Professional Documents
Culture Documents
Solution.
In the network, event 1 is the starting event while event 8 is
the end event. There are following four paths from the starting event
to the end event :
8-10- 12
5-812
6 - 8 - 1 1
4-8 14
8-10- 12 7-10 - 15
3-7-9
6
5-710 4
4-6-8
5
3-5-6
FIG. 5.9
Path A:1-2-7-8
Path B:1-2-6-8
Path C :1-3-6-8
Path D:14-5-6-8
The optimistic time for each of the path is equal to the sum
of all to's of activity of that path. Similarly, the pessimistic time and
most likely time of each of the paths can be found. These times are
shown in Table 5.5.
Table 5.5
Path A 1-2-7-8 19 26 35
Path B 1 2 6 8 17 26 40
Path C 1-3-6 8 18 27 36
Path D 1 4 5 6 8 19 28 39
1-2 6 11 8.17
A 2-7 10 12 10.00 26.34
7-8 5 8 12 8.17
1-2 6 11 8.17
B 2-6 4 8 14 8.33 26.83
6-8 7 10 15 10.33
13 3 7 6.67
C 3-6 8 10 12 10.00 27.00
6-8 7 10 15 10.33
14 5 7 10 7.17
D 45 4 8 6.00 28.33
5-6 3 6 4.83
68 7 10 15 10.33
From Table 5.6, we find that path D is critical since Etg for
this path is the maximum.