EXAMPLE OF CPM

EXAMPLE 1
 Prepare an arrow network based on the
events given and overall duration to complete
the project.
 Calculate the earliest start event time and

latest start event time.


 Indicate the critical path and critical activity in

the network diagram that has been prepared.


EXAMPLE 2
a) Prepare an arrow network based on the events given in the
Table 1 below and overall duration to complete the project.
b) Calculate the earliest start event time and latest start event
time.
c) Indicate the critical path and critical activity in the network
diagram that has been prepared in (a).

Activity Duration
(days)

1-2 14
2-3 13
2-4 12
3-6 20
4-5 18
4-6 24
5-8 18
6-7 15
QUESTION 1
a) Prepare an arrow network based on the events given in the
Table 1 below and overall duration to complete the project.
(15 marks)
b) Calculate the earliest start event time and latest start event
time. (7 marks)
c) Indicate the critical path and critical activity in the network
diagram that has been prepared in Question 1 (a).
Activity Duration
(days)

1-2 2
2-3 4
2-4 3
3-5 4
4-5 8
4-6 4
5-6 1
5-7 8
QUESTION 2
a) Prepare an arrow network based on the events given in the
Table 1 below and overall duration to complete the project.
(15 marks)
b) Calculate the earliest start event time and latest start event
time. (7 marks)
c) Indicate the critical path and critical activity in the network
diagram that has been prepared in Question 1 (a).
Activity Duration
(days)

1-2 14
2-3 13
3-4 11
2-4 12
2-6 20
4-5 24
5-8 18
6-7 15
QnA