Professional Documents
Culture Documents
RULES / PROPERTIES:
Program Evaluation and Review Technique (PERT) is a scheduling method originally designed to
optimum cost and time criteria. PERT emphasizes the relationship between the time each
activity takes, the costs associated with each phase, and the resulting time and cost for the
PERT is an integrated project management system. These systems were designed to manage
the complexities of major manufacturing projects, the extensive data necessary for such
industrial efforts, and the time deadlines created by defense industry projects. Most of these
management systems developed following World War II, and each has its advantages.
PERT was first developed in 1958 by the U.S. Navy Special Projects. Traditional techniques such
as line of balance, Gantt charts, and other systems were eliminated, and PERT evolved as a
means to deal with the wide-ranging time periods it takes to finish the critical activities of an
overall project.
PERT helps to calculate the probability of success of each activity and the whole project as well.
A vital aspect of PERT is the formula used for the calculation of expected project time. The
project reads:
Where T = expected completion time,
A = optimistic estimate,
Page 1 of 18
M = most likely estimate,
B = pessimistic estimate.
It helps in
Standard deviation looks at how spread out a group of numbers is from the mean, by looking at
the square root of the variance. The variance measures the average degree to which each point
Important Note: In order to calculate the total time duration of the project, the variance of the
Question # 1:
Mc Gee Carpets and Trim installs carpet in commercial offices. McGee is very concerned with
the amount of time it took to complete several recent jobs. Some of her workers are very
Page 2 of 18
unreliable. A list of activities and their optimistic complete time, the most likely time and
pessimistic complete time for new contract are given in the following table.
Standard
Activity A M b Predecessor Mean Variance
deviation
3+ 4 (6)+8/6
A 3 6 8 ----- 0.69 0.83
= 5.8
D 6 7 8 C 7 0.11 0.33
H 3 6 9 F 6 1 1
I 10 11 12 G 11 0.11 0.33
J 14 16 20 C 16.3 1 1
Page 3 of 18
Step 4: Calculate the duration of the project = by constructing the network diagram using the
mean value – Forward pass , backward pass, slack and identify the critical activates.
The mean / duration of the project is the sum of mean of critical activities.
The Variance of the project is the sum of variance of critical activities only.
c- Identify the percentage of success if the project can be success in less than 33 weeks
d- Identify the percentage of success if the project can be completed in more than 34 weeks
-0.068 – ( -.048)
0.412
(ii) What is the probability that the project is completed in 40day , 45 days and 35 days
Q2. President of Fennema construction has developed the tasks durations and predecessor
Page 4 of 18
Mean Variance SD
Activity a m b Predecessor
Time [(b-a)/6]2 (b –a)/6
A 4 8 10 ---- 7.6 1 1
C 8 12 16 A 12 1.77 1.3
D 4 6 10 A 6.3 1 1
E 1 2 3 B 2 0.11 0.3
H 2 2 2 F 2 0 0
I 6 6 6 F 6 0 0
- The sum of duration of critical activities should be considered as the duration of the project.
- The sum of variance of critical activities should be considered as the variance of the whole
project.
- The sum of SD of the critical activities should be considered as the SD of the whole project
- Duration of the whole project = 39.9, Variance of the project = 8.23 , SD of the project = 6.15
Page 5 of 18
Z = (x- mean) /SD of the project ( in case you are calculating for the project)
Z = (x – mean) / SD of the activity ( in case you are calculating for the activity)
Calculate the probability of the project if it can be complete between x 1 and x2 ( interval
statement)
Calculate the prob of the project if it can be completed in less than x time. ( lesser than )
Calculate the prob of the project if it can be completed in more than x time ( more than )
Calculate the prob of the activity if the activity can be completed in x time.
(ii) What is the probability that the project is completed week 36?
Page 6 of 18
Q3. Jeck Kanet Manufacturing produces custom-built pollution control device for medium size
steel mills. The most recent project undertaken by Jack requires 14 different activities. The
optimistic time, most likely time and pessimistic time to complete projects are given in the
table
Activity Precessions a m b
A -- 4 6 7
B --- 1 2 3
C A 6 6 6
D A 5 8 11
E B,C 1 9 18
F D 2 3 6
G D 1 7 8
H E,F 4 4 6
I G,H 1 6 8
J I 2 5 7
K I 8 9 11
L J 2 4 6
M K 1 2 3
N L,M 6 8 10
Page 7 of 18
Q 4. Using PERT find the total duration of the given project which has 16 activities.
A -- 1 2 4
B -- 3 3.5 4
C --- 10 12 13
D -- 4 5 7
E -- 2 4 5
F A 6 7 8
G B 2 4 5.5
H C 5 7.7 9
I C 9.9 10 12
J C 2 4 5
K D 2 4 6
L E 2 4 6
M F,G,H 1 6 6.5
N J,K,L 1 1.1 2
O I,M 5 7 8
P N 5 7 9
What is the probability that the project is completed in 31 days, 29 days, and 33 days .
What is the probability that the project will be completed in less than 29 days
Page 8 of 18
Q5. Southwestern university Project
Calculate the total duration, variance and standard deviation of the project
Estimate the project probability that it will be completed in less than 265 days
Page 9 of 18
Q7- The precedence network diagram in the following figure reflects optimistic, most likely,
a. Convert the diagram into tabular form and mention the predecessors.
b. The expected completion time for each path and its variance.
c. The probability that the project will require more than 49 weeks.
Page 10 of 18
Q8- Mr. Itzaz is a project manager and wants to plan for his new upcoming assignment for
construction of a new block. With the help of his initial working he has developed following
Page 11 of 18
9- Mr. Murad has completed the time and variance estimation for his project with the help of
project
between 34 to 37 weeks
Page 12 of 18
Q10- Jack Kanet is planning to manufacture custom built pollution control devices and for such
- Find the probability that the project will exceed 5 days from the mean time.
- Find the probability that the project will be completed 5 days lesser than mean time.
Page 13 of 18
Page 14 of 18
Page 15 of 18
Page 16 of 18
Page 17 of 18
Page 18 of 18