriate using or operating agency 13
AFH 32-1282V1
AFH 32-1282V1
! !
Contamination washing devices such as a portable nozzle washer truck Miscellaneous tools such as
(1) (2) (3) (4) Binoculars Flashlights (insulated) Insulated fuse puller Magnifying glass (5) Tape recorder, tape, and batteries (6) Video camera and accessories (7) Oil sample bottle and syringes and gas sample bottles
14
AFH 32-1282V1
AFH 32-1282V1
Cleaning devices (1) Vacuum cleaner (2) Compressed air cleaner (not for use in medium or high voltage enclosures or other locations where dust could cause flashover) Miscellaneous materials as necessary to clean, wipe, paint, insulate, solder, or for other small field-fix repairs.
15
AFH 32-1282V1
AFH 32-1282V1
CHAPTER 2. GENERAL SUBSTATION GUIDANCE 2-1. Use of Substation One-Line Diagrams. A substation is an area
or an equipment group which contains switches, circuit breakers, buses, and transformers. It provides for the switching of power circuits and for the transforming of electrical power from one voltage to another or from one system to another. Stations without transformers are more properly called switching stations, but for simplicity the word substation will be used to include switching stations. a. Determine Systems Circuit Arrangement. A system is designed to meet load requirements, reliability, and flexibility. The criticality of the load also means maintainability must be considered.
b. Basic Circuit Arrangements. Various common distribution systems are shown on Figures 2-1, 2-2, 2-3, 2-4, 2-5, and 2-6. Understanding how your facilitys distribution system is configured is the key to providing safe clearing or isolating procedures for any portion of the system needing maintenance and repair. Figure 2-1 is the simplest circuit arrangement. This simple system provides no backup reliability and loads cannot be backfed as is the case with Figure 2-2. Selective systems (Figures 2-3 and 2-4) provide alternate sources of input power. Network systems (Figures 2-5 and 2-6) provide the ultimate in service reliability.
16
AFH 32-1282V1
AFH 32-1282V1
SOURCE OF SUPPLY CIRCUIT BREAKER LOAD CENTER
DISCONNECT SWITCH
LOAD CIRCUITS
LOAD UNITS
AFH 32-1282V1
AFH 32-1282V1
CIRCUIT BREAKER
LOAD CIRCUITS
PRIMARY FEEDERS
LOAD CIRCUITS
TO OTHER LOADS
AFH 32-1282V1
AFH 32-1282V1
PRIMARY FEEDERS
NETWORK PROTECTOR
LOAD CIRCUITS
LIMITER LUGS
LOAD CENTERS
AFH 32-1282V1
AFH 32-1282V1
For maintenance to be done safely, operating information must define energy paths and switching control components. Each component should be provided with a unique identification and a specific location. a. One-Line Diagram Preparation. As a part of the Apparatus Documentation (see Paragraph 1-4) each installation should prepare safety electrical one-line diagrams. Develop safety electrical one-line diagrams from the installation electrical one-line diagrams. Installation electrical oneline diagrams are design documents made for construction and contain unnecessary installation data. Safety electrical one-line diagrams should be prepared by facility personnel and should show only data relevant to safe operating procedures. Table 2-1 indicates installation electrical one-line diagram deficiencies that make this document a poor substitute for a safety electrical one-line diagram. Installation electrical one-line diagrams may still need to be consulted for design information for replacements. Table 2-2 summarizes the minimum recommended features of safety electrical one-line diagram b. Equipment Location Plan Preparation. As a part of the Apparatus Documentation (see Paragraph 1-4) each installation should prepare a simplified electric equipment layout corresponding to the safety electrical one-line diagram. The plan should locate all the components shown on the safety electrical one-line diagram using the same identification. Also show power circuit routing which cannot be observed at the site.
20
AFH 32-1282V1
AFH 32-1282V1
21
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
(3) Interpretation. Infrared hot-spot temperature gradients indicating possible deficiencies are given in AFMAN 32-1280(I) for equipment. Table 3-1 lists temperature rises above ambient which have been found practical in regard to equipment problems.
b. Permanent Ground System Resistance Tests. A ground resistance test set can be used to determine the effectiveness and integrity of the grounding system. See AFMAN 32-1280(I) and AFMAN 32-1185 for the importance of adequate grounding in operating and maintaining electrical systems safely. (1) Precautions. Testings of grounds can create hazardous conditions as all electrical conductive paths for overvoltage and fault currents are connected to the substation ground system. Rubber gloves, blankets, and other protective devices are recommended. 24
AFH 32-1282V1
AFH 32-1282V1
(2) Action. Measure the ground path resistance of all branches of the grounding system from ground connections at support structure, equipment enclosures, and neutral conductors to the ground system. Measure other resistances covered in Table 3-2 which indicates maximum acceptable ground resistances.
Measured Substation Gates and gateposts2 Operating rods and handles of group operated switches and their supporting structures
In accordance with departmental standards. Measurement of flexible gate ground connection adequacy.
(3) Recommendations. Where no departmental standards are available it is recommended that substations of 1,000 kVA or less have a maximum ground resistance of 5 ohms and substations over 1,000 kVA have a maximum ground resistance of 3 ohms. c. Corona. Check for corona as covered in Paragraph 8-3.
25
AFH 32-1282V1
AFH 32-1282V1
3-2. Substation Support Elements EPM Reports. Each installation should prepare local blank EPM report forms to be filled out by the inspecting technicians. (See Paragraph 1-4). The following tables indicate the data to be recorded.
a. Basic Substation Support Elements Information to Be Determined Before the Inspection. Provide a suitable record header with blank spaces for insertion of the following data given in Table 3-3. Pictures 3-1, 3-2, 3-3, and 3-4 show actual substation support elements.
Type Switching only High- to medium-voltage Medium- to low-voltage Aerial service Underground service
For guidance on EPM reports covering bushings, instrument transformers, and surge arresters see AFH 32-1282V2.
