Professional Documents
Culture Documents
Introductions
Before getting started, please use the comments area below to introduce yourself (youre colleagues want to meet you!) Tell us the business sector/industry youre coming from, your company name if you like, your experience with project management so far and if you have ever been involved with the challenging world of Earned Value! What are your expectations from the course?
Initiating
Planning
Executing
Closing
identify stakeholders
coordinate resources
manage stakeholders
resources reporting
Planning
Executing
WBS Schedule - Critical Path Method Distribute Budget Cost Profile Allocate Resources Project Baseline
Planning
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
WBS Schedule - Critical Path Method Distribute Budget Cost Profile Allocate Resources Project Baseline
planned baseline
Planning
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Executing
WBS Critical Path Method Distribute Budget Cost Profile
status date
Planning
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Executing
WBS Critical Path Method
Control
Planning
Project: Project: Replacement of pits and ducts along a 200m pavement.
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Planning
Project: Project: Replacement of pits and ducts along a 200m pavement.
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
For training purposes, we shall focus on the first project activity that will guide us through the Earned Value Elements.
planned baseline
Planning
Project: Project: Replacement of pits and ducts along a 200m pavement.
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Activity: Lay 50m of ducts Baseline Duration: 3weeks 15days Baseline Cost: $10.000
Planning
Activity: Lay 50m of ducts Baseline Duration: 3weeks 15days Baseline Cost: $10.000 Cost profile: Week 1: $3.000 Week 2: $5.000 Week 3: $2.000 $8.000 $3.000 $10.000 15m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
The schedule has been developed. The baseline is set. We have planned to lay 50m of ducts within 15 days. The budgeted cost is $10.000 and it is cumulatively distributed along the activity duration.
Planning
Activity: Lay 50m of ducts Baseline Duration: 3weeks 15days Baseline Cost: $10.000 Cost profile: Week 1: $3.000 Week 2: $5.000 Week 3: $2.000 Budget At Completion (BAC): $10.000 Distribution over the activity duration Week 1: $3.000 Week 2: $5.000 Week 3: $2.000 $8.000 $3.000 $10.000 15m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
The schedule has been developed. The baseline is set and the BAC has been agreed. We have planned to lay 50m of ducts within 15 days. The baseline cost, is $10.000 and it is cumulatively distributed along the activity duration. The BAC is not standing alone. For each week of the activity a specific amount of work has been planned to be performed.
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
15m
50m 40m
$8.000 $3.000
$10.000 planned baseline Budget At Completion (BAC): $10.000 Period $3.000 $5.000 $2.000 Cumulative $3.000 $8.000 $10.000 Activity Duration: 15d Period Cumulative 5d 5d 5d 5d 10d 15d
Work Planned: 50m of ducts Period Week 1: 15m Week 2: 25m Week 3: 10m Cumulative 15m 40m 50m
The schedule has been developed. The baseline is set and the BAC has been agreed. We have planned to lay 50m of ducts within 15 days. The baseline cost, is $10.000 and it is cumulatively distributed along the activity duration. The BAC is not standing alone. For each week of the activity a specific amount of work has been planned to be performed.
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
15m
50m 40m
$8.000 $3.000
Executing
Activity: Lay 50m of ducts Baseline Duration: 3weeks 15days Baseline Cost: $10.000 Cost profile: Week 1: $3.000 Week 2: $5.000 Week 3: $2.000 $8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
We planned to lay 15meters within the first five days. However, one week later when the progress updated, only 10m were completed. The actual activity cost is so far $3.000.
Executing
Activity: Lay 50m of ducts Baseline Duration: 3weeks 15days Baseline Cost: $10.000 Cost profile: Week 1: $3.000 Week 2: $5.000 Week 3: $2.000 Actual Cost (AC) on Week 1: $3.000 Actual Cost is the cost of work performed by the day the progress updated. Its not necessarily the cost that has been paid to the contractor. $8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
We planned to lay 15meters within the first five days. However, one week later when the progress updated, only 10m were completed. The actual activity cost is so far $3.000.
