You are on page 1of 31

OFFICIAL TESTING CHECKLIST

Name of the Project :


Equipment/Facilities:
Location
:
Phase
:
Size of Wire :

Horsepower Rating :

Work Description
Check the directional flow arrow on the pipes.
Check all gate valves if functioning properly.
Check for pump overheating.
Check the leak at packing seal.
Check the leaks at all gate valves.(Normally open/Normally closed.)
Grease and lubricate bearings.
Check all screws, holding, mounting nuts and bolts.
Check moving parts (bearing, etc.)
Inspect all electrical controllers and components .
Check the pipe painting.
Test and check for noise and vibration.
Hydrostatic Pressure Test.
Check the pressure gauges.

Voltage
:
Breaker Rating :
Status

Remark/s

Get ampere and voltage reading of the motor.


L12:
Cut-In Pressure:
L23:
Cut-Out Pressure:
L31:
Test insulation resistance of the motors.
L1-L2:
L2-L3:
L3-L1:

L1:
L2:
L3:
L1-Ground :
L2-Ground :
L3-Ground :

Recorded by:
Contractor/Supplier
Witnessed and Certified by:

M / E Engineer

CMT Head

Senior MEPF-In-Charge

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING CHECKLIST
Name of the Project :
Equipment/Facilities:
Location
:
Pump No.
Voltage

JOCKEY PUMP

:
:

Phase :
Size of Wire :
Work Description

Horsepower Rating :
Breaker Rating :
Status

Remark/s

Check the proper tagging of valves.(Normally open / Normally closed.)


Check all gate valves if functioning properly.
Check for pump overheating.
Check the leak at packing seal.
Check the leaks at all gate valves and check valves.
Check the directional flow arrow on the pipes.
Check all screws, holding, mounting nuts and bolts.
Check all electrical controllers and components .
Test and check for noise and vibration.
Get ampere and voltage reading of the motor.
L12:
Cut-In Pressure:
L23:
Cut-Out Pressure:
L31:
Test insulation resistance of the motors.
L1-L2:
L2-L3:
L3-L1:

L1:
L2:
L3:
L1-Ground :
L2-Ground :
L3-Ground :

Recorded by:
Contractor/Supplier
Witnessed and Certified by:

M / E Engineer

CMT Head

Senior MEPF-In-Charge

QA/BTO Head

ATION - Quality Control Management


TESTING CHECKLIST

Remark/s

CMT Head

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING CHECKLIST
Name of the Project

Equipment/Facilities
Location
:

GENERATOR SET

Geneset No.
:
Capacity
:
FullLoad Current :
INDICATORS
Radiator Water Level
Radiator Water Temperature
Fuel Level
Engine Oil Level
Battery Charger
Battery Charge, Vdc
Battery Solution Level
Frequency Reading
Revolution Per Minute, RPM
Pilot Light Indicator
Ventilation
Voltmeter Reading
L1L2
L2L3
L3L1
Ammeter Reading
L1
L2
L3

Voltage :
Frequency:
RPM
:
STANDARD

Time

READINGS
Time

Time

REMARKS

Full
Full
Full or 3/4
Functional
24 - 27 Vdc
Full
60 Hz
1800
Functional

Recorded by:
Contractor/Supplier
Witnessed and Certified by:

M / E Engineer

CMT Head

Senior MEPF-In-Charge

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING CHECKLIST
Name of the Project :
Equipment/Facilities:
Location
:

VRV No.:
Size of Wire :
High Pressure:

VARIABLE REFRIGERANT VOLUME (VRV)

Horsepower Rating :

Voltage:
Breaker Rating:
Low Pressure :

Work Description
Check the system if has refrigerant leak.
Inspect contacts of starter, relays and ensure that these are clean.
Check lubrication of bearings, bushing of blower motor, fans of VRV and
FCU's
Check pulley al;ignment and conditions of belt and adjust tensions if
necessary.
Check for any unusual noise or vibration.
Check for any water leak around the VRV and drain pipes.
Check all panels and ensure that these are properly secured.

