WEEKLY PROGRESS REPORT

3/24/2012

Project Informations Contract Start Date: Mobilization Date: Project Comp. Date: Resources Responsible Staff: Project Manager Project Engineer Site Engineer Electrical Engineer Foreman Labour Mason Carpentar Steel Fitter Plumber Electrician Painter Operators Helpers A/C Mechanics Office Assistant Security

4-Feb-12 14-Jan-12

Construction Period Days Elapsed Days Balance Machinery Excavator Mixer Machine

240 Days 47 (19.58%) 193 (80.42%) 1 1

Planned Progress 5.670 Actual Progress 3.372 Balance 2.198 Expected Progress Next Week (By Site Engineer)

Riaz Ahmed

Comments (Project Manager)

Comments (Planning Engineer)

Other Ranks Accommodation, MAM(A)

WEEKLY PROGRESS REPORT

3/24/2012