Executing
Activity: Lay 50m of ducts Baseline Duration: 3weeks 15days Baseline Cost: $10.000 Cost profile: Week 1: $3.000 Week 2: $5.000 Week 3: $2.000 Actual Cost (AC) on Week 1: $3.000 Actual Cost is the cost of work performed by the day the progress updated. Its not necessarily the cost that has been paid to the contractor. $8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
We planned to lay 15meters within the first five days. However, one week later when the progress updated, only 10m were completed. The actual activity cost is so far $3.000. You may also see the AC as Actual Cost of Work Performed (ACWP).
The Actual Cost, or Actual Cost of Work Performed (ACWP) consists of: Actual [Labor + Non labor (equipment and machinery) + Material (the cost of ducts) + Expenses (like training, but expenses do not apply to all the project activities)]
Executing
Activity: Lay 50m of ducts Baseline Duration: 3weeks 15days Baseline Cost: $10.000 Cost profile: Week 1: $3.000 Week 2: $5.000 Week 3: $2.000 Actual Cost (AC) on Week 1: $3.000 Actual Cost is the cost of work performed by the day the progress updated. Its not necessarily the cost that has been paid to the contractor. Work Cost 15m $3.000 10m $3.000 $8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Week 1
Planned
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
50m
$8.000 $3.000
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
50m
$8.000 $3.000
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Planned Value Cost (PVC) or Budgeted Cost of Work Scheduled (BCWS) How much work should have been done at the end of week 1? Planned Value is the target against which we are measuring the progress
Work Planned: 50m of ducts Period Week 1: 15m Week 2: 25m Week 3: 10m Cumulative 15m 40m 50m
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Planned Value Cost (PVC) or Budgeted Cost of Work Scheduled (BCWS) How much work should have been done at the end of week 1? Planned Value is the target against which we are measuring the progress
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
PVC = BAC x Planned % Complete We planned to complete 30% of the Budget At Completion ($10.000) at the end of the week 1.
Week 3: 10m
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
PVC = BAC x Planned % Complete We planned to complete 30% of the Budget At Completion ($10.000) at the end of the week 1.
Week 3: 10m
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Actual Cost (AC) is the Actual Cost of Work Performed until the status date (you may also see ACWP). The Actual Cost of the work at the end of the week1 is $3.000.
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Actual Cost (AC) is the Actual Cost of Work Performed until the status date (you may also see ACWP). The Actual Cost of the work at the end of the week1 is $3.000.
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
PVC = $10.000 x 30% = $3.000 AC= $3.000 It doesnt look that bad, right?
planned baseline
Actual Cost (AC) is the Actual Cost of Work Performed until the status date (you may also see ACWP). The Actual Cost of the work at the end of the week1 is $3.000.
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Earned Value (EV) signifies how much work has been actually done. To measure the EV we need to know: BAC Performance % Complete
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Earned Value (EV) signifies how much work has been actually done. To measure the EV we need to know: BAC Performance % Complete
We planned to perform 15m at the end of week 1 which is the 33,33% of the total work. However, we performed only 10m, which the 20% of the total work.
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Earned Value (EV) signifies how much work has been actually done. To measure the EV we need to know: BAC Performance % Complete
We planned to perform 15m at the end of week 1 which is the 33,33% of the total work. However, we performed only 10m, which the 20% of the total work.
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Earned Value (EV) signifies how much work has been actually done. To measure the EV we need to know: BAC Performance % Complete
We planned to perform 15m at the end of week 1 which is the 33,33% of the total work. However, we performed only 10m, which the 20% of the total work.
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Earned Value (EV) signifies how much work has been actually done. To measure the EV we need to know: BAC Performance % Complete
Earned Value explains whether the Actual Cost (AC) has been spent effectively (Performance % Complete) providing the physical results that was estimated to (Planned Value).
Question:
How is the project doing?
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Answer:
The project is not doing very well Here are the facts: PVC = $10.000 x 30% = $3.000 AC= $3.000 EV = $10.000 x 20% = $2.000
$8.000 $3.000 $10.000 15m 10m 40m 50m
planned baseline
Earned Value explains whether the Actual Cost (AC) has been spent effectively (Performance % Complete) providing the physical results that was estimated to (Planned Value).