26
AFH 32-1282V1
AFH 32-1282V1
27
AFH 32-1282V1
AFH 32-1282V1
28
AFH 32-1282V1
AFH 32-1282V1
29
AFH 32-1282V1
AFH 32-1282V1
b. Basic Inspection Items to be Checked. Provide an EPM inspection report with column headings covering items to be checked off for each listed item number given in Table 3-4.
c. Inspection Items to be Covered. List inspection items to be covered. Table 3-5 indicates substation support element readings or test values and appropriate evaluation paragraphs for passing criteria. Table 3-6 indicates substation support element components and appropriate inspection actions.
Readings or test values Ambient temperature Infrared temperature rise Ground resistance
Readings should identify location or be provided with such identification in a separate report.
30
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
Maximum continuous current, amperes 3,000 2,000 3,000 2,000 3,000 3,000 3,000 3,000
First number is for indoor oiless circuit breakers. Second number is for outdoor circuit breakers. Oil circuit breakers manufactured before 1975 may have an 8 cycle rating. This rating affects coordination and short circuit studies; it does not affect maintenance requirements.
4-2. Circuit Breaker Conducting Contacts and Arc Extinguishing Processes. Circuit opening of the conducting contacts causes an arc to form which is extinguished
by various methods. Examples of the various types of arc extinguishing media are shown on Pictures 4-1, 4-2, 4-3, and 4-4. 33
AFH 32-1282V1
AFH 32-1282V1
34
AFH 32-1282V1
AFH 32-1282V1
35
AFH 32-1282V1
AFH 32-1282V1
a. Conducting Contact Opening. An energized circuit breaker draws an arc when its conducting contacts are separated. The temperature of the arc ionizes the insulating medium and sustains the arc. On current zero, arcing ceases and the voltage across the contacts increases. The voltage buildup results in an arcing restrike from the electric field and from thermal effects of the initial arcs charged particles Only when the arc is cooled well below its ionization temperature at current zero will the arc be fully extinguished and current interruption accomplished. b. Extinguishing Methods. Various methods provide arc extinguishing. All methods involve either cooling the arc or providing an insulating atmosphere unfavorable to ionization or to reionization. Arc chutes in air magnetic circuit breakers with their barriers use side-by-side fins through which the arc is drawn by the establishment of a magnetic field. This longer arc is then cooled by convection. Air magnetic circuit breakers have both main and arcing contacts. (See Paragraph 7-2.a.) Oil in oil-insulated circuit breakers vaporizes and forms air bubbles whose hydrogen is unfavorable to ion production. Sulfur hexafluoride (SF6) in SF6-insulated circuit breakers is about 100 times more effective than air in extinguishing the arc. Vacuum in vacuum circuit breakers is an even better arc extinguisher since its high dielectric does not allow ionization to maintain itself and restrike after a current zero.
An operating mechanism needs some form of energy to open and close the circuit breaker contacts at the required speed. The circuit breaker mechanism must cause acceleration, movement, and deceleration at each opening and closing stroke. Equally important the circuit breaker must stay open or closed until directed either manually or automatically to perform otherwise.
36
AFH 32-1282V1
AFH 32-1282V1
a. Operating Energy. All operating mechanisms use some form of stored energy for opening and closing the circuit breaker. Pictures 4-5, 4-6, 4-7, and 4-8 show examples of various operating mechanisms. (1) Stored Energy Methods. Table 4-2 indicates some of the various methods of stored energy used to open and close circuit breakers. The method used to close the circuit breaker may not be the same method used to open the circuit breaker. It takes more energy to close a circuit breaker than to open the unit. In both cases the contact motion is slowed by dampers at the end of the stroke.
1. 2. 3.
1. 1.
AFH 32-1282V1
AFH 32-1282V1
38
AFH 32-1282V1
AFH 32-1282V1
39
AFH 32-1282V1
AFH 32-1282V1
b. Spring-Operating Mechanisms. The stored energy is usually provided by springoperating mechanisms. Motor-wound springs store closing/opening energy. Springs are latched either in the closed or the open position until a manual or automatic direction releases them. (1) Closing. A latch must hold against a large force to prevent the spring from unwinding. By providing a main latch, an in-between latch, and a trip latch in series the necessary releasing electromechanical devices becomes a low-energy system. The three latches act as a mechanical amplifier. A small amount of corrosion, lack of lubrication, proper alignment on the lowenergy end of the amplifier can prevent the trip latch from operating. A much greater amount of these defects are needed to prevent the main latch from operating. (2) Opening. On energizing the trip coil a latch is released or a pilot valve is actuated and the opening operation goes to completion without necessarily requiring the tripping coil to be energized through the entire operation. c. Pneumatic/Hydraulic Operating Mechanisms. Pneumatic/hydraulic amplifiers have a main valve operated by a pilot valve (directed by the closing or tripping coil). Their design lowers the electromechanical energy requirement. d. Auxiliary Devices. Auxiliary contacts indicate the circuit breaker position by energizing indicating lights. Auxiliary contacts signal the need for early replacement of stored energy spring winding motors, hydraulic pump/air compressors, and other auxiliary devices when contacts are provided that monitor the adequacy of that stored energy device.
40
AFH 32-1282V1
AFH 32-1282V1
e. Interlocks. Interlocks prevent releasing the closing spring when the circuit breaker is already closed or operating the unit as it is moved from the connected position to the test or to the disconnected position. f. Safety. Isolate control and current, and voltage instrument transformer secondary circuits to protect against unintentional operation. (1) Control Circuits. Understand the control method including interconnecting circuits and remove control fuses, open test switches, and disable any other control inputs. Lockout/tagout precautions should cover all isolating requirements. (2) Closing/Opening. Circuit breakers are both opened and closed with stored energy mechanisms which may remain charged even when a circuit breaker has been withdrawn from its enclosure. The mechanisms may be still capable of operating the circuit breaker in the withdrawn position. If the circuit breaker is closed, make sure the opening device circuit is discharged before you approach it with your tools or fingers. If the circuit breaker is open, block it and wire the trip latch to prevent the circuit breaker from closing. Above all, read the manufacturers instructions so that you can predict the condition of the circuit breaker.
