You are on page 1of 27

SAFETY IN COMMISSIONING AND START UP OPERATIONS

S.K. Ghosh, IOCL S.M. Vaidya, IOCL


12th August, 2010

PLANT START-UP AND COMMISSIONING

Plant commissioning is the first of many start-ups; Potential hazardous : Ability to operate not proven; Many unknown factors.

Expensive; ROI severely affected; Financial viability under question.

ELEMENTS OF SUCCESSFUL COMMISSIONING

MANPOWER DEPLOYMENT
Multi-disciplinary core team years prior to commissioning; including team leader 2

Balance team deployment at least 1 year prior to commissioning; Blend of experienced and new in the ratio of 3:1; Deploying few senior members of project team for maintenance jobs; Team leader should able to command the resources; Top management support to the team.

TRAINING
Extensive theoretical and field training on similar plants; Training at critical equipment vendors workshop; Training simulator commissioning; must be placed 1 year before

Structured training on emergency responses, handling of hazardous chemicals; Licensor training; Inducting commissioning group for HAZOP; Mock operational drills.

The Process;

Conditioning and Special Equipment;

Starting Procedures;

Limits Of Operation;

Shutdown Procedures;

Develop work and safety procedures;

Specify typical maintenance activities;

Select and purchase maintenance supplies and spare parts;

Negotiate with vendors and contractors;

Keep maintenance records; Make detailed designs of any changes and additions made

Technical manual for process technology and equipment SOPs; Safety valve and rupture disk manual, listing the design basis for each safety device, and giving the procedure for taking it out of service; Training manual detailing the program for new personnel; Safety manual depicting emergency response etc.; policies, procedures

Maintenance procedures specific to the new plant; Change Management .

PRE-COMMISSIONING
Pre-commissioning completion; activities overlap mechanical

Plant is segregated into manageable systems / subsystems / flushing loops; Checking of design conformity; Checking status of Electrical, Mechanical & Instrument Installations; No Load / Load run of rotary equipment; Flushing, Cleaning, Drying etc.; Loop checking should also start after flushing.

CHECK LISTING
Why to do? When to do? Who is to do? How to do? What to do?

WHAT TO DO IN CHECK LISTING?

To be done as per system/sub-systems; System is as per P&ID; Identifying skewness of Flanges; Short/Long Bolting; Use of proper gasket color codes; Support systems.

Contd..

WHAT TO DO IN CHECK LISTING?

Location of drains/vents; Column/Vessels internals as per drawing; Positioning of instruments; Valve / CVs installations;

SEQUENTIAL PRE-START UP SAFETY CHECKS MULTI LAYER APPROACH


Safety checks by Licensors compliance; In-house multidisciplinary compliance; OISD Audit - compliance; In-house multidisciplinary audit before feed-in; Adherence to Plant/Equipment check list; *External audit is done e.g. Shell Global did for PNC. audit as per OISD Format

OBJECTIVE OF PRE-START UP SAFETY REVIEW


Construction as per design specification; P&IDs are complete; System Protection Interlocks/ ESDs; O&M & Safety system / Procedures /Documentation; Training & its effectiveness; Statutory compliances are met;

MINIMUM FACILITIES BEFORE START UP

Implementation of Work permit system; Fire fighting facilities extinguishers etc.; including positioning of

Clearly defined emergency exits , with display boards; Removal of debris / connections; temporary structures and power

Tested Paging systems & availability of Walkie talkies; Readiness of OWS /CRWS system with ETP in operation; contd..

MINIMUM FACILITIES BEFORE START UP


Availability of adequate PPEs /First Aid boxes; Judicious implementation of isolation scheme; Properly stenciled Utility points with connecting hoses / lancers; Unlocking of springs/ supports of all headers; All gas / hydrocarbon detectors are tested and kept on; ESD s are tested , documented and kept activated etc.; Flare system is in position.

OTHER START UP SAFETY ISSUES


Multidisciplinary group accountability for flange box-up/RTJ Joints; Best leak test is at operating severity; Hydrogen leakage depressurization ; should only be attended after

O2 content in N2 must be checked before inertisation; Furnace lit up with pilot only; keeping main valve blinded, purge fire box min. for 15mnts after each attempt; Water /Condensate draining from all low points after gas backing up; Condensate draining before charging steam headers; contd..

OTHER START UP SAFETY ISSUES


Catalyst injection lines of petrochemical plants to be flushed with mineral oils; In Naphtha Cracker Units important headers to be dried up to (-)65/70oC to avoid hydrate formation; White oil tanks to be commissioned with at least 5 cm of water level; Black oil tank should be commissioned dry, top M/H cover may be kept open if required; Blind Lists are ready; All safety valves, including TSVs are in line; contd..

OTHER START UP SAFETY ISSUES


LPD/HPV valves closed and capped;

All supports are un-locked; Fine mesh strainer on rotary equipment; ESD/De-pressurisation systems check; Flare area to be cordoned chances of during start up. fire balls

You might also like