Draw the network for the following activities and find the critical pa

EX- 21
Activity
1-2
1-3
1-5
2-3
2-6
3-4
4-7
5-6
6-7

Duration(days)
3
4
14
10
5
4
6
1
1

Ex-26

EX-22
Duration(days)
4
2
5
7
7
2
5

Ex-27

Activity
Duration(days)
1-2
9
1-4
4
1-3
7
2-5
7
3-4(dummy)
0
3-6
5
4-6
8
5-6
8
5-7
9
5-8
10
6-7
6
7-9
10
8-9
2

Ex-30
Activity
Duration(days)
1-2
1-3
1-4
2-3(dummy)
3-4
3-5
4-5(dummy)
5-6
5-7
6-7

Activity
1-2
1-3
1-4
2-3
2-5
3-5
4-5

Activity
1-2
1-3
2-4(dummy)
2-7
3-4(dummy)
3-8
4-5
5-6
6-7(dummy)
6-8(dummy)
7-9
8-9
9-10
10-11

Duration(days)
3
8
0
1
0
2
4
7
0
0
5
6
8
9

Ex-31

4
7
6
0
5
7
0
5
6
0

Activity
A
B
C
D
E
F
G

Immediate Predecessors
Duration(days)
____
10
____
9
A
9
A
8
B
7
B
11
D,E
5

Activity
A
B
C
D
E
F
G
H
I

Ex-34
Immediate Predecessors
Duration(days)
____
8
___
6
A
14
A
5
C
11
D
7
B
11
E,F
4
G
18

Activity
A
B
C
D
E
F
G
H
I
J
K
L

Ex-38
Immediate Predecessors
Duration(days)
__
3
A
2
A
4
A
6
B
3
E
2
C
6
D
4
G
4
D
2
J
2
F,H,I
4

Activity
A
B
C
D
E
F
G

Ex-35
Immediate Predecessors
Duration(days)
___
6
___
5
A
4
B
4
B
4
C,D
6
E
6

Activity
A
B
C
D
E
F
G
H

Ex-39
Immediate Predecessors
Duration(days)
___
4
____
7
A
3
A
3
B
2
B
2
D,E
2
F,G
3

ng activities and find the critical path and the duration of the project

Activity
1-2
1-3
1-4
2-4
3-4
4-5

Activity
1-2
1-3
1-4
2-5(dummy)
3-5
4-5(dummy)
5-6
5-7
5-8
6-7(dummy)
7-9
8-11
9-10
9-11
10-11
11-12

Ex-23
Duration(days)
9
8
15
5
10
2

Ex-28
Duration(days)
4
3
3
0
2
0
1
2
3
0
3
5
2
4
0
2

Activity
1-2
1-3
2-4
3-4
3-5
4-6
5-6

Ex-24
Duration(days)
2
8
4
1
2
5
6

Ex-29
Activity
Duration(days)
1-2
4
1-3
3
1-5
2
2-3(dummy)
0
2-4
1
2-5
3
2-6
4
3-7
5
4-6(dummy)
0
5-7(dummy)
0
5-9
6
6-7
2
6-9
4
7-8
1
8-9
5

Ex-32
Duration(days)

Activity
A
B
C
D
E
F

Immediate Predecessors Duration(days)


____
12
___
10
A
5
A
6
B,C
16
D
16

Activity
A
B
C
D
E
F
G
H
I
J
K

Ex-33
Immediate Predecessors
Duration(days)
___
13
A
8
B
10
C
9
B
11
E
10
D,F
8
E
6
H
7
G,I
14
J
18

Duration(days)

Activity
A
B
C
D
E
F
G
H

Ex-36
Immediate Predecessors Duration(days)
___
2
___
4
___
3
A
1
B
6
C
5
D,E
7
F,G
2

Duration(days)

Activity
A
B
C
D
E
F
G
H

Ex-40
Immediate Predecessors Duration(days)
___
1
___
2
___
2
A,B
2
B,C
4
C
1
D
4
G,E,F
8

Activity
A
B
C
D
E
F
G
H
I

Ex-37
Immediate Predecessors
Duration(days)
___
7.8
___
20
___
33
A
18
A
20
B
9
C
9.8
D
8
E,F
4

Ex-25
Activity
Duration(days)
Activity
Duration(days)
1-2
30 6-7
7
1-3
7 7-8(dummy)
0
2-4
10 7-9
7
3-4(dummy)
0 8-9
12
3-10
30 8-10(dummy)
0
4-5
14 9-11
15
4-8
21 10-11
15
5-6
10

Duration(days)

Duration(days)