Frequency:
Compressor No.:
Capacity in TR :
Status

Phase :

Remark/s

Get ampere and voltage reading of the motor.


L12:
Cut-In Pressure:
L23:
Cut-Out Pressure:
L31:
Test insulation resistance of the motors.
L1-L2:
L2-L3:
L3-L1:

L1:
L2:
L3:
L1-Ground :
L2-Ground :
L3-Ground :

Recorded by:
Contractor/Supplier
Witnessed and Certified by:

M / E Engineer

CMT Head

Senior MEPF-In-Charge

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING CHECKLIST

Name of the Project :


Equipment/Facilities:
Location
:

Pump No.
Voltage

SUMP PUMP

:
:

Frequency :
Size of Wire :

Work Description
Check alignment of belt.
Check and clean fan blade.
Re-tension belt. (if necessary)
Check motor.
Check electrical control. Tighten terminals.
Check the directional flow arrow on the pipes.
Clean contacts of magnetic contactor.
Check all electrical controllers and components .
Check setscrews of circuit breakers and controls.

Phase :

Horsepower Rating :
Breaker Rating :
Status

Remark/s

Get ampere and voltage reading of the motor.


L12:
Cut-In Pressure:
L23:
Cut-Out Pressure:
L31:
Test insulation resistance of the motors.
L1-L2:
L2-L3:
L3-L1:

L1:
L2:
L3:
L1-Ground :
L2-Ground :
L3-Ground :

Recorded by:
Contractor/Supplier

Witnessed and Certified by:

M / E Engineer

CMT Head

Senior MEPF-In-Charge

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING CHECKLIST

Name of the Project :


Equipment/Facilities:
Location
:

Pump No.
Voltage

SUPPLY BLOWER / EXHAUST BLOWER

:
:

Frequency :
Size of Wire :
Work Description

Phase :

Horsepower Rating :
Breaker Rating :
Status

Remark/s

Check motor.
Check electrical control and terminals.
Check the canvas connector.
Check for vibration.
Check bearings.
Check for lose bolts.
Check airduct hangers.
Check the cleanliness of the area.
Get ampere and voltage reading of the motor.
L12:
Cut-In Pressure:
L23:
Cut-Out Pressure:
L31:
Test insulation resistance of the motors.
L1-L2:
L2-L3:
L3-L1:

L1:
L2:
L3:
L1-Ground :
L2-Ground :
L3-Ground :

Recorded by:
Contractor/Supplier

Witnessed and Certified by:

M / E Engineer

CMT Head

Senior MEPF-In-Charge

QA/BTO Head

ATION - Quality Control Management


TESTING CHECKLIST

Remark/s

CMT Head

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
Name of the Project :
Equipment/Facilities:
Location
:
Specifications
Type of Equipment
Brand
Model Others

SWIMMING POOL

:
:
:
:

Work Description
PUMP and MOTOR - General Condition
Temperature
Sound
Control Panel
Pipes and Gate Valves
Return
Main Drain Valve
Skimmer Line
Check the directional flow arrow in the pipes.
Check the tagging of the installed lighting in the pool.
Check the proper tagging of valves.(normally open /normally close)

Status

Remark/s

FILTER TANK
Filter Element
Pressure
Result of Water Test
Pump Room Physical Apperance

Recorded by:
Contractor/Supplier

Witnessed and Certified by:

M / E Engineer

CMT Head

Senior MEPF-In-Charge

QA/BTO Head

ATION - Quality Control Management

NG/INSPECTION CHECKLIST

Remark/s

CMT Head

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
Name of the Project :
Equipment/Facilities:
Location
:

