Question No 1: Consider the network diagram which consists of the following


activities.

Calculate the following time estimates for each activity


Earliest Start Time (EST)
Earliest Finish Time (EFT)
Latest Start Time (LST)
Latest Finish Time (LFT)

Solution No: 1

Activities Duration (EST) (EFT) (LST) (LFT)


=(EST+D) =(LFT-
D)
0-1 2 0 2 0 2
1-2 8 2 10 10 16
1-3 10 2 12 2 12
2-4 6 10 16 16 22
2-5 3 10 13 22 25
3-4 3 12 15 19 22
3-6 7 12 19 12 19
4-7 5 16 21 22 27
5-7 2 13 15 25 27
6-7 8 19 27 19 27
Question No 2:
The time estimates for the activity of the PERT diagram are given in the
table below. Calculate the expected time, variance and standard deviation for
each activity

Solution No: 2

Activity

1-2 1 2 3 2 1/3 1/9


2-3 8 1 12 10 1/3 1/9
0
2-4 2 4 6 4 1/3 1/9
2-5 3 5 7 5 1/3 1/9
3-6 4 5 6 5 1/6 1/36
4-6 7 8 9 8 1/6 1/36
5-7 6 8 10 8 1/3 1/9
6-7 1 4 7 4 1/2 1/4

The End.