4-4. Circuit Breaker Elementary Diagrams. Review the circuit breaker elementary diagram provided in the manufacturers instructions. Check any modifications given in the operations manual for the specific system. The effect of open-close-trip actuators, control operating power input, open and close activating and monitoring devices, and safety interlocks all impact on the circuit breaker operating mode. That impact can affect the safety of the maintenance technician and the continued operation of the device. An elementary diagram of a spring-operated circuit breaker mechanism is shown on Figure 4-1 and the mode of operation discussed in Figure 4-2.
41
AFH 32-1282V1
AFH 32-1282V1
WL
OPERATION LS1 OPEN UNTIL SPRINGS aa ARE FULLY CHARGED LS1 CLOSED UNTIL SPRINGS bb ARE FULLY CHARGED LS2 OPEN UNTIL SPRINGS aa ARE FULLY CHARGED LS2 CLOSED UNTIL SPRINGS bb ARE FULLY CHARGED LC OPEN UNTIL MECHANISM IS RESET
PS2
PS1 OPEN IN ALL EXCEPT BETWEEN TEST AND CONNECTED POSITIONS PS2 CLOSED IN ALL EXCEPT BETWEEN TEST AND CONNECTED POSITIONS
AFH 32-1282V1
AFH 32-1282V1
As soon as the secondary disconnects engage, the spring charging motor automatically starts charging the closing springs provided the control power is available. When the springs are charged, the motor cut off (LS1/bb and LS2/bb) switch turns the motor off. The breaker may be closed by making the control switch close (CS/C) contact. Automatically upon closing of the breaker, the motor starts charging the closing springs. The breaker may be tripped any time by making the control switch trip (CS/T) contacts. Note the position switch (PS) contact in spring release (SR) circuit in the scheme. This contact remains made while the breaker is being levered between Test and Connected position. Consequently it prevents the breaker from closing automatically even though control switch close contact may have been made while the breaker is levered to the Connected position. When the CS/C contact is made, the SR closes the breaker. If the CS/C contact is maintained after the breaker closes, the Y relay is picked-up. The Y/a contact seals in Y until CS/C is opened. The Y/b contact opens the SR circuit so that even though the breaker would subsequently open, it could not be re-closed before the CS/C were released and remade. This is the anti-pump function.
AFH 32-1282V1
AFH 32-1282V1
Circuit breaker nameplate data can provide useful information when Apparatus Documentation data is not available or has been lost. Tables 4-3 and 4-4 show minimum circuit breaker information required on circuit breaker nameplates for low-voltage circuit breakers and for medium and high voltage circuit breakers respectively.
44
AFH 32-1282V1
AFH 32-1282V1
For circuit breakers rated 250 V maximum with short circuit breaking current of 5000 amperes, the short circuit breaking current shall be permitted to be omitted. If the proper operations or installation is a dependent upon an insulation barrier If symbols are used, O will be used to indicate the open and I will indicate the closed position.
2 3
45
AFH 32-1282V1
AFH 32-1282V1
Table 4-4. Medium and high voltage circuit breaker minimum nameplate information
Circuit breaker Manufacturers name Rated line closing switching surge factor Manufacturers type designation Rated short-circuit current Manufacturers serial number Rated interrupting time Year of manufacture Normal operating pressure Rated frequency Minimum operating pressure Rated continuous current Gallons of oil per tank or weight of gas per breaker Rated maximum voltage (kV) Weight of circuit breaker complete (with oil or gas) Rated voltage range factor K Instruction book number Rated full wave impulse withstand voltage (kV) Parts list number Rated switching-impulse withstand voltage Assigned out-of-phase switching current rating ! Terminal to ground - circuit breaker closed ! Terminal to terminal - circuit breaker open
46
AFH 32-1282V1
AFH 32-1282V1
Table 4-4. Medium and high voltage circuit breaker minimum nameplate information (cont.)
Ratings for capacitance current switching Transient overvoltage factor Back-to-back shunt capacitor bank current Open-wire line charging current Transient inrush current peak Isolated shunt capacitor bank current Transient inrush current frequency Manufacturers name Manufacturers type designation Manufacturers serial number Year of manufacture Closing control voltage range Tripping control voltage range Closing current Tripping current Operating mechanism Compressor control switch closing and opening pressures Low pressure alarm switch closing and opening pressures Low pressure lockout switch closing and opening pressures Wiring diagram number Instruction book number Parts list number
47
AFH 32-1282V1
AFH 32-1282V1
Table 4-4. Medium and high voltage circuit breaker minimum nameplate information (cont.)
Current transformers1 Manufacturers name Connection chart showing: Manufacturers type designation ! Full winding developing Rated frequency, if other than 60 cycles ! Taps American National Standard accuracy class ! Ratio in terms of primary and secondary currents Instruction book number ! Polarity Curve sheet ! Pole and pocket location Accessories Identification Pertinent operating characteristics
1
Nameplates located at respective terminal blocks. Includes mutual reactance and self-impedance (resistance, reactance, and impedance) for linear couplers.
48
AFH 32-1282V1
AFH 32-1282V1
CHAPTER 5. CIRCUIT BREAKER TESTING 5-1. De-Energized Circuit Breaker General Tests.
Always test circuit breakers in the test position. If there is no test position (stationary circuit breakers) test only after the circuit breaker has been de-energized and grounded. Tests must be done in accordance with the safety requirements for de-energized electrical line work given in Paragraph 1-4. Convert measured insulation resistances and power factors from the test temperature to the reference temperature of 20 degrees C (AFMAN 32-1280(I)). a. Contact Resistance Tests. Repeated arcing or excessive corrosion of circuit breaker contacts increases contact resistance which is detrimental to the contacts ability to carry current. Increased contact resistance may also indicate loose joints or misaligned contacts. (1) Application. Apply a direct-current source (of at least 100 amperes of current for medium and high voltage circuit breakers) from the circuit breakers input terminal/bushing to its output terminal/bushing. Close the circuit breaker and with a low-resistance instrument measure the resistance of each pole. The average resistance values for 15-kV-class circuit breakers should normally be between 200 and 250 micro-ohms. (2) Test Values. The resistance should not exceed the values specified by the circuit breaker manufacturer for the type, voltage, and current rating of the circuit breaker. Contact resistance varies with low-voltage circuit breakers and usually is measured by millivolt drop rather than micro-ohm resistance. In the absence of manufacturers data compare the measured poles contact resistance to adjacent poles and/or to similar circuit breakers ratings. Investigate any deviations exceeding the 49
AFH 32-1282V1
AFH 32-1282V1
manufacturers tolerance or any deviation of more than 50 percent if compared to similar circuit breakers or adjacent poles. b. Insulation Resistance Pole-to-Pole Tests. This test is meaningful only on a comparative basis. A gradual decline in resistance with age is normal; however, a sudden decline means insulation failure is imminent. A continued downward trend indicates insulation deterioration, even through measured resistance values are above the minimum acceptable limits. (1) Application. Use a megohmeter to measure insulation resistance with the circuit breaker in both the open and closed positions. (a) Circuit Breaker Open. Connect the megohmeter lead to one input or output pole terminal of the circuit breaker with all other five pole terminals grounded. Repeat for the other five terminals. (b) Circuit Breaker Closed. Connect the megohmeter lead to one closed pole (either input or output) terminal of the circuit breaker with either the input or output of the other two closed pole terminals grounded. Repeat for the other two phases. (c) Test Values. Take the ambient temperature during measurements. Correct the measured insulation resistance and record. Compare with acceptance and previous test values. See Table 5-1 for test voltages and minimum insulation resistances.
50
AFH 32-1282V1
AFH 32-1282V1
5000 20000 100000
c. Control Wiring Insulation-Resistance Tests. Perform insulation-resistance tests at 1000 volts direct current. Do not perform the test on wiring connected to solid-state components. Insulation resistance should be a minimum of 2 megohms. d. Insulation Power Factor Tests. Use an insulation power factor test set in accordance with the test sets instructions. The use of the set requires previous training and the set manufacturer should supply test-data forms. Limit test voltages to below the line-to-line voltage rating of the circuit breaker. Take measurements which allow computation of the power factor based on the measured insulation watts loss divided by the volt-amperes applied. Check power factor for both open and closed positions of the circuit breaker. Power factor test results should be evaluated on the basis of previous results but any value above 1 percent warrants investigation. (1) Precautions. Power factor measurement instrumentation must be well shielded if it is used in a substation area where there may be a significant level of electrostatic interference. Using a higher frequency power supply may help solve the interference problem. (2) Advantages: The insulation power factor test can detect defective insulation in series with good insulation, a condition that may be masked when using the insulation resistance test. The insulation resistance test may indicate a false low value of resistance because of the many parallel paths and the variation due to the volume of the insulation system. A negative power factor is an indication of tracking across the insulation system. 51
AFH 32-1282V1
AFH 32-1282V1
e. Dynamic Travel Tests. Use a motion analyzer to check mechanical operation of the circuit breaker at full speed. Compare circuit breaker travel and velocity values to the manufacturers acceptable limits and with the historical record for the circuit breaker. Small variations in speed or travel can indicate deteriorating conditions of the circuit breakers closing mechanism, stored energy system, shock absorbers, and other mechanical parts. f. Trip and Close Coil Minimum Operating Voltage Tests. For circuit breakers without integral diagnostic capabilities, connect a switch and rheostat in series with the coil circuit (trip or close) being checked and across the terminals to the applicable remote control switch. Connect a voltmeter across the coil. Starting at below 50 percent of rated coil voltage, gradually increase the voltage until the coil plunger picks up and successfully operates the circuit breaker. Make several trial operations of the circuit breaker, and record the minimum operating voltage. (1) Tripping. Most circuit breakers should trip at about 55 percent of rated trip-coil voltage. Measure the trip-coil resistance and compare it with the factory test value to disclose shorted turns. Many modern circuit breakers have trip coils which will overheat or burn out if left energized for more than a short period. An auxiliary switch is used, in series with the coil, to open the circuit as soon as the circuit breaker has opened. The auxiliary switch must be properly adjusted to successfully break the arc without damage to the contacts. (2) Closing. Follow the same procedure for determining the minimum closing coil voltage. Record the minimum voltage that will close the breaker and the closing coil resistance.
52
AFH 32-1282V1
AFH 32-1282V1
5-2. De-Energized Tests Specific to the Circuit Breaker Type. The voltage rating and the type of insulation requires tests specific to the circuit breaker design. a. Low-Voltage Circuit Breakers. The protective tripping device is an integral part of the circuit breaker. The unit may be equipped with an electromechanical trip unit or a static trip unit. Electromechanical units may have a thermal (inverse time overload) protection, magnetic (instantaneous short-circuit) protection, or a thermal-magnetic combination. Static units are solid-state electronic devices which provide many additional protective features. All tripping times should be checked to assure they meet the manufacturers time-current characteristic tolerance band. Use a circuit breaker test set and make field adjustments in accordance with the test sets instruction. Do not compromise the protection by exceeding the trip units adjustable range. Field repair is not recommended. If the trip unit is not functioning properly it should be replaced. It may also be advisable to replace the entire circuit breaker. b. Oil-Insulated Circuit Breakers. Check oil dielectric strength, power factor, interfacial tension, and color in accordance with requirements given for insulating liquid tests in AFH 32-1282V2. c. SF6-Insulated Circuit Breakers. Check for moisture content. Service-aged moisture content should be less than 300 parts per million (ppm) by volume (10 ppm new). Do not energize any gas-insulated equipment where the gas density is less than 50 percent of nominal or if the moisture content exceeds 1,000 ppm. Moisture content should be checked with a moisture analyzer approved for SF6 gas. Follow the procedures in and as often as recommended by the manufacturers instructions. Some SF6 bottles have a sample valve. Some SF6 bottles are sampled through a filling valve using a valved sampling tube arrangement which prevents contaminants from entering the SF6 bottle. It is recommended that trained contract personnel do the checking.
53
AFH 32-1282V1
AFH 32-1282V1
CHAPTER 6. CIRCUIT BREAKER EVALUATIONS 6-1. Circuit Breaker EPM Reports. Each installation should prepare local blank EPM report forms to be filled out by the inspecting technicians. (See Paragraph 1-4.) The following tables indicate data which may need to be recorded. Evaluate the extent of data required based on your installation needs and maintenance ability.
a. Basic Circuit Breaker Information To Be Determined Before The Inspection. Provide a suitable record header with blank spaces for insertion of the following data given in Table 6-1.
