Professional Documents
Culture Documents
CONSULTING ENGINEERS
Civil &Structural Engineering Consulting
P.O Box 6851
Harare
Tel. 04-771484
Cel. 0773 282 522
FEBRUARY 2015
INFRASTRUCTURE DESIGN
PARAMETERS FOR RESIDENTIAL
DEVELOPMENT
CONTENTS LIST
Page
1. INTRODUCTION
1.1
General
1.2
Town Planning
1.2.1
2. SITE DESCRIPTION
2.1
Location
2.2
Topography
2.3
Geology
3. PARAMETERS OF DESIGN
3.1
Design References
4.1
4.2
Local Roads
4.1.1 General
10
11
2
4.3
4.4
4.2.1 General
11
4.2.2 Design
11
4.2.3 Materials
12
12
13
Sewer Reticulation
13
13
13
14
15
15
Water Reticulation
16
16
16
16
18
18
1. INTRODUCTION
1.1
General
Dande Civils was appointed by Waverley Cooperative for the design of their
infrastructure services for 271 stands for residential purpose. This design report
forms part of the Consultants appointment and covers the strategy for the
planning, designing and construction of the of the infrastructure services.
Weaverley cooperative intend
reticulation, for the 271 stands , with associated bulk and link infrastructure on
behalf of Kadoma Municipality.
The development principles to be adopted by the development team of Town
Planners, Engineers and Architects is to develop a township with green areas,
adopt green engineering principles and appropriate engineering technologies
as is practical.
Engineering Reticulation Services will therefore be as follows;
Civil Engineering
-
1.2
Town Planning
1.2.1
The original Town Planning from the own plan developed by the
Regional Office of the Department of Physical Planning was used. This
town plan was the layout used for the initial civil design.
1.2.2
Topographical Survey
Detail
on
site
topographical
survey
is
design of,
Sewer reticulation
Roads reticulation
2. SITE DESCRIPTION
2.1. Location
The proposed housing development is located on portions of Subdivision A of
Plot 3 of Railway Farm 9 situate in the district of Kadoma and is situated in
Kadoma.
2.2 Topography
The site generally slopes down towards stand number 3666
2.3 Geology
Attached is a preliminary site assessment of the insitu soils Appendix 1.
Material is generally SG5-SG9 material with a few areas with SG3
3. PARAMETERS OF DESIGN
CIVIL
ZIMBABWE
Ministry of Local Government & Housing for Water, Sewerage, Road
& S/W BCHOD : 1981
-
SOUTH AFRICA
-
Local Roads
4.1.1
General
The road reticulation system within the Township is developed on the following
principles :-
Design speed on the roads is to be limited to 40 km/hr by the use of traffic calming
measures mini traffic circles or speed bumps. However, and where possible, the design
stopping / site distance is to be designed for a traffic speed of 60km to ensure additional
safety within the local streets for pedestrian movement.
Adjacent all local streets and the bus route, one side only , paved footways are to be
installed providing all weather pedestrian movement facility.
Roads geometric and pavement design has been undertaken with criteria from the
Guidelines for the Provision of Engineering Services in Residential Township issued by the
National Housing Board SA.
4.1.2 Road Cross-Sections
Class 4 Road- Local bus route
18m Road Reserve
-
Edging support of pre cast concrete mountable kerb on low side and pre cast
concrete edging on high side
900mm wide footway on low side (Acts with the road as an additional paved
S/W channel in the event of substantial storm water discharge.
Classification
8
Design speed
40km /hr
60km/hr for site stopping ,horizontal and vertical
alignment where feasible.
Edging support of pre cast concrete mountable kerb on low side and pre cast
concrete edging on high side
900mm wide footway on low side (Acts with the road as an additional paved
S/W channel in the event of substantial storm water discharge.
Reserves to be top soiled and grass seeded to avoid erosion and provide a
visually pleasing finish to the reserves.
Classification
4.1.3
Horizontal Alignment
Due to the restrictions of Town Planning, certain horizontal curves on the roads will
not meet the minimum centre line radii and curve widening may need to be applied
if desirable and practicable
- Centre line radii required
-18m reserve- 40m Min R
- 10m Reserve- 10m Min R
- Junctions inner radii for bell mouth
4.1.4
Vertical Alignment
Road Gradient
Class 4 Max gradient 10% Class 5
Max gradient 12%
In certain short sections of roads these grades will need to be exceeded to ensure
stormwater control and avoidance of erosion to reserves, as the dictates of the topography
and design in minimizing cut/fill requirements.
Vertical Curves
Class 4
Class 5
Pavement Design
Road Class 4 :
Class E1
Class ER / EO
General
As noted in Section 4.1 the local residential access roads are to be utilized as far as
possible to transmit localized Storm-water discharge to U/G pipe system or side
drains.
The pipe system, side drains or direct discharge from the roads via kerb chute outlets
will transfer the storm-water discharge into the three existing drainage channels on the
northern side of the development area of 271 stands.
Local design storm intensity will be for 1:5 storm discharge with 1: 10 year storm
surcharge onto the roads.
The roads and road reserves will also act as the major S/W discharge conduit for
storms up to 1:50 year intensity.
4.2.2
Design
Topography
Paved areas
11
Channelized Flow
4.2.3
-
Materials /Installation
Inlets to U/G pipework will be via kerb inlets or gulley inlets with concrete inlet
chambers and brick manhole chambers
Concrete inlet channels will be used to increase the capacity of the standard
2m long Kerb inlets with end inlet to the KI to cater for the additional flow.