Initiating
Planning
Executing
Closing
Actual Cost
Earned Value
EV = BAC x Performance % Complete
Initiating
Planning
Executing
Closing
Actual Cost
ACWP: Actual Cost of Work Performed
Earned Value
BCWP: Budgeted Cost of Work Performed
Earned Value elements within the Project Management lifecycle Why two terms for the same thing?
Monitor & Control
Initiating
Planning
Executing
Closing
Actual Cost
ACWP: Actual Cost of Work Performed
Earned Value
BCWP: Budgeted Cost of Work Performed
Earned Value elements within the Project Management lifecycle Why two terms for the same thing?
Monitor & Control
Initiating
Planning
Executing
Closing
New term !
Actual Cost
ACWP: Actual Cost of Work Performed
Earned Value
BCWP: Budgeted Cost of Work Performed
Earned Value elements within the Project Management lifecycle Why two terms for the same thing?
Monitor & Control
Initiating
Planning
Executing
Closing
New term !
Actual Cost
ACWP: Actual Cost of Work Performed
Earned Value
BCWP: Budgeted Cost of Work Performed
Old term !
Earned Value elements within the Project Management lifecycle Why two terms for the same thing?
Monitor & Control
Initiating
Planning
Executing
Closing
New term !
Actual Cost
ACWP: Actual Cost of Work Performed
Earned Value
BCWP: Budgeted Cost of Work Performed
Old term !
Performance % Complete
Earned value is all about measuring the work performed.
The Performance % Complete should provide realistic and tangible information for the projects progress. It is selected during the project planning and can be different for each Work Package. Althouth there are several methods in this course we focus in three methods, proven to be best practices. Performance % Complete Percent Complete Estimates Weighted Milestones Fixed Formula $8.000 $3.000 EV = BAC x Performance % Complete $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Performance % Complete
Percent Complete Estimates
It's the most commonly used measurement method as it's easy to administer within the already complex project environment. However it is subjective and often relies on the project manger's perspective. Expert judgment, experience and comprehensive understanding of the project scope are the requirements to maximize the benefits of the % complete estimates in the project. $8.000 $3.000 EV = BAC x Performance % Complete $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Performance % Complete
Percent Complete Estimates
It's the most commonly used measurement method as it's easy to administer within the already complex project environment. However it is subjective and often relies on the project manger's perspective. Expert judgment, experience and comprehensive understanding of the project scope are the requirements to maximize the benefits of the % complete estimates in the project. $8.000 $3.000 EV = BAC x Performance % Complete $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
However, it can be less subjective when tangible measurement is involved; like in our example the meters of the pits and ducts planned to complete per week (or per reporting period).
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned You can use it for work packages that exceed one measurement period. The milestone values should be set before the work starts. EV = BAC x Performance % Complete baseline
The challenge is to agree on the values and make it clear to everyone involved what the values represent.
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned Other examples are: 10/90 EV = BAC x Performance % Complete 25/75 0/100 baseline
it's time to get some meaningful results from the project and try to forecast the future of the project realistically
it's time to get some meaningful results from the project and try to forecast the future of the project realistically Estimate To Complete
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Question:
How can we estimate the cost left to perform until the completion of the activity?
$8.000 $3.000
Answer:
The Estimate To Complete cost ETC:
ETC = BAC AC
ETC = $10.000 $3.000 = $7.000
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Question:
How can we estimate the cost left to perform until the completion of the activity?
$8.000 $3.000
Answer:
The Estimate To Complete cost ETC:
ETC = BAC AC
ETC = $10.000 $3.000 = $7.000
Because the remaining activity cost is not fixed. It may vary depending on several factors, like additional changes that may change the budget. Perhaps we will be able to complete the activity earlier and therefore cost less, or later than planned, or use more resources which causes increased cost.
it's time to get some meaningful results from the project and try to forecast the future of the project realistically Estimate At Completion
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Question:
So, at the end of the activity how much will it cost?
$8.000 $3.000 $10.000 planned baseline
Answer:
The Estimate At Completion cost EAC:
Why do we Estimate At Completion? Because the variable used to forecast the cost at the completion of the activity/project is the ETC. Therefore, is not a fixed figure and can be adjusted in the future.
