Project Close Out Phase
Mapping of Construction Project Life Cycle and PMBOK
Project Delivery System, Contract System
The Brief, Identification of alternatives, Site Investigation, Public Input, Code Analysis, Preliminary Cost Estimate, Financial Feasibility Analysis, Funding, Site Selection and Land Acquition Project Charter
Schemati c Design Detail Design
Legal/Contract Issue, Planning & Scheduling, Budgeting and Cost System, Organizing of Worksite, Subkontraktor, Project Organization Procurement Management Scope Management Time Management Cost Management HR Management Risk Management
Project Monitoring & Control, Safety Management, Material Management, Documentation and Communication
PMBOK Side
Earn Value Performance Report
Scope Management
Knowledge Area & Processes
PM Mapping
Initiating Planning Executing
Monitoring & Controlling 4.4 Monitor & Control Project Work 4.5 Perform Integrated Change Control 5.4 Verify Scope 5.5 Control Scope
Closing
4. Project Integration Management
4.1 Develop Project Charter
4.2 Develop Project Management Plan
4,3 Direct & Manage Project Execution
4.6 Close Project or Phase
5. Project Scope Management
5.1 Collect Requirements 5.2 Define Scope 5.3 Create WBS 6.1 Define Activities 6.2 Sequence Activities 6.3 Estimate Activity Resources 6.4 Estimate Activity Duration 6.5 Develop Schedule 7.1 Estimate Costs 7.2 Determine Budget 8.1 Plan Quality 8.2 Perform Quality Assurance 9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage Project Team 10.3 Distribute Information 10.4 Manage Stakeholder Expectation
6.Project Time Management
6.6 Control Schedule
7. Project Cost Management 8. Project Quality Management 9. Project HR Management
7.3 Control Cost 8.3 Perform Quality Control
9.1 Develop HR Planning
10. Project Communication Mgt
10.1 Identify Stakeholder
10.2 Plan Communication
10.5 Report Performance
11. Project Risk Management
11.1 11.2 11.3 11.4 11.5
Plan Risk Management Identify Risk Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Responses 12.2 Conduct Procurement
11.6 Monitor and Control Risk
12. Project Procurement Mgt.
12.1 Plan Procurement
12.3 Administer Procurement
12.4 Close Procurement
Close Project or Phase
Project Close Out
Finalizing all activities across all of the Project Management Process Groups to formally close the project or a project phase. Staging of Project Close Out : Finalizing The Works and Get the Acceptance Project Financing Close Out Final Project Documentation Lesson Learned Documentation Shut-down project facilities
Finalizing the Works and Get the Acceptance
Clean Up Preliminary Punch List Pre Final Inspection Final Punch List Final Inspection Trainings Keys hand over Final Testing and Commissioning
Project Financing Close Out
Finalize subcontractor Payment Final Release of Claim (Waiver of lien) Consent of Surety for final payment Final Quantity Request for Final Payment Liquidated Damages Final Payment and release of retainage Final Accounting of completion Final Certificates
Certificate for payment Contractors certificate of Completion Certificate of substantial completion (partial occupancy) Certificate of Completion Cetificate od occupancy
Warranties for Defect Liability Periods
Final Project Documentation
As Built Drawings Operating and Maintenance Manuals Records archiving and transfer
Lesson Learned Documentation
Post-project Analysis, critique and reports Owner Feedback A Closing Comment
Lessons Learned (1/2)
What has been accomplished What has gone right What has gone wrong How can avoid those mistakes How can we do better next time
10
Lesson Learned (2/2)
Organizational Process Assets (Lessons Learned Files) Other Projects Project Lessons Learned Organization Files
Your PROJECT
Lessons learned will become part of the historical data for this project and other projects in the organization, and to be used for future project planning.
11
Shutdown Project Facilities
Terminate project office infrastructure Terminate technical infrastructure Release and reassigned the project team
Checklist for Closing a Large Project
DESCRIPTION Needed ? Yes Identify Remaining Work Closing/Termination Plan Personal Evaluations Close-Out Work Orders Audit Final Changes Pay All Vendors Close-Out Books/Audit Final Delivery Instructions Customer Training Notify Purchasing of Completion Equipment Redeployed Materials Returned to Inventory Staff Reassigned Close-Down Procedures Engineering Documentation Final Staff Meeting(s) Final Report and Review Meeting
S & K Baker - The Complete Idiot's Guide to Project M anagement (2000)
Required Date
Responsible Person
Notes
No