You are on page 1of 7

REPAIRS TO PIPING Supreme Mechanical Company Limited - Timesheet - October 2008

Labour Oct.05 - Oct.11 Oct.12 - Oct.28


Double time Labour Hrs Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Total Hr Rates Amount
Employees Name: Cat. Cat. 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Keynatta Burton Sup Reg.
OT 3 8 2 13 $ 3,861.00 $ 50,193.00
Everton Mcknight W-1 Reg.
OT 3 8 2 13 $ 2,546.00 $ 33,098.00
Keishna Salmon W-1 Reg.
OT 3 8 2 13 $ 2,546.00 $ 33,098.00
Aplyn Bennett W-1 Reg.
OT 3 8 2 13 $ 2,546.00 $ 33,098.00
Donnavon Bennett F-1 Reg.
OT 3 8 2 13 $ 2,546.00 $ 33,098.00
Romain Morgan F-1 Reg.
OT 3 8 2 13 $ 2,546.00 $ 33,098.00
Rudolph Francis F-1 Reg.
OT 3 8 2 13 $ 2,546.00 $ 33,098.00

Straight time
Keynatta Burton Sup Reg. 8 8 8 8 32 $ 1,931.00 $ 61,792.00
OT
Everton Mcknight W-1 Reg. 8 8 8 8 32 $ 1,273.00 $ 40,736.00
OT
Keishna Salmon W-1 Reg. 8 8 8 8 32 $ 1,273.00 $ 40,736.00
OT
Aplyn Bennett W-1 Reg. 8 8 8 8 32 $ 1,273.00 $ 40,736.00
OT
Donnavon Bennett F-1 Reg. 8 8 8 8 32 $ 1,273.00 $ 40,736.00
OT
Romain Morgan F-1 Reg. 8 8 8 8 32 $ 1,273.00 $ 40,736.00
OT
Rudolph Francis F-1 Reg. 8 8 8 8 32 $ 1,273.00 $ 40,736.00

11/02/2021
REPAIRS TO PIPING Supreme Mechanical Company Limited - Timesheet - October 2008
Labour Oct.05 - Oct.11 Oct.12 - Oct.28
Double time Labour Hrs Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Total Hr Rates Amount
Employees Name: Cat. Cat. 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Total Labour $ 554,989.00

Consumables Amt Unit Rate


Welding rods 125 Lbs 250.00 $ 31,250
7 x 1/4 Grinding discs 2 ea 615.00 $ 1,230
4 x 1/4 Grinding discs 4 ea 415.00 $ 1,660
4 x 1/8 Cutting discs 10 ea 515.00 $ 5,150
Oxygen 0.75 bottle 2,200.00 $ 1,650
Acetylene 0.25 bottle 4,500.00 $ 1,125
Diesel 100 Liters 92.00 $ 9,200
Total Consumables $ 51,265

Material Amt Unit Rate


Supply paint 1 gal 3,200.00 $ 3,200
Supply Thread tape 5 Roll 145.00 $ 725

Total Material $ 3,925

Equipment No. Hours Rate/Hr


Pick-up Truck 1 45 938.44 $ 42,230
Welding Plant 3 45 938.44 $ 126,689
Cutting Set 1 45 295.31 $ 13,289
Small Grinder 4 45 246.10 $ 44,298
Large Grinder 1 45 305.17 $ 13,733
Come-along 1 45 138.00 $ 6,210
Total Equipment $ 246,449

Sub Total $ 856,628


Add GCT 16.5 % $ 141,344

Total piping carried to summary $ 997,971

11/02/2021
REPAIRS TO HEAT EXCHANGER Supreme Mechanical Company Limited - Timesheet - October 2008
Labour Oct.05 - Oct.11 Oct.12 - Oct.18
Straight Time Labour Hrs Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Total Hr Rates Amount
Employees Name: Cat. Cat. 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Keynatta Burton Sup Reg. 8 8 $ 1,931.00 $ 15,448.00
OT
Everton Mcknight W-1 Reg. 8 8 $ 1,273.00 $ 10,184.00
OT
Keishna Salmon W-1 Reg. 8 8 $ 1,273.00 $ 10,184.00
OT
Aplyn Bennett W-1 Reg. 8 8 $ 1,273.00 $ 10,184.00
OT
Donnavon Bennett F-1 Reg. 8 8 $ 1,273.00 $ 10,184.00
OT
Romain Morgan F-1 Reg. 8 8 $ 1,273.00 $ 10,184.00
OT
Rudolph Francis F-1 Reg. 8 8 $ 1,273.00 $ 10,184.00
OT

Double Time
Keynatta Burton Sup Reg.
OT 7 7 $ 3,861.00 $ 27,027.00
Everton Mcknight W-1 Reg.
OT 7 7 $ 2,546.00 $ 17,822.00
Keishna Salmon W-1 Reg.
OT 7 7 $ 2,546.00 $ 17,822.00
Aplyn Bennett W-1 Reg.
OT 7 7 $ 2,546.00 $ 17,822.00
Donnavon Bennett F-1 Reg.
OT 7 7 $ 2,546.00 $ 17,822.00
Romain Morgan F-1 Reg.
OT 7 7 $ 2,546.00 $ 17,822.00
Rudolph Francis F-1 Reg.
OT 7 7 $ 2,546.00 $ 17,822.00

