Proposal Water Distribution System, English
Proposal Water Distribution System, English
CHAPTER
CONTENT
INTRODUCTION PROJECT DESCRIPTION BACKGROUND/SITUATION ANALYSIS PROJECT OBJECTIVES DESIRED IMPACT AND OUTCOME OF THE PROJECT RISK MANAGEMENT PLAN PROJECT ORGANIZATION AND STAFFING PROJECT WORK PLAN DETAILED BUDGET REQUIREMENT OTHER RELEVANT INFORMATION ATTACHMENTS
I.
INTRODUCTION
Every year as summer approaches, areas around the world grow concerned about seasonal drought. There are areas where drought is a regular year to year occurrence that lasts longer than just the summer. Philippines are one of these areas that experiences this season. It can impact crop production and cause changes to the natural distribution of various species. Distribution of water to a plantation must be increased drastically to secure food production for future generation. The general approach is to avoid water loss and to ensure that all distributed water is being utilized by the crop. By this Water Regulator System, it will help the farmers to fight this season because this system will provide water needed for the plant to remain its vitality and maintain the crops yield.
II.
PROJECT DESCRIPTION
WATER REGULATOR SYSTEM AGRICULTURAL AND TECHNOLOGICAL CABRERA, LORIEBIE REAL ROSALES, ELDHIE ANN EGNALIG
Number of Benefits: Project Beneficiaries: Location of Beneficiaries: Date of Implementation/Duration: Area of Project Implementation: Budget Required: Budget Requested:
100 FARMERS, OWNERS OF A PLANTATION PHILIPPINES SEPTEMBER 20, 2013/30 DAYS BRGY. BUGAS-BUGAS, MUNICIPALITY OF PLACER, SURIGAO CITY Php 21, 215.36 Php 25, 000.00
III.
BACKGROUND SITUATION/ANALYSIS
Philippines are one of those areas that can experience summer season which may become as drought season. Shortages in precipitation, changes in evapo transpiration, and reduced ground water levels can create stress and problem for the crops. To secure our food production for future generations, the distribution of water to a plantation must be increased drastically as this season experienced. The Water Regulator System prompted to help the farmers to fight from the damages caused by this season. This device also controls the water flow in a plantation which helps farmers to save water.
IV.
PROJECT OBJECTIVES
To create a system that controls the distribution of water in a plantation. To design a regulator that conserve water and helps to fight the drought experienced by the country.
STRATEGIES Prepare all the materials needed. Find location in a plantation to put the pipes and tubes.
V.
This system has a great effect in our economy. It increases crop yield in spite of experiencing the seasonal drought. It gives a solution in a continuous increasing demand of the food and to the improvement, sustainability and efficiency of the agricultural sector. And it also saves water as you start The following are the specific measures to sustain the system: System regularly maintained and checked for leaks Nozzles and other applicators regularly calibrated Checked for evenness of application
VI.
There are risk and factors that may hamper or hinder the successful implementation of this system. One of these is the lack of control over the project team from the decentralization of decisionmaking and subsequent ineffective ratification of decisions, there should be an approval rights on all significant decisions. Another is the large expenditures for the acquisition of the hardware, software, and implementation cost. Otherwise find sponsors for the project to minimize the expenditures. Lastly is the weather condition, the weather should be good to avoid the delay of implementation and may cause changes in work plan.
VII.
PROJECT ORAGANIZATION AND STAFFING Responsibilties Planning Committee Programmer Designer Electronics, trouble shooting Installer Contact Person Real, Betoy Lerio, Jomel Belbes, Tanem Erigay, Jade De Mesa, Edelyn Contact Details 09075615101 09092751905 09156894523 03175896423 09306458525
Office/Staff Designated Cabrera, Loriebie Rosales, Eldhie Ann Belbes, Jane Clerigo, Jessrich De Mesa, Prince Josh
X.
PROJECT WORK PLAN PERSON IN CHARGE Engr. Cabrera, Loriebie Mr. Tan, Kimbom Engr. Cabrera, Loriebie Mr. Tan, Kimbom Engr. Gonzales, Tom Engr. Cabrera, Loriebie Mr. Tan, Kimbom Engr. Gonzales, Tom Mr. Tan, Kever Engr. Camus, Rhea Mr. Kier, Baby Ms. Espina, Florides RESOURCES NEEDED
ACTIVITIES
OUTPUT/TARGET
INDICATORS
COST
Nov. 4, 2013
Php100
Nov. 5, 2013
Php20, 000
Plan and analyze about the making of the project to achieve the desired objectives
Preparation Phase
Prepare all the materials, place for the construction and the materials needed in a project
Php150
The farmer will receive a data to her mobile phone notifies him that water were reached to its desired level
Engr. Rosales, Eldhie Ann Engr. Cabrera Engr. Cabrera, Loriebie Mr. Tan, Kimbom Engr. Gonzales, Tom Mr. Tan, Kever Engr. Camus, Rhea Mr. Kier, Baby Ms. Espina, Florides Engr. Led, Josh Engr. Cabrera
Php200
Php3, 000
I.
DETAILED BUDGET REQUIREMENT Description A flexible tubes used to convey water. Amount Needed Php 22,050 Marlyn Hardware Php 2,100 Php 699 Php 66.36 Php 100 Regular Load in Globe Tattoo USB stick for Internet Connection. Php 400 Php 21,215.36 Prime Hub Alibaba Uni City Margarita Proposed Source/s
Budget Line Item Tubes, Pipe and Hose Control and Safety Valves Mobile Phone Microchip Stationery Regular Load TOTAL