AFH 32-1282V1
AFH 32-1282V1
c. Inspection Items To Be Covered. Inspection items to be covered will vary dependant upon the voltage level and insulation type of the circuit breaker as covered in the following paragraphs of this chapter. Table 6-2 indicates circuit breaker readings and appropriate evaluation paragraphs for passing criteria applying to the various circuit breaker types. See AFH 32-1282V2 for bushing, instrument transformer, and surge arrester requirements.
Inspection includes both external and internal inspections. External inspections are covered in Table 6-3. Follow procedures of Table 6-4 for internal tank inspections. 54
AFH 32-1282V1
AFH 32-1282V1
Component Inspection 4. Protective device operation/calibration a. Control circuits b. Relays c. Alarms d. Gauges e. Relief devices f. Calibrations 5. Oil insulation a. Filling b. Filtering c. Sampling 6. SF6 insulation3 7. Operation under load a. Malfunctions b. Friction 8. Heater operation
May require lubrication, cleaning, adjusting, and aligning. For infrared checking see Paragraph 3.1.a. 3 See Table 6-2.
55
AFH 32-1282V1
AFH 32-1282V1
Table 6-4. Internal high-voltage circuit breaker tank procedures and checks
1. Accessing the tank a. Remove covers, lower tank, extract oil or gas and transfer to approved storage or processing equipment b. Ventilate and wipe down oil-insulated units. Pull a vacuum on gas insulated units. c. Check, measure, adjust, lubricate, align, and repair: (1) Contacts (2) Interrupters (3) Internal current transformers (4) Resistors, capacitors, and lift rods d. Replace any desiccant material, if applicable 2. Seal the tank and: a. Refill oil-insulated units to the proper level and inspect for leaks b. Pull a vacuum per manufacturers specified time for gas-insulated units and if no leaks are present refill tank to the proper pressure
6-3. Medium-Voltage Vacuum or Air Insulated Metal-Clad Switchgear Circuit Breakers. Pictures 6-1 and 6-2 indicate protective features on all metal-clad switchgear. Pictures 63 and 6-4 indicate details of air-magnetic arc chutes. Table 6-5 indicates circuit breaker components and appropriate inspection actions for circuit breakers withdrawn from the switchgear and de-energized unless indicated to be in the test position. BE CAUTIONED THAT HIGH POTENTIAL TESTING OF VACUUM BOTTLES CAN CAUSE X-RAY EMISSION. USE MANUFACTURERS SAFETY PRECAUTIONS. 56
AFH 32-1282V1
AFH 32-1282V1
57
AFH 32-1282V1
AFH 32-1282V1
58
AFH 32-1282V1
AFH 32-1282V1
1 With circuit breaker in the test position and using a test coupler. 2Remove arc chutes for inspection 3 Record manufacturers recommendation, as found condition, and as left condition. 4 Measure overtravel and determine from manufacturers instructions if any measured overtravel is acceptable. 5
Provide a one-minute alternating-current high potential in accordance with the manufacturers instructions. caution.
See previous
59
AFH 32-1282V1
AFH 32-1282V1
Table 6-6 indicates circuit breaker components and appropriate inspection actions. Drawout circuit breakers should be removed from their enclosures. Stationary circuit breakers should be de-energized and grounded. Pictures 6-5 and 6-6 show the two usual type of low-voltage circuit breakers. Pictures 6-6 and 6-7 show drawout contacts for power and control respectively.
Component inspection 2. Drawout units a. Racking mechanism, cell fit and element alignment. Verify contact wipes and other adjustments are correct. b. Operating mechanism functions both electrically and mechanically c. Lubrication requirements d. Control devices
On nonsealed units.
60
AFH 32-1282V1
AFH 32-1282V1
61
AFH 32-1282V1
AFH 32-1282V1
62
AFH 32-1282V1
AFH 32-1282V1
63
AFH 32-1282V1
AFH 32-1282V1
64
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
66
AFH 32-1282V1
AFH 32-1282V1
Operation may be electrically or mechanically initiated. Safety interlocks may prevent operation. Optional monitoring devices are available. Interrupter switches, like circuit breakers, have a contact and arc extinguishing system, an operating mechanism, and an abnormal-conditions current-detection system. Air is the usual insulating medium and switches are designed only for use on medium-voltage systems. a. Contact and Arc Extinguishing Process. Generally switches are constructed with both main and arcing contacts. The main contacts carry the continuous current and the arcing contacts break the arcing current. Arc chutes are coated to generate a de-ionizing gas under the heat of the arc. The design lengthens and thus cools the arc promoting rapid extinguishing. 67
AFH 32-1282V1
AFH 32-1282V1
b. Operating Mechanism. Stored energy from a heavy-duty spring provides the force necessary to open or close the switch. The switch handle charges the spring when operated either up for closing or down for opening. The stored energy of the spring operates independently of the operator. Switches cannot be teased into any intermediate position. All mechanisms can be manually operated. Many interrupter switches are provided with motor operators controlled by the current-detection system. Motor operators have a well documented history of operating problems. c. Current Detection Systems. The drawback to interrupter switches as compared to circuit breakers is their current-detection system under abnormal operating conditions. (1) Overloads. On overloads fuses will operate to open the circuit. (2) Fault Conditions. Fuses will operate properly on line-to-line faults. They may not operate on line-to-ground faults. Therefore safety precautions must be observed when manually opening switches. d. Precaution in Opening or Closing Switches. These operations can be extremely dangerous if they are performed when there is an uncleared fault condition at the switch. Safety orders should be very clear that the operator must stand to the side of the switch and wear a blast suit and fireresistant clothing. e. Safety Interlocks. Interlocks are required by industry standards to prevent contact with energized switch components. Pictures 7-1, 7-2, 7-3, and 7-4 show features that ensure energized parts are isolated from operating personnel.