ETC = ETC + AC
EAC = $7.000 $3.000 = $10.000
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000
15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
$8.000 $3.000
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000
15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
$8.000 $3.000
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000
15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
$8.000 $3.000
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000
15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
$8.000 $3.000
Dont forget that our activity is already underperforming. The ETC and EAC reflect the current status of the activity/project. However, at this point they dont include the cost of delay or underperformance.
Identifying the cost variance between the AC and EV enable us a more realistic picture of the activity performance at the current time period.
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000 CV = $-1.000
$8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000 CV = $-1.000
$8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Which is the relationship between the AC and the EV? Cost Performance Index (CPI) = EV / AC CPI = $2.000 / $3.000 = 0.67
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000 CV = $-1.000 CPI = 0.67
$8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
Which is the relationship between the AC and the EV? Cost Performance Index (CPI) = EV / AC CPI = $2.000 / $3.000 = 0.67 In simple terms, for each dollar spent, only 0.67 worth paying!
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000 CV = $-1.000 CPI = 0.67
$8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000 CV = $-1.000 SV = $-1.000 CPI = 0.67
$8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
As with the CV, we want to identify and compare the work planned to perform within a time period with the work accomplished.
The Schedule Variance (SV) will provide us with the right information. It is expressed in in monetary values. SV = EV PV SV = $2.000 - $3.000 = $-1.000
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000 CV = $-1.000 SV = $-1.000 CPI = 0.67
$8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
How the Planned and the Earned Value are related? Schedule Performance Index (SPI) = EV / PV SPI = $2.000 / $3.000 = 0.67
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000 CV = $-1.000 SV = $-1.000 CPI = 0.67 SPI = 0.67
$8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
How the Planned and the Earned Value are related? Schedule Performance Index (SPI) = EV / PV SPI = $2.000 / $3.000 = 0.67
BAC = $10.000 PVC = $3.000 AC = $3.000 EV = $2.000 ETC = $7.000 EAC = $10.000 CV = $-1.000 SV = $-1.000 CPI = 0.67 SPI = 0.67
$8.000 $3.000 $10.000 15m 10m 40m 50m
Project Week
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
planned baseline
CPI, SPI rule: CPI > 1 more work done than what actually paid for. CPI = 1 you got exactly what you paid for. CPI < 1 less work done than what actually paid for. SPI > 1 - ahead of schedule. The work accomplished is more that the work planned. SPI = 1 - the work accomplished is exactly the work planned. SPI < 1 - behind schedule. The work accomplished is less than planned.
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Project Week
Back to our example The first reporting period (week 1) we have the following results: Activity: Lay 50m of ducts BAC: $10.000 PVC AC EV ETC EAC CV SV
$9.000 $8.000 $3.000 Week 1 $3.000 $3.000 $2.000 $7.000 $10.000 $-1.000 $-1.000
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Project Week
$9.000 $8.000 The first reporting period (week 1) we have the following results: Activity: Lay 50m of ducts BAC: $10.000 PVC AC EV ETC EAC CV SV $3.000 Week 1 $3.000 $3.000 $2.000 $7.000 $10.000
$-1.000 $-1.000
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Project Week
$9.000 $8.000 The second reporting period (week 2) the activity performance is: Activity: Lay 50m of ducts BAC: $10.000 PVC AC EV ETC EAC CV SV $3.000 Week 1 $3.000 $3.000 $2.000 $7.000 $10.000
$-1.000 $-1.000
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Project Week
$9.000 $8.000 The second reporting period (week 2) the activity performance is: Activity: Lay 50m of ducts BAC: $10.000 PVC AC EV ETC EAC CV SV $3.000 Week 1 $3.000 $3.000 $2.000 $7.000 $10.000 $-1.000 $-1.000
$-2.000 $-1.000
04 03 02 01 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Project Week
$9.000 $8.000 The second reporting period (week 2) the activity performance is: Activity: Lay 50m of ducts BAC: $10.000 PVC AC EV ETC EAC CV SV $3.000 Week 1 $3.000 $3.000 $2.000 $7.000 $10.000 $-1.000 $-1.000
$-2.000 $-1.000
Denise Fotopoulou