Professional Documents
Culture Documents
Don Streu, Kuito Development Mgr, ChevronTexaco Overseas Petroleum, Angola Ruben M. Costa, Head of Production Department, Sonangol DPP, Angola Abstract
By implementing a phased development approach, Angolas Kuito field achieved first oil just 30 months after discovery, making Kuito this countrys first deepwater production. Equally impressive was the continuous emphasis on project safety. Although greater than five (5) million construction hours have accumulated, the corresponding lost workday incident rate is less than one per million hours worked. Kuitos phased development strategy has minimized cycle time while mitigating numerous subsurface uncertainties associated with complex, deepwater turbidite channel systems. This approach was especially beneficial, as there were no analogous, offset reservoirs in the region. It has also provided valuable production and operability information for subsequent subsea well location and facilities enhancement decisions. In addition, phased development has minimized initial capital requirements while accelerating production, helping to fund further developments within Block 14. The Kuito development consists of a Floating Production, Storage and Offloading (FPSO) vessel, a dedicated export buoy, two separate subsea production centers, a separate subsea water injection center, and a remote gas injection well. This paper reviews the unique aspects of progressing Kuito since its April 1997 discovery, discussing how phased development and contracting strategies mitigated project risks for this fast-track project.
Introduction
Block 14 is situated within the Lower Congo Basin, offshore Angola. It covers 4000 square kilometers, in water depths extending from 200 to 2000 meters. The Kuito field is located in the northeastern portion of Block 14 in water depths of over 400 meters. Cabinda Gulf Oil Company (a ChevronTexaco subsidiary) operates this block on behalf of the Block 14 Contractor Group, which consists of Cabinda Gulf (31%), Sonangol P&P (20%), TotalFinaElf (20%), Agip (20%) and Petrogal (9%). Kuito represents the first of nine prolific Block 14 oil discoveries to date. Implementing a phased development strategy has yielded many tangible benefits, including the production of almost 55 million barrels of oil since field discovery, while providing critical reservoir performance information useful to progress subsequent Block 14 developments. Three phases of Kuito development have already been executed (Phase 1A, 1B and 1C), whose scope has included the installation of facilities to process up to 100,000 barrels of oil per day and inject 135,000 barrels of water per day. There have also been 19 producing wells, 9 water injection wells and 1 gas injection well drilled. Production flows from two separate subsea centers to the Kuito FPSO, which can store up to 1.4 million barrels of processed oil. The FPSO is connected to an export buoy, designed to berth VLCC (very large crude carrier) size conventional tankers. Offloading 920,000 barrel parcels takes less than 36 hours. What follows is a review of this development, including the geologic setting, an overview of the Kuito phases and a discussion on the phased approach and contracting strategies that contributed to this deepwater projects economic success.
formations). The Kuito oil accumulation occurs within an Upper Miocene system and consists of vertically stacked, laterally migrating, sinuous events that are up to 700 feet thick. Major sand depositions are primarily associated with the channel axis facies and minor sands occur in overbank or non-channel areas. Sands are also found in vertical injection features that serve to create pressure communication across intervening shales. Reservoir quality in the turbidite channels is excellent with high porosity (25% to 30%) and permeability (3-4 Darcies). Kuitos oil gravity ranges from 18o to 24o API.
consisted of Single Buoy Moorings (SBM) for the FPSO, Coflexip Stena Offshore International (CSOI) for risers and flowlines, and ABB Offshore Technology (ABBOT) for the subsea manifolds/trees/control systems. The consortium approach was an effective way to rapidly integrate the work activities of numerous worldwide locations (Angola, Singapore, Malaysia, Indonesia, Norway, UK, USA, and France), paramount to achieving the projects reduced cycle time goals. Once contracts were executed, the responsibility for resolving all interface issues was given to this contractor consortium. No payment to the consortium until system acceptance Kuitos subsea facilities (export buoy, risers, flowlines, manifolds, and trees) were all paid in fixed, lump sums. The Kuito FPSO is leased from Sonasing, a joint venture between SBM and Sonangol (the Angolan National Oil Company). However, no payments were made to the consortium members until all the facilities were proven operational (systems acceptance). In effect, the consortium carried the project expenses through to Kuito first oil. The cost of the consortium carry was minimal because of a compressed execution schedule. The combination of zero payment until system acceptance along with liquidated damages for late delivery was instrumental in providing the contractor consortium with a very strong motivation to minimize project cycle time while achieving the required equipment quality and performance specifications. Contracting strategy designed to mitigate reservoir-related risks A combination of phasing Kuito and its leased FPSO contract strategy served to mitigate subsurface uncertainties. The contracting plan committed to only a short-term FPSO lease with the following options: upgrade the FPSO at a later date if the expected reservoir performance was observed during Phase 1A purchase a new-build vessel with higher capacity if up-side reservoir performance was observed during Phase 1A terminate the FPSO contract if the downside reservoir performance was observed during Phase 1A, relocating the vessel to another development As the Kuito reservoir has performed as originally characterized, Phase 2A plans are currently being executed to increase water handling and gas compression capacities. However, had either of the other two reservoir outcomes evolved, the contracting strategy provided acceptable contingencies. Production System Performance incentives and penalties Operating charter payments are proportional to the performance of the system in terms of percent of available production realized. This is achieved through a set of performance-related incentives and penalties: liquidated damage and bonus for production throughput, processing quality, gas utilization, gas flaring and environmental compliance. The breadth and composition of these performance incentives and penalties were quite unique when they were instituted.
shunt tube technology that resulted in a lost wellbore. A rigorous review process for introducing new technology, involving the industry experts, identifying alternatives, and defining the downside is key to successful outcomes.
Contracting Plans
A well developed contracting plan, utilizing a contractor consortium to manage complex technical and schedule interfaces, is an effective way to reduce overall project risks and execution costs. With the proper contract terms and provisions, this approach places most of the execution risk responsibilities with the Contractors. Obviously the Contractor will incorporate these execution risks in the contract price. Therefore, this approach should only be used when there are clear cost versus risk benefits and tradeoffs, as was the case with Kuito.
Making full use of the Decision & Risk Analysis (D&RA) processes
Applying D&RA processes throughout Kuito development was a useful technique to help build and share a common team member / stakeholder understanding of the project risks, uncertainties, ranges, rewards, and trade-offs between various decision options.
Concluding Remarks
Phased development is an effective means to minimize reservoir risks in a fast-track project environment. It also limits initial capital requirements and generates early cash flows. Combining this approach with prudent contracting strategies has produced almost 55 million barrels of oil in only 5 years from Kuito field discovery. Kuito is clearly a successful deepwater development, whose experiences have yielded a much better understanding of deepwater Angolan tertiary reservoirs while enhancing the development potential of future deepwater fields.