68
AFH 32-1282V1
AFH 32-1282V1
69
AFH 32-1282V1
AFH 32-1282V1
70
AFH 32-1282V1
AFH 32-1282V1
(1) Standard Switch Interlock Safeguards. Fuses are not accessible unless the switch is open. The switch cannot close when the fuses are accessible. Access to the switch compartment is prevented unless the stored energy mechanism is discharged or blocked. (2) Drawout Switch Interlock Additional Safeguards. Movement of the removable element is prevented when the switch is in the closed position. The switch cannot be closed (mechanically or electrically) when the removable element is at any intermediate point between the disconnected and connected positions. Movement of the removable element to and from the connected position is prevented if the operating spring is in the charged position. f. Optional Monitoring Devices. Fuses are often provided with blown fuse indicators. Surge arresters, instrument transformers, meters, relays, and additional interlocks may be installed to protect and monitor the interrupter switch.
Perform contact-resistance tests across each switch blade and fuse holder and insulation resistance tests on each pole phase-to-phase and phase-to-ground for one minute with a test voltage in accordance with Table 5-1. See Table 7-5 for test requirements. Always test interrupter switches in the test position. If there is no test position (stationary interrupter switches) test after the interrupter switches have been de-energized and grounded. Tests must be done in accordance with the safety requirements for de-energized electrical line work given in Paragraph 1-4. Convert measured insulation resistances from the test temperature to the reference temperature of 20 degrees C (see AFMAN 32-1280(I)).
71
AFH 32-1282V1
AFH 32-1282V1
Type Ambient temperature Contact resistance pole-to-pole (microhms) Insulation resistance (megohms)
Investigate any values which deviate from adjacent poles or similar switches by more than 50 percent.
Each installation should prepare local blank EPM report forms to be filled out by the inspecting technicians. (See Paragraph 1-4.) The following tables indicate data which may need to be recorded. Evaluate the extent of data required based on your installation needs and maintenance ability. a. Basic Interrupter Switch Information To Be Determined Before the Inspection. Provide a suitable record header with blank spaces for insertion of the following data given in Table 7-6.
AFH 32-1282V1
AFH 32-1282V1
b. Basic Inspection Items To Be Checked. Provide an inspection listing with column headings covering items to be checked off for each listed number given in Table 3-4. c. Inspection Items To Be Covered. List inspection items to be covered. Table 7-5 indicates interrupter switch readings and appropriate evaluation paragraph for passing criteria. Table 7-7 indicates interrupter switch components and appropriate inspection actions.
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
75
AFH 32-1282V1
AFH 32-1282V1
76
AFH 32-1282V1
AFH 32-1282V1
77
AFH 32-1282V1
AFH 32-1282V1
78
AFH 32-1282V1
AFH 32-1282V1
c. Construction Requirements. Assemblies are built to specific minimum industry standards as covered by Table 8-1. Major medium-voltage switchgear differences are given in Table 8-2.
Voltage level
Device requirement
Title Metal-clad switchgear1 Metal-enclosed interrupter switchgear Metal-enclosed lowvoltage power circuit breaker switchgear Deadfront distribution switchboards Medium, Type MC Medium, Type MEI Low Drawout circuit breakers Stationary or drawout switches Stationary or drawout circuit breakers Stationary or drawout switching devices
Low
Metal-clad switchgear is also classified as metal-enclosed. Insulated bus in some cases may be available as an optional manufacturers provision, but bare bus is the minimum requirement.
79
AFH 32-1282V1
AFH 32-1282V1
80
AFH 32-1282V1
AFH 32-1282V1
Tests are generally limited to ground resistance tests on permanent ground systems, and insulation resistance tests on buses and control wiring. See Table 83 for test requirements.
Readings should identify location or be provided in a separate report. See Table 5-1 for insulation resistance test values.
Always test assemblies in accordance with the safety requirements for energized electrical line work given in Paragraph 1-4. Convert measured insulation resistances from the test temperature to the reference temperature of 20 degrees C (see AFMAN 32-1280(I)). Use a hand-held corona tester to determine if corona is being produced. If corona is present investigate insulation and insulators for corrosion, tracking, or dirt buildup and replace if necessary. Infrared tests should be done as covered in Paragraph 3-1. 81
AFH 32-1282V1
AFH 32-1282V1
a. Corona Discharges. Electrically charged bodies exert forces (electrostatic) on one another. If the potential gradient between bodies is high enough, the breakdown level of air (as affected by pressure, temperature, and humidity) can be exceeded. This breakdown can cause an electric discharge which results in the formation of corona. Any formation of corona indicates an insulating deficiency. In switchgear, corona (if it occurs) is usually localized in the tiny air gaps between bus bars and its insulation or, between two contiguous insulating members. b. Corona Actions. Corona ionizes the surrounding air converting oxygen to ozone (O3) and nitrogen and humidity to nitric acid (HNO3). These two by-products along with ion and electron bombardments of organic materials will damage assemblies. Corona should be checked for using a detector at each assembly EPM review. Do not wait until the distinct smell, the popping, spitting, crackling or frying noise, or communication reception interference indicates corona formation. Each installation should prepare local blank EPM report forms to be filled out by the inspecting technicians. (See Paragraph 1-4.) The following tables indicate data which may need to be recorded. Evaluate the extent of data required based on your installation needs and maintenance ability. a. Basic Assembly Information To Be Determined Before the Inspection. Provide a suitable record header with blank spaces for insertion of the following data given in Table 8-4.
