Professional Documents
Culture Documents
In this paper, the project management process adopted to address the Key Challenges
like Management, Planning and Reporting methodology during execution of the project are
summarised.
2.0 Evolution of Program Management System for the Project
The main stake holders in the project were Indian Air Force (IAF), Hindustan
Aeronautics Limited(HAL) and Foreign Business Partner, During the initial phase of the
project dedicated program manager for the entire program was appointed with complete
responsibility and authority for all technical performances, cost and schedule aspects. As
the project was of complex nature with stringent time constrains having stakeholder
remotely located key challenge was to evolve an efficient and cost effective program
management methodology for successful execution of the project. The process flow was
evolved which was also concurred by all the stakeholders. The process flow adopted is
given in figure-1.
Program Reviews
4.1
Agenda
Attendees
The agenda also included core Stake Holders as well as part time Stake holders
who were directly or indirectly attributed in the Program. It was ensured that the attendees
collectively consist of appropriately qualified and empowered personnel who were capable
of fully supporting the Review and making decisions on the points undergoing review.
All documents nominated as part of a review package were reviewed and
commented on by concerned Stake Holders prior to commencing the design review. The
comments were implemented prior to the design review, which was an entry criteria for
each review.
4.1.3
Review Conclusion
Formal design review minutes were circulated to all the concerned Stake Holders.
The action log together with the action needs and dates for completion was published
within the review completion.
published with all appropriate attachments within One week of conducting the meeting.
The minutes of joint meetings was signed jointly by concerned Stake Holders.
Completion of each review was considered to be achieved upon issue of the
formal minutes and completion of any relevant actions to the satisfaction of concerned
Stake Holders.
Regular review of the actions was carried out during the weekly reviews.
In case, it was found that the review is not satisfactory as per the technical
baseline, necessary changes in the design were carried out along with re-conducting of the
review.
4.1.4
Review Requirements
On request of Stake holders, certain reviews were combined to ensure the most
cost effective process and time savings.
4.2
Entry Criteria: The documents required for review prior to commencing the PDR
Conclusion: The review was formally agreed by all stake holders that the design is
sufficiently mature to pass into the detail design, development and manufacturing process
and there is an acceptable route to clearance.
4.2.2
2.
3.
4.
Entry Criteria:
Successful completion of PDR, action list of PDR and the documents required for review
prior to commencing the CDR.
Conclusion:
Declaration of design and performances was signed and ensured that design was mature
enough to go ahead for implementation / production activities.
4.2.3
4.2.4
4.2.5
4.3.
Summary
Kick-off Meeting
Kick of meeting with participants of all Stake Holders were held to present all the
preparation and efforts done in for the implementation of the program. Discussions
included but were not limited to internal plan, program organization, resources etc.
4.4.2
Progress Meetings
Regular internal progress meetings were held to review the progress.
4.4.3
basis were held at a mutually agreed time. The purpose of the meeting was to hold
detailed technical discussions and any associated issues of the program.
Overall progress/performance was determined with corrective action defined
where appropriate. Issues that were beyond the responsibility / scope of the meeting
representatives was highlighted and raised to appropriate levels of management within
each organization. An action log was maintained to record the technical issue status. The
objectives and timescales of the actions were set during the review.
4.5.
Program Reports
Every month progress report was submitted to concern authorities. The report
includes the following:
4.6
Tasks achieved in the previous month with reference to the program plan
Risk status
Payment status
Program Plans
5.1
Risk Management
Risk Management process was defined to tackle risks in the program. The
objective of the risk management system was to early identify and track risks in the
program and systematically reduce the elements that could affect the ability to meet the
program technical, cost or schedule objectives. The risk register was reviewed at every
progress meeting to ensure that the status of the risk is current and that an appropriate
mitigation strategy is available.
5.2
Configuration Management
Configuration Management plan was implemented for the program, in accordance
with procedures defined.
5.3
Data Management
Comprehensive data depositary for all data generated for program was
maintained. Every task was documented to ensure complete audit trails for every task
performed. Data base was maintained for all the deliverables data items, their issue and
status of their delivery.
Business Benefit
This project was executed on Pilot Project. Based on the successful
implementation of pilot project concept, further follow on project on similar line is in
process.
Lesson Learnt
Apart from language, cultural differences of foreign business partner, one of the
key learning lessons during execution of the project is schedule management. While
preparing the schedule of the program, national and other holidays of foreign business
partners and Indian holidays to be considered, otherwise schedule management becomes
crucial to achieve milestones of the project. As part of project closure, report covering
various issues, experience, lessons learnt, problems faced during execution of the
program was recorded and released.
Awards
Two Prestigious awards have been conferred by Aeronautical Society of India
(AeSI) & Society of Defence Technologies (SODET) respectively for design innovation and
considering successful execution of the project.
10
Conclusion
The project management process adopted for execution of the project was found
to efficient and effective in Indian defence project involving various stake holders like
Foreign Business Partner, HAL and government Certification agencies
Considering the thrust by the Indian government towards self reliance and Make in
India policy, one of the strategic necessities is achieving self reliance in Military
Aerospace.
Modern project management process is a powerful transformational management
methodology that has undeniably shown to help individuals and organizations successfully
plan and accomplish many difficult objectives and projects around the world. Project
management has grown, matured and spread around the world to include a robust set of
theories, principles, methodologies, practices, activities, professionals and organizations.
Adoption of systematic project management practices/models in defence sector not only
will help to attain project objectives but also provide a scope for national savings by
lowering project execution costs.
Tailored Project Management Mechanisms/Models and Practices with WIN WIN
situation for all stake holders will be a key challenge in the coming years.
References
1.
2.
3.
4.
Author Profile
Author Name
Name of the Organisation
Email
Fax
Phone
papