Professional Documents
Culture Documents
Ioc Commissioning Safety
Ioc Commissioning Safety
Plant commissioning is the first of many start-ups; Potential hazardous : Ability to operate not proven; Many unknown factors.
MANPOWER DEPLOYMENT
Multi-disciplinary core team years prior to commissioning; including team leader 2
Balance team deployment at least 1 year prior to commissioning; Blend of experienced and new in the ratio of 3:1; Deploying few senior members of project team for maintenance jobs; Team leader should able to command the resources; Top management support to the team.
TRAINING
Extensive theoretical and field training on similar plants; Training at critical equipment vendors workshop; Training simulator commissioning; must be placed 1 year before
Structured training on emergency responses, handling of hazardous chemicals; Licensor training; Inducting commissioning group for HAZOP; Mock operational drills.
The Process;
Starting Procedures;
Limits Of Operation;
Shutdown Procedures;
Keep maintenance records; Make detailed designs of any changes and additions made
Technical manual for process technology and equipment SOPs; Safety valve and rupture disk manual, listing the design basis for each safety device, and giving the procedure for taking it out of service; Training manual detailing the program for new personnel; Safety manual depicting emergency response etc.; policies, procedures
PRE-COMMISSIONING
Pre-commissioning completion; activities overlap mechanical
Plant is segregated into manageable systems / subsystems / flushing loops; Checking of design conformity; Checking status of Electrical, Mechanical & Instrument Installations; No Load / Load run of rotary equipment; Flushing, Cleaning, Drying etc.; Loop checking should also start after flushing.
CHECK LISTING
Why to do? When to do? Who is to do? How to do? What to do?
To be done as per system/sub-systems; System is as per P&ID; Identifying skewness of Flanges; Short/Long Bolting; Use of proper gasket color codes; Support systems.
Contd..
Location of drains/vents; Column/Vessels internals as per drawing; Positioning of instruments; Valve / CVs installations;
Implementation of Work permit system; Fire fighting facilities extinguishers etc.; including positioning of
Clearly defined emergency exits , with display boards; Removal of debris / connections; temporary structures and power
Tested Paging systems & availability of Walkie talkies; Readiness of OWS /CRWS system with ETP in operation; contd..
O2 content in N2 must be checked before inertisation; Furnace lit up with pilot only; keeping main valve blinded, purge fire box min. for 15mnts after each attempt; Water /Condensate draining from all low points after gas backing up; Condensate draining before charging steam headers; contd..
All supports are un-locked; Fine mesh strainer on rotary equipment; ESD/De-pressurisation systems check; Flare area to be cordoned chances of during start up. fire balls