82
AFH 32-1282V1
AFH 32-1282V1
b. Basic Inspection Items To Be Checked. Provide an inspection listing with column headings covering items to be checked off for each listed number given in Table 3-4. c. Inspection Items To Be Covered. List inspection items to be covered. indicates assembly readings and appropriate evaluation paragraph for passing criteria. indicates switchgear/switchboard assembly components and appropriate inspection items. Table 8-3 Table 8-5
83
AFH 32-1282V1
AFH 32-1282V1
84
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
AFH 32-1282V1
(1) Electrolytes. Lead acid batteries have an acidic electrolyte solution of sulfuric acid (H2SO4) and their nominal voltage is 2.0 volts per cell. Nickel cadmium batteries use an alkaline electrolyte (potassium hydroxide) and their nominal voltage is 1.2 volts per cell. (2) Construction. The physical size of a vented battery will generally be larger than a valve regulated battery providing the same energy because of the difference in construction. (3) Details. Pictures 9-1, 9-2, 9-3, and 9-4 show equipment and maintenance details. (a) Vented Batteries. Vented (flooded) cells are constructed with the liquid electrolyte completely covering (flooding) the closely spaced plates, so that there is a large volume of free electrolyte. Vented units are characterized by a removable vent cap which allows the electrolyte to be checked and adjusted as needed. Overcharge will produce gases which vent through the cell, requiring regular water replacement. Vent caps must be accessible and are provided with flame arresters. Gassing requires ventilation to avoid explosive possibilities and possible corrosive damage to battery terminals. (b) Valve-Regulated Batteries. Valve-regulated cells are sealed, with the exception of a valve that opens periodically to relieve excessive internal pressure. Once the pressure is relieved the valve closes and reseals. No cell check of an electrolyte level nor the specific gravity of each cell can be made. These batteries are not maintenance-free as some 10 or more maintenance checks are still necessary. Outgassing of these batteries is low at normal charge rates, but it can occur when there is a battery or battery charger failure. Cells can pose a hazard if enclosed so as to inhibit cooling air, or installed so as to place them in the heat flow of electronics which may occupy the same enclosure. 86
AFH 32-1282V1
AFH 32-1282V1
87
AFH 32-1282V1
AFH 32-1282V1
88
AFH 32-1282V1
AFH 32-1282V1
c. Precautions. Safety precautions cannot be ignored, since every station battery installation presents hazards. The importance of using safety equipment, such as rubber gloves, goggles, aprons, and of having an eyewash water bottle present, cannot be overemphasized. The three major hazards are from the electrolyte in the battery, the gases emitted by the battery, and the potential electrical short circuit capability available from the batterys stored energy.
Readings and tests must be done in accordance with the safety requirements for energized electrical line work given in Paragraph 1-4. Convert indicated readings from the test temperature to the reference temperature of 77 degrees F (25 degrees C) (see AFMAN 32-1280(I)). Also see suggested test accessory list for battery maintenance in AFMAN 32-1280(I). a. In-Service Energized Readings. The following readings should be taken at not less than the indicated interval as given in Table 9-1. Methods for checking resistances include using lowresistance ohmmeters or measuring the millivolt drop during capacity testing. Resistance values may vary greatly, from less than 10 micro-ohms to 100 micro-ohms. If significant changes in resistances (20 percent above installation value) occur, or manufacturers recommended limits are exceeded, workers should take corrective action. Maintenance personnel should refer to manufacturers recommendations regarding cleaning and re-torquing connections.
89
AFH 32-1282V1
AFH 32-1282V1
Monthly
Quarterly
Annually
1
1. 2. 3. 4. 5. 6. 7. 1. 2. 3.
90
AFH 32-1282V1
AFH 32-1282V1
(1) Importance of Correct Conductive Path Resistances. The majority of catastrophic battery failures can be traced to problems within the conduction path of the battery system. The conduction path includes all internal buses, terminal posts, and connecting straps between cells. (2) Connections. All connections must remain tightened to manufacturers recommended torque specifications to avoid sparking or excessive heat buildup, possibly resulting in a battery fire. All connections should be checked for proper torque requirements annually and after a heavy discharge. Cell-to-cell and cell-to-terminal resistances should be checked and recorded after torquing. b. Out-of-Service Energized Tests. The objective of battery testing is to ensure that the battery system can store the required energy and deliver it efficiently when the need arises. A capacity test can evaluate the batterys ability to store the required energy and deliver constant current over extended periods. An integrity test can determine whether internal battery deterioration or connection path problems (such as corrosion) would prevent efficient delivery of energy. Each of these tests requires that the battery be disconnected from the battery charger and tested using an artificial load. The test disconnection period must have been approved and scheduled so that equipment operation affected by these tests is not jeopardized. This means an approved and specific date and period for the test. (1) Capacity Load Test. Capacity test duration should be equal to the duty period for which the battery was sized (usually 8-hours). The procedure is given in Table 9-2. Provide at least every 5 years until the battery shows signs of degradation or has reached 85 percent of its life expectancy. Then provide the test every year. Sufficient degradation capacity to warrant annual capacity testing varies among battery types. (See Table 9-3.)
91
AFH 32-1282V1
AFH 32-1282V1
92
AFH 32-1282V1
AFH 32-1282V1
(2) Integrity Load Test. Provide anywhere from quarterly to annually depending on the relative importance of the equipment that the battery supports. The procedure is given in Table 9-4.
Each installation should prepare local blank EPM report forms to be filled out by the inspecting technicians. (See Paragraph 1-4.) The following tables indicate data which may need to be recorded. Evaluate the extent of data required based on your installation needs and maintenance ability.
93
AFH 32-1282V1
AFH 32-1282V1
a. Basic Battery Installation Information To Be Determined Before the Inspection. Provide a suitable record header with blank spaces for insertion of the following data given in Table 9-5.
Cell type Cell size No. of cells Ampere-hours at ______ hour rate Nominal specific gravity at 77 degrees F1 Nominal system float voltage Battery charger Manufacturer Serial no. Instruction manual Nominal system Float voltage
94
AFH 32-1282V1
AFH 32-1282V1
b. Basic Inspection Items To Be Checked. Provide an inspection listing with column headings covering items to be checked off for each listed number given in Table 3-4. c. Inspection Items To Be Covered. List inspection items to be covered. Tables 9-1, 9-2, 9-3, and 9-4 indicate battery installation readings and tests and appropriate evaluation paragraph for passing criteria. Tables 9-6, 9-7, and 9-8 indicate battery installation components and appropriate inspection actions.
Add water to the high water line Deviation of more than 3 degrees C requires determination of cause1, Increase of more than 20 percent above installation value, clean, retorque, and retest connections Adjust to be in recommended operating range Provide equalizing charges if individual cell or average for all cells specific gravity drops more than 10 points2 Provide an equalizing charge immediately if any cell voltage is below 2.13 volts at the time of inspection
Replace for short-circuited units. Adjust environment if caused by outside conditions. Adjusted for temperature and electrolyte level. Drop is for difference of individual cells from average of cells at time of inspection or for all cells from the average installation value.
