Professional Documents
Culture Documents
(5) (4,A)
1 4 7
4 14
(3)
6
(8) (6,B) (7)
3 6
5 7 3
The numbers and letters in parenthesis indicate resource requirements. For instance, activity 2-5
needs 15 men and equipment B.
Critical activities cannot be scheduled since they have no float. They have to start at a specified
time and finish at a predetermined date. However, non-critical activities can be scheduled in a
variety of ways.
One obvious schedule is to begin all activities at their earliest Start time.
8 8 17 17
2 5
8 9 8
4 11
0 0 1 4 7 25 25
4 14
3 6
5 7 3
5 15 12 22
Resource aggregation for this case is shown in the first table. It can be seen that no float has been
assigned to any activity. This means that, floats become a safety margin at the end of each chain.
ACTIVITY M/E 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1-2 M 10 10 10 10 10 10 10 10
1-2 E A A A A A A A A
2-5 M 15 15 15 15 15 15 15 15 15
2-5 E B B B B B B B B B
5-7 M 8 8 8 8 8 8 8 8
1-4 M 5 5 5 5
4-7 M 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4-7 E A A A A A A A A A A A A A A
4-6 M 3 3 3 3 3 3
1-3 M 8 8 8 8 8
3-6 M 6 6 6 6 6 6 6
3-6 E B B B B B B B
6-7 M 7 7 7
TOTAL MEN 23 23 23 23 25 23 23 23 28 28 25 25 26 26 26 19 19 12 8 8 8 8 8 8 8
TOTAL A 1 1 1 1 2 2 2 2 1 1 1 1 1 1 1 1 1 1 - - - - - - -
TOTAL B - - - - - 1 1 1 2 2 2 2 1 1 1 1 1 - - - - - - - -
CUMULATIVE MEN 23 46 69 92 117 140 163 186 214 242 267 292 318 344 370 389 408 420 428 436 444 452 460 468 476
CUMULATIVE A 1 2 3 4 6 8 10 12 13 14 15 16 17 18 19 20 21 22 22 22 22 22 22 22 22
CUMULATIVE B - - - - - 1 2 3 5 7 9 11 12 13 14 15 16 16 16 16 16 16 16 16 16
Another schedule is to start each activity as late as possible. Resource aggregation for this case is
shown in the second table. It can be seen that total floats at the start of each activity have been
used. That means; with this schedule, a delay in one activity delays the completion date of the
whole project.
ACTIVITY M/E 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1-2 M 10 10 10 10 10 10 10 10
1-2 E A A A A A A A A
2-5 M 15 15 15 15 15 15 15 15 15
2-5 E B B B B B B B B B
5-7 M 8 8 8 8 8 8 8 8
1-4 M 5 5 5 5
4-7 M 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4-7 E A A A A A A A A A A A A A A
4-6 M 3 3 3 3 3 3
1-3 M 8 8 8 8 8
3-6 M 6 6 6 6 6 6 6
3-6 E B B B B B B B
6-7 M 7 7 7
TOTAL MEN 10 10 10 10 10 10 10 15 20 20 28 27 27 27 27 25 28 21 21 21 21 21 19 19 19
TOTAL A 1 1 1 1 1 1 1 1 - - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL B - - - - - - - - 1 1 1 1 1 1 1 2 2 1 1 1 1 1 - - -
CUMULATIVE MEN 10 20 30 40 50 60 70 85 105 125 153 180 207 234 261 286 314 335 356 377 398 419 438 457 476
CUMULATIVE A 1 2 3 4 5 6 7 8 8 8 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
CUMULATIVE B - - - - - - - - 1 2 3 4 5 6 7 9 11 12 13 14 15 16 16 16 16
When the cumulative figures for Labor, Machinery A, and Machinery B are plotted against time
for comparison, it is realized that;
The earliest start schedule, for all resources require a heavy initial rate of investment which
decreases considerably later in the project.
It is therefore apparent that the available float is purchased in the form of a safety margin,
at the cost of a heavy initial rate of investment.
The latest start schedule, on the other hand, permits a small initial rate of investment but
requires a considerable increase later.
The low initial rate of expenditures in this case is obtained at the cost of consuming all
floats and accepting the risk of a completely critical network.
Following graph demonstrates the resource utilization curves for early and late dates. In the
literature, these curves are known as S-Curves. The name is coming from the ‘S’ shape of the
graph, which is typical in many project. An S-Curve simply shows cumulative values, including
resource usage hours and cost, plotted against the time.
S Curve
Minimum
Total Usage Slope Line
CUMULATIVE USAGE OF RESOURCE "R"
Project Duration
PROJECT TIME
A comprise is possible between these two extremes, which results in a fairly constant work force
and hence a fairly constant rate of investment over the whole project duration and a more efficient
usage of equipment A and B. The development of this compromise schedule is known as Resource
Leveling.
Resource leveling is an attempt to assign resources to project activities in a manner that will
improve productivity and efficiency. We will deal with labor, called the work force, but the same
approach can be used for allocating other resources such as equipment and money.
Why should we level the work force?
A D
4
5 5
1 B E 5 16 16
0 0 3
3 5
3 11
C F
2
6 10
6 6
Crew Size
Normal
Activity Normal Minimum
Duration
A 5 5 1
B 3 4 2
C 6 8 8
D 5 6 3
E 5 4 2
F 10 4 2
10
9
8
7
6
5
4
3
2
1
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
WORK DAYS
Theoretical maximum crew size that would be required if the allocation could be perfectly spread
out over the project duration:
Max crew size = 175 worker-days / 16 days = 10.9 ~ 11 workers per day
This means that it might be possible to accomplish the work with no more than 11 workers per
day. If the theoretical max crew size were 13, no further reduction on the daily allocation would
be possible. Try 12 workers per day and 11 workers per day. No further reduction is possible (than
11 workers/day)
Note: Rarely can a real project approach the theoretical maximum crew size because of work
sequencing and the completion congestion mentioned earlier.
9
8
7
6
5
4
3
2
1
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
WORK DAYS
11
10
9
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
WORK DAYS
CLASS EXAMPLE 2:
Level the daily labor requirement to no more than 10 workers per day, and draw the histogram
for your solution.
A C E G
2 4 6
D d1 I
1 7 8
B F H
3 5
3 8 11 14 15 18
A C E G
2 4 6
3 6 4 2
D d1 I
0 0 1 20 20 7 8 22 22
7 2
B F H
3 5
4 10 6
4 4 14 14
Crew
Normal Duration
Workdays
Size
Worker-days
Minimum
Required
Activity
Normal
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A 3 6 2 1 (2 2 2 )
B 4 8 2 2 (2 2 2 2)
C 6 30 5 3 (3 5 5 5 3 3 3 3 )
D 7 28 4 2 ( 4 4 4 4 4 4 4)
E 4 12 3 2 ( 3 3 3 3)
F 10 30 3 3 (3 3 3 3 3 3 3 3 3 3)
G 2 4 2 1 ( 2 2)
H 6 18 3 3 (3 3 3 3 3 3)
I 2 6 3 3 (3 3)
Total = 142 Daily → 4 4 4 5 8 8 8 10 10 10 10 7 7 7 6 6 6 6 5 5 3 3
9
Workers / day
1 4 8 12 15 21