PAPER THREE
DATE: DECEMBER, 2020 TIME: 6 HOURS
b) With the use of an appropriate diagram describe the matrix organizational structure and
show why its advantageous for an organization that does multiple projects concurrently.
(6 marks)
a) Use the following project data to answer questions below. (Time is given in weeks).
(i) The project completion time, critical activities and all paths for the project Network.
(8 marks)
(ii) The likelihood of completing the project in 60 weeks. (6 marks)