95
AFH 32-1282V1
AFH 32-1282V1
96
AFH 32-1282V1
AFH 32-1282V1
CHAPTER 10. PROTECTIVE SENSING, PROCESSING, AND ACTION DEVICES 10-1. Device Performance.
function: ! ! ! a. to sense and indicate operating parameters within design requirements for user information (instruments and meters) to process the data when operating parameters have increased to values in excess of design requirements (protective relays and alarms) to actuate protective devices when such action is needed to prevent equipment damage (overcurrent and fault interrupting protective and switching devices). Indicating Devices. Indicating devices include instruments and meters. Electrical systems operate because control devices or systems
(1) Electrical Instruments. Industry standards define electrical instruments as devices used to measure the present value of electrical quantities under observation. An instrument may be an indicating instrument or a recording instrument. By this definition ammeters, voltmeters, and frequency meters are instruments, not meters.
97
AFH 32-1282V1
AFH 32-1282V1
(2) Electrical Meters. Industry standards define electrical meters as devices used to measure and register the cumulative value of electrical quantities with respect to time. For example, a watthour meter is used to measure and register the amount of average electrical power over a period of time. (3) Electrical Measurements. Many units measuring ac values will do so using average, peak, or effective values, based on the assumption that the system provides a pure sine wave. With the growing use of solid-state equipment, the waveforms being measured are increasingly less like a pure sine wave. Resulting measurements made from equivalent rms instruments or meters can be misleading, but such results are not necessarily the fault of the measuring device. Whenever possible use true rms instruments or meters. b. Protective Relays. A relay is an electrical device designed to interpret input data in a prescribed manner. When specific input conditions occur, the relay responds to cause contact operation or a similar sudden change in associated electric control circuits. Protective relays are designed to operate circuit breakers and contactors, usually medium-voltage units. Relays can be set more precisely than fuses. Relays are adjustable with respect to both time and current, a feature that also applies to solid-state, direct-tripping, low-voltage circuit breakers. Input data analyzed is usually electrical, but may be mechanical or thermal, or evaluate other conditions or a combination of conditions. Electrical conditions can be overcurrent, overvoltage or undervoltage, a combination of current and voltage, current balance, direction of current flow, frequency, impedance, or other electrical data.
98
AFH 32-1282V1
AFH 32-1282V1
c. Alarms. A predefined change in the condition of equipment or the failure of equipment to respond correctly can operate audible or visual indications to announce that the condition needs personnel attention. Alarms can vary from target indications or relays or contact closures operating audible gongs with silencing switches or annunciators with nonautomatically reset devices. d. Safety Items. Isolate control circuits, that is remove control fuses, open test switches, and operate selector controls as required. (1) Other Circuits. Keep other overlapping and interconnecting control circuits associated with operating equipment de-energized if necessary for safety. (2) Secondary Control Circuits. Isolate control, current, and voltage transformer secondary circuits to protect against unintentional operation from tests on the device being checked.
10-2. Device Testing. Always test devices in the test position. If there is no test position operate after the device has been de-energized and grounded. Tests must be done in accordance with the safety requirements for de-energized electrical line work given in Paragraph 1-4. Electrically confirm that current transformer and voltage transformer secondary circuits are intact.
a. Instruments and Motors. Calibration and adjustment are required to meet the requirements of AFMAN 32-1280(I) and to meet the manufacturers published data on accuracy. b. Protective relays. Verify satisfactory performance of each control, protective functions and alarm in accordance with the protection scheme and manufacturers instructions. Perform the tests given in Table 10-1. 99
AFH 32-1282V1
AFH 32-1282V1
Criteria Manufacturers instruction manual System protective requirements System protective requirements System protective requirements
c. Pickup Parameters. Relays are selected to perform certain functions. To standardize on reference use, they are given device function numbers by IEEE C37.2 (Standard Electrical Power system Device Function Numbers). (Device function numbers also describe other electrical power apparatus equipment in addition to relays.) Device function numbers readily identify devices in drawings, diagrams, instruction books, publications and specifications. The use of 52 for circuit breakers, 51 for an ac time overcurrent relay, 65 for a governor, and 86 for a lockout relay provides a simple brief method of designating the devices operational performance. Table 10-2 indicates the usual pickup parameters for relays found in substation switchgear.
100
AFH 32-1282V1
AFH 32-1282V1
101
AFH 32-1282V1
AFH 32-1282V1
d. Pictures 10-1 and 10-2 show an electromechanical relay and a solid-state relay respectively.
10-3. Installation-Wide Operating Systems. Systems include supervisory control and data acquisition (SCADA) systems and digitally-controlled Air Force switchgear systems. Perform maintenance in accordance with Operations and Maintenance Manuals furnished with the systems. Pictures 10-3 and 10-4 show installation-wide operating systems. 10-4. Protective Sensing, Processing, and Action Device EPM Reports. Each installation should prepare local blank EPM report forms to be filled out by the inspecting technicians. (See Paragraph 1-4.) The following tables indicate data which may need to be recorded. Evaluate the extent of data required based on your installation needs and maintenance ability.
a. Basic Assembly Information To Be Determined Before the Inspection. Provide a suitable record header with blank spaces for insertion of the following data given in Table 10-3.
AFH 32-1282V1
AFH 32-1282V1
103
AFH 32-1282V1
AFH 32-1282V1
104
AFH 32-1282V1
AFH 32-1282V1
b. Basic Inspection Items to Be Checked. Provide an inspection listing with column headings covering items to be checked off for each listed number given in Table 3-4. c. Inspection Items To Be Covered. Table 10-1 indicates relay tests and appropriate criteria. Table 10-4 indicates instrument, metering, and protective relay general checks. For specific repairs and replacements see the manufacturers maintenance instructions.
AFH 32-1282V1
Notes
AFH 32-1282V1
106
AFH 32-1282V1
Notes
AFH 32-1282V1
107
AFH 32-1282V1
Notes
AFH 32-1282V1
108
AFH 32-1282V1
Notes
AFH 32-1282V1
109
AFH 32-1282V1
Notes
AFH 32-1282V1
110