11/02/2021
REPAIRS TO HEAT EXCHANGER Supreme Mechanical Company Limited - Timesheet - October 2008
Labour Oct.05 - Oct.11 Oct.12 - Oct.18
Straight Time Labour Hrs Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Total Hr Rates Amount
Employees Name: Cat. Cat. 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Total Labour $ 210,511.00

Consumables Amt Unit Rate


Welding rods 45 Lbs 250.00 $ 11,250
7 x 1/4 Grinding discs 2 ea 615.00 $ 1,230
4 x 1/4 Grinding discs 4 ea 415.00 $ 1,660
Oxygen 0.5 bottle 2,200.00 $ 1,100
Acetylene 0.25 bottle 4,500.00 $ 1,125
Diesel 50 Liters 92.00 $ 4,600
Total Consumables $ 20,965

Material Amt Unit Rate

Total Material $ -

Equipment No. Hours Rate/Hr


Pick-up Truck 1 15 938.44 $ 14,077
Welding Plant 3 15 938.44 $ 42,230
Cutting Set 1 15 295.31 $ 4,430
Small Grinder 3 15 246.10 $ 11,075
Large Grinder 4 15 305.17 $ 18,310
Come-a-long 1 15 246.10 $ 3,692

Total Equipment $ 93,812

Sub Total $ 325,288


Add GCT 16.5 % $ 53,673

Total carried to summary $ 378,961

11/02/2021
REPAIRS TO D-70 WATER TANK Supreme Mechanical Company Limited - Timesheet - October 2008
Labour Oct.12 - Oct.18 Oct.19 - Oct.25
Double time Labour Hrs Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Total Hr Rates Amount
Employees Name: Cat. Cat. 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Keynatta Burton Sup Reg.
OT 2 7 11 20 $ 3,861.00 $ 77,220.00
Everton Mcknight W-1 Reg.
OT 2 7 11 20 $ 2,546.00 $ 50,920.00
Keishna Salmon W-1 Reg.
OT 2 7 11 20 $ 2,546.00 $ 50,920.00
Aplyn Bennett W-1 Reg.
OT 2 7 11 20 $ 2,546.00 $ 50,920.00
Donnavon Bennett F-1 Reg.
OT 2 7 11 20 $ 2,546.00 $ 50,920.00
Romain Morgan F-1 Reg.
OT 2 7 11 20 $ 2,546.00 $ 50,920.00
Rudolph Francis F-1 Reg.
OT 2 7 11 20 $ 2,546.00 $ 50,920.00

11/02/2021
REPAIRS TO D-70 WATER TANK Supreme Mechanical Company Limited - Timesheet - October 2008
Labour Oct.12 - Oct.18 Oct.19 - Oct.25
Double time Labour Hrs Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Wed Thur Fri Sat Sun Mon Tue Total Hr Rates Amount
Employees Name: Cat. Cat. 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Total Labour $ 382,740.00

Consumables Amt Unit Rate


Welding rods 125 Lbs 250.00 $ 31,250
7 x 1/4 Grinding discs 2 ea 615.00 $ 1,230
4 x 1/4 Grinding discs 4 ea 415.00 $ 1,660
Oxygen 0.75 bottle 2,200.00 $ 1,650
Acetylene 0.25 bottle 4,500.00 $ 1,125
Diesel 50 Liters 92.00 $ 4,600
Total Consumables $ 41,515

Material Amt Unit Rate


Supply, roll and cut 1/4
m.s plate 168 Sq..Ft 1,637 $ 275,016

Total Material $ 275,016

Equipment No. Hours Rate/Hr


Pick-up Truck 1 20 938.44 $ 18,769
Welding Plant 3 20 938.44 $ 56,306
Cutting Set 1 20 295.31 $ 5,906
Small Grinder 3 20 246.10 $ 14,766
Large Grinder 1 20 305.17 $ 6,103
Come-a-long 1 20 138.00 $ 2,760
Hydraulic jack 2 20 187.50 $ 7,500
Total Equipment $ 112,111

Sub Total $ 811,382


Add GCT 16.5 % $ 133,878

Total carried to summary $ 945,260

11/02/2021
November 20,2009

31 Bushy Park, St. Catherine


Tel: 1-876 983-8341/361-4452/848-4722

PETROJAM LIMITED bgt0 l


96 Marcus Garvey Drive
Kingston 15, Jamaica

INVOICE # 11

Attention: Miss Narda Banton

Project : PIPING FABRICATION & INSTALLATION

We Hereby submit our cost for the sum of Three Million Four Hundred and Ninty Six Thousand and Twenty
Two Dollars Ten cents ($3,496,022.10) to provide supervision, Labour,equipment, materials, tools and
consumables for piping fabrication & installation.
Item Description Amount

1 Value of original contract Completion 3,884,469


2 Amount been invoiced 90% 3,496,022.10
3 Balance 388,446.90

TOTAL COST FOR PAYMENT NOW $ 3,496,022.1

Yours truly,
SUPREME MECHANICAL COMPANY LIMITED

Christopher Gordon

Managing Director

-----------------------