Concrete chute outlets (precast and insitu) will be used on kerbed roads to
discharge to open drainage systems
Pipework will be precast concrete pipes with spigot and socket flexible joints
equivalent to Class C pipework with Class B bedding full granular surround and
bedding factor 1.8.
Cover under roads to be 1m to soffit but with concrete surround, 750 mm to soffit
will be acceptable provided a minimum of 450 mm cover to the pipe is available
when the road pavement is being constructed.
Open drains will be designed to suit the required flows with concrete or stone lining
to avoid erosion where required.
4.2.4
At the bottom of steep roads when the flow cannot change direction due to
velocities or horizontal alignment requirements of the Town Planning Layout
The open areas will generally be graded to form a central shallow V drain which may or
12
may not have the invert lined dependent upon stormwater discharge velocities.
However, as drain lining can also act as paved walkways I is considered that lining of the
invert should be undertaken
4.2.5
-
Potential perched water tables at the intersection of the granite sills and
granite whale backs
In these areas single aggregate stone bedding will be used to ensure protection to
underground pipework and open concrete lined drains and underground fin drains
will be installed adjacent roads to protect the road pavement.
4.3
Sewer Reticulation
4.3.1 Sewer Capacity
The Design Approach to Water and Sewerage Problems Relative to Urban
(Predominantly High Density) and Rural Communities in Zimbabwe and Guidelines
for the Provision of Engineering Services and Amenities in Townships DevelopmentSouth Africa identify typical water consumption rates in urban centers as:
Item Description
Return to Sewer
Medium Income
Design Guideline
4.3.2
The designs developed for sewer reticulation are based on data contained
above. Designs have taken into account the following.
-
Ease of maintenance
13
Sewerage reticulation is mid-block where the plan and terrain permits it. The
sewer lines are located at 1.0 meter from the stand (plot) boundary.
The minimum pipe size is 110 millimeters in diameter. (O/D UPVC)
Sewage velocities have been designed to be high enough to transport solids,
but not so high that scouring of pipes would occur. Minimum velocities for
design have been achieved at the daily peak, which is not less than 0.6 m/s
with pipe flow 0.5D.
Peak flow factors have been limited to 5.25 x dry weather flow which is the
requirement to meet the blue standard of reticulation design as per Zimbabwe
regulations.
Stand connections are to be Y-connections, capped and attached to markers
to indicate their location. Each connection shall be located at the lower end of
the stand. If convenient erf connection will be made directly to the sewer line
M.H.
The design for connections has been based on 1:60 fall from any point on the
stand GL. +450mm (min) to give a minimum connection depth to the main
161mm dia sewer line.
Manholes have been located at a maximum spacing of 80m for 110mm
diameter pipes and 90m for pipes of 225mm diameter and above. Manholes
locations for larger diameter pipes have been designed to accommodate the
maintenance equipment available to the maintaining authority.
4.3.3
Computer Analysis
Manhole invert
Pipe grades
Drop manholes
Gradients
Maximum
Minimum
160
1:10
1:120
200
1:16
1:150
250
1:24
1:200
315
1:30
1:300
400
1:40
1:350
675
1:70
1:600
Material Specification
The pipeline material to be used is uPVC pipes sewer class 34 with flexible spigot
and socket joints for all sewer reticulation. Pipework above ground on pipe bridge
sections will be Mild Steel coated and painted as specified with Viking Johnson
Coupling Joints to allow for expansion.
Manholes are to be pre-cast concrete rings 1m dia unless noted on the drawings.
15
Water Demand
Design Guideline
1000liters/stand/day
South
Medium Income
African
Guidelines
2
Schools - Day
20liters/ pupil/day
Zimbabwe Guidelines
Shops
20 liters / Employee
Zimbabwe Guidelines
Bars
Zimbabwe Guidelines
Offices
20 liters / Employee
Zimbabwe Guidelines
4.4.2
The designs developed for water reticulation are based on data contained in
the above documentation.
Designs have taken into account the following :Phase 1
-
Average Flow + Fire Flow from 1no. Hydrant to be used for final pipe
sizing.
4.4.3
Design Parameters
Item Description
1
Design Guideline
Zimbabwe Guidelines
Zimbabwe Guidelines
Zimbabwe Guidelines
Fire Flow
Zimbabwe Guidelines
75mm diameter.
Adjacent to Institutional centers - additional Fire
Hydrant
7
Institutional Demand
Schools Boarding 80 liters / Boarding pupil
Zimbabwe Guidelines
Zimbabwe Guidelines
17
Zimbabwe Guidelines
to processes used.
Dry services industry 10 000 -15 000 liters /Ha
Wet Industrial to be individually
assessed.
8
SA Guidelines
4.4.4
Computer Analysis
Flow (l/s)
Velocity (m/s)
Pressure (m)
4.4.5
uPVC pipes Class 9 with spigot and socket joints for all water reticulation
pipelines
18
Joints
connections for
Bends to be
uPVC pressure bends up to 450 .with spigot and socket
joints
All bends, tees etc required thrust block as specified on the drawings.
19
TITLE
Project Team
Dande Civils
Client
Weaverley Cooperative
Client Project No
..
Status of Report
Final
Morad Report No
10 February 2015
Hons
Initials & Surname
Peer reviewed
by
Signature
Date
Signature
Date
M Kaendeza (Pr.Eng)
Initials & Surname