SWITCHGEAR / POWER ROOM


PARTICULARS

Status

NORMAL AND EMERGENCY CIRCUIT BREAKER


a.) Check the proper labeling of normal, Emergency and commom circuit breaker.
b.) Check the inside components for possible problem in the transferring like dust and foreign objects.
c.) Check if there is a "mechanical interlock" installed between normal and emergency circuit breaker.
d.) All joints of the busbar and twerminal connections are properly tightened.
e.)Insulation on conductors should be examined for overheating or chafing that could progress into an
insulation failure. Damaged conductors should be replaced.
f.) Mechanisms should be manually operated to ensure proper working condition.
PAD MOUNTED TRANSFORMER
a.) Check the rated capacity of the transformer.
b.) Check the temperature readings and load current. Excessive temperature indicates an overload or
perhaps some interference with the normal means of cooling.
c.) Check the pressure and vacuum gauges.
d.) Check the insulators and insulating surfaces of bushing for trackings, cracks, or chipped skirts, and
the gasket bases for leaks.
LOAD BREAK SWITCH
a.) Check the specification of the vacuum circuit breaker.
b.) Check the arm lever for manual operation.
c.) Check the selector switch of the vacuum circuit breaker. Should have a permanent cover to avoid
accidental contact.
SAFETY CONCERNS
a.) Check the entrance /exit incase emergency problems occurred. Should be free from obstruction.
b.) Fire extinguisher should be present in the area.
c.) All live parts should be covered with appropriate enclosures.
d.) It should never assumed that acircuit breaker is in the open position because the handle mechanism
is in the open position. Always double check for safety.
f.) Lighting system in the area should be properly illuminated.
Recorded by:
Contractor/Supplier
Witnessed and Certified by:

M / E Engineer

CMT Head

Senior MEPF-In-Charge

QA/BTO Head

ATION - Quality Control Management

NG/INSPECTION CHECKLIST

Status

CMT Head

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
Name of the Project :
Equipment/Facilities:
Location
:

PARKING AREAS

Work Description
Flooring (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Slot Parking Number
Directional Signage
Emergency Light
Elevetor Parking Lobby
Cleanliness of the area
Location

Status

Remark/s

Status

Remark/s

Status

Remark/s

Work Description
Flooring (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Slot Parking Number
Directional Signage
Emergency Light
Elevetor Parking Lobby
Cleanliness of the area
Location

Work Description
Flooring (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Slot Parking Number
Directional Signage
Emergency Light
Elevetor Parking Lobby
Cleanliness of the area

Recorded by:
Contractor

Witnessed and Certified by:

Site Engineer

CMT Head

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
Name of the Project :
Equipment/Facilities:
Location
:

FIRE EXIT

Items For Inspection


Flooring / Stair (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Emergency Light
Fire Exit Door with panic device and door closer
Cleanliness of the area
Location

Status

Remark/s

Status

Remark/s

Status

Remark/s

Items For Inspection


Flooring / Stair (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Emergency Light
Fire Exit Door with panic device and door closer
Cleanliness of the area
Location

Items For Inspection


Flooring / Stair (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Emergency Light
Fire Exit Door with panic device and door closer
Cleanliness of the area

Recorded by:
Contractor

Witnessed and Certified by:

Site Engineer

CMT Head

QA/BTO Head

ATION - Quality Control Management

NG/INSPECTION CHECKLIST

Remark/s

Remark/s

Remark/s

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
Name of the Project :
Equipment/Facilities:
Location
:

ELECTRICAL & AUXILLARY ROOM

Items For Inspection


Flooring (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Smoke Detector
Ventilation
Tagging for Panel Board
Harnessing of Wire
Cleanliness of the area
Location

Status

Remark/s

Status

Remark/s

Status

Remark/s

Items For Inspection


Flooring (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Smoke Detector
Ventilation
Tagging for Panel Board
Harnessing of Wire
Cleanliness of the area
Location

Items For Inspection


Flooring (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Smoke Detector
Ventilation
Tagging for Panel Board
Harnessing of Wire
Cleanliness of the area

Recorded by:
Contractor

Witnessed and Certified by:

Site Engineer

CMT Head

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
Name of the Project :
Equipment/Facilities:
Location
:

