100% found this document useful (1 vote)
2K views4 pages

Church Building Plan

The document outlines a building project plan for renovating and completing construction of the Limbe SDA Church over three years. It details 13 phases of construction work including strengthening walls, roofing, wiring, flooring, plastering, furnishing, and external works. An operational plan is provided for each phase with objectives, timelines, and allocated resources. Fundraising ideas include contributions from church members and special events, as well as request letters and individual member activities.

Uploaded by

Violet Freeborn
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views4 pages

Church Building Plan

The document outlines a building project plan for renovating and completing construction of the Limbe SDA Church over three years. It details 13 phases of construction work including strengthening walls, roofing, wiring, flooring, plastering, furnishing, and external works. An operational plan is provided for each phase with objectives, timelines, and allocated resources. Fundraising ideas include contributions from church members and special events, as well as request letters and individual member activities.

Uploaded by

Violet Freeborn
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd

LIMBE SDA CHURCH BUILDING PROJECT Overview This will guide the steps to be followed by the building committee

in the project of renovating and finishing construction of Limbe SDA Church. The overall goal is to finish construction of the church in the year 2010, three years from now. There will be yearly review of the plan by the building committee with the approval of the Church Board Committee and the Church Business Meeting. Goals The different steps to be taken towards the renovation and re-construction process divided into phases will form the goals of the building project committee. Steps 1. Have an approved church structure plan 2. Launch a fund raising campaign 3. Strengthen the walls a. Concrete pillars b. Raising the gable c. Entry porch 4. Roofing a. Un-roofing b. Re-roofing 5. Doors and windows a. Window framing and panning b. Door framing and door fitting 6. Wiring and piping a. Electricity accessories b. Water system toilets and sinks 7. Flooring I a. Concrete flooring ( on original terraces) b. Baptism pool 8. Plastering I a. Inside plastering b. Painting 9. Flooring II a. Fine/smooth cementing 10. Furnishing a. Wood benches for the hall b. Desk chairs for offices c. Shelves and lockers for the storeroom 11. External works a. Outside wall plastering b. Drainage c. Landscaping 12. PA System 13. Ceiling

Operational Plan 1. Have an approved church structure plan Objective Resources to be allocated Timelines 2. Launch a fund raising campaign Objective Resources to be allocated Timelines 3. Strengthen the walls a. Concrete pillars Objective Resources to be allocated Timelines b. Raising the gable Objective Resources to be allocated Timelines c. Entry porch Objective Resources to be allocated Timelines 4. Roofing d. Un-roofing Objective Resources to be allocated Timelines e. Re-roofing Objective Resources to be allocated Timelines 5. Doors and windows f. Window framing and panning Objective Resources to be allocated Timelines g. Door framing and door fitting Objective Resources to be allocated Timelines

6. Wiring and piping h. Electricity accessories Objective Resources to be allocated Timelines i. Water system toilets and sinks Objective Resources to be allocated Timelines 7. Flooring I j. Concrete flooring ( on original terraces) Objective Resources to be allocated Timelines k. Baptism pool Objective Resources to be allocated Timelines 8. Plastering I l. Inside plastering Objective Resources to be allocated Timelines m. Painting Objective Resources to be allocated Timelines 9. Flooring II n. Fine/smooth cementing Objective Resources to be allocated Timelines 10. Furnishing o. Wood benches for the hall Objective Resources to be allocated Timelines p. Desk chairs for offices Objective Resources to be allocated Timelines q. Shelves and lockers for the storeroom Objective Resources to be allocated Timelines

11. External works r. Outside wall plastering Objective Resources to be allocated Timelines s. Drainage Objective Resources to be allocated Timelines t. Landscaping Objective Resources to be allocated Timelines 12. PA System Objective Resources to be allocated Timelines 13. Ceiling Objective Resources to be allocated Timelines Fund Raising Ideas 1. Church Members a. Family goals b. Jesus Ways goals c. Builders Day Collection 2. Special Events a. Church Musical programme b. Outside Special Musical show c. Fund raising dinner 3. Special Request Letters for Donations a. Personal friends b. Within Adventist family c. International donors d. Government 4. Local church individual members fund raising activities a. Small business