17, '03 Aug 24, '03 Aug 31, '03 Sep 7, '03 Sep 14, '03 Sep 21,

Sep 7, '03 Sep 14, '03 Sep 21, '03 Sep 28, '03 Oct 5, '03
ID Task Name Duration Predec M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1 Propsoal for NEIU 1.5 days 4 8/20
2 Network Diagram 2 hrs 1 100%
3 take MS project tutorial from New Hori 8 days 100%
4 Start MS Project file 2 hrs 3SS 100%
5 Cost and Time Estimates 1 day? 1 100%
6 Cat 6 Cable run Termination 2 days 2 100%
7 Configure DHCP Router to assign IP a 2 hrs? 6 100%
8 Esthitics/Testing 5 days 6 90%
9 Independent Study Paperwork 4 hrs? 25%
10 Initial Security Set up 1 day 8 100%
11 Phase 1 of Client Manual Completed 2 days? 10 0%
12 Initial Phase Checkpoint 1 day? 5,11 9/4
13 Client Procurement meeting 2 hrs? 12 0%
14 Solicit Bids for equipment 2 days? 13 0%
15 Order equipment 3 days 14 0%
16 Setup Server 3 hrs 15 0%
17 initial Server Configuration 5 days 16 0%
18 Set up ICS 4 days 17 0%
19 Create Virtual Private Network connec 1 day? 18 0%
20 Phase 2 client manual update 6 hrs? 19,18 0%
21 Phase 2 complete 1 hr? 18,20 10/1
22 Partition and map drives 2 days 21 0%
23 set up active directory services 4 days 21 0%
24 Install Antivirus Software 1 day? 23 0%
25 Create VPN account 3 days 24
26 Create Data Back up Schemes 3 days? 25
27 Test Back up data 2 days 26FS-1
28 Create Disaster Plan 6 days 27FS-1
29 Configure IIS for Intra net 10 days 27FS+
30 create intranet for video clips 5 days? 29
31 Phase 3 client manual update 6 hrs 30
32 Phase 3 complete 1 hr 31
33 Begin Phase 4 1 day 32
34 Plan disaster drill 5 days 33
35 Run disaster drill 3 days 34
36 Test security 6 days 35FS-1
37 Begin compiling documentation 1 day 36
38 Prepare for network demonstration 3 days 37
39 Give Demonstration 1 day? 38
40 Publish complete Website for project 3.88 mons
41 Client Network Manual 66 days?
42 Master Project Document. 15.1 wks
43 Submit all materials to NEIU 1 day?
44 Submit all materials to Client 1 day

Critical Split Baseline Milestone Project Summary

Critical Split Task Progress Milestone External Tasks


Project: VOIP Cat6 Network Project
Date: Fri 9/5/03 Critical Progress Baseline Summary Progress External Milestone

Task Baseline Split Summary Deadline

Page 1
Oct 12, '03 Oct 19, '03 Oct 26, '03 Nov 2, '03 Nov 9, '03 Nov 16, '03 Nov 23, '03 Nov 30, '03 Dec 7, '03 Dec 14, '03
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

0%
0%
0%
0%
0%
0%
0%
11/10
11/11
0%
0%
0%
0%
0%
0%
20%
0%
5%
12/12
12/17

Critical Split Baseline Milestone Project Summary

Critical Split Task Progress Milestone External Tasks


Project: VOIP Cat6 Network Project
Date: Fri 9/5/03 Critical Progress Baseline Summary Progress External Milestone

Task Baseline Split Summary Deadline