PUMPS' ROOM

Items For Inspection


Flooring (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Smoke Detector
Ventilation
Tagging & Arrow for valves and piping
Tagging for Panel Board
Tagging for pumps and motors
Color coding of pipe
Cleanliness of the area
Cistern Tank
Float valve
Application of tank epoxy
Clealiness of the tank
Access door w/ provision for lock
Location

Status

Remark/s

Status

Remark/s

ROOFDECK

Items For Inspection


Flooring (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Tagging for control panel
Tagging for pumps and motors
Cleanliness of the area
Over-head Tank
Electrode
Sight glass
Physical appearance of the tank
Cleanliness (inside) of the tank
Manhole w/ provision for lock

Recorded by:
Contractor

Witnessed and Certified by:

Site Engineer

CMT Head

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
Name of the Project :
BUILDING AMENITIES
Main Lobby
Items For Inspection
Flooring (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Smoke Detector
Sprinkler heads
Ventilation / Air conditioning System
Furniture and decorative items
Equipment
Elevator lobby
Signage
Cleanliness of the area

Status

Remark/s

Status

Remark/s

Function Room
Items For Inspection
Flooring (Physical Appearance)
Wall (Physical Appearance)
Ceiling (physical Appearance)
Illumination or Lighting System
Smoke Detector
Sprinkler heads
Ventilation / Air conditioning System
Furniture and decorative items
Equipment
Signage
Cleanliness of the area

Recorded by:
Contractor

Witnessed and Certified by:

Site Arch't./ Engineer

CMT Head

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
Name of the Project :

Others

Cleanliness of
the area

Emergency
Lights

Sprinkler Heads

Smoke
Detectors

Convenience
Outlet

Lighting System

Flooring, Wall
and Ceiling

Items For
Inspection

HALLWAYS AND ELEVATOR LOBBIES

REMARKS

Gnd Flr
2nd Flr
3rd Flr
4th Flr
5th Flr
6th Flr
7th Flr
8th Flr
9th Flr
10th Flr
11th Flr
12th Flr
14th Flr
15th Flr
16th Flr
17th Flr
18th Flr
19th Flr
20th Flr
21st Flr
22nd Flr
23rd Flr
24th Flr
25th Flr
26th Flr
27th Flr
28th Flr
29th Flr
30th Flr

Recorded by:
Contractor
Witnessed and Certified by:

Site Arch't./ Engineer

CMT Head

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
INSULATION TEST
Name of the Project :

Contractor :

Instrument Used:
Model
:
Test Voltage
:
Panel Name
:
Location
:
Circuit
No.

Date
Time
Weather

Description

Wire Size

L - L

L - L

L - L

Reading in Mega-Ohms, M
L - N L - N L - N L - G

L - G

:
:
:

L - G

N-G

Test
Time

Recorded by:
MEPF Engineer

CMT HEAD

Project-in-charge

QA/BTO Head

Witnessed and Certified by:

M/E Engineer

Remarks

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
MECHANICAL LEAK TEST / PLUMBING FLOW TEST
Name of the Project :

Contractor :

Instrument Used:
Model
:
Type of Test
:
Location
:

Date
Time
Weather

Item

Description Of The Item To Be Tested

Date of Initial Testing:


Remarks:

Initial Testing
Remarks

:
:
:

Final Testing
Remarks

Date of Final Testing:

Recorded by:

Witnessed and Certified by:


Site Arch't./ Engineer

CMT Head

QA/BTO Head

MEGAWORLD CORPORATION - Quality Control Management


OFFICIAL TESTING/INSPECTION CHECKLIST
PRESSURE/LEAK TEST
Name of the Project :

Contractor :

Instrument Used:
Model
:
Type of Test
:
Location
:

Date
Time
Weather

Initial Testing

Final Testing

:
:
:

Pressure in PSI
Item

Description Of The Item To Be Tested

Design
Req't.

Initial Rdg. Final Rdg.

Remarks

1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
Date of Initial Testing:
Remarks:

Date of Final Testing:

Recorded by:
Contractor

Witnessed and Certified by:

Site Arch't./ Engineer

CMT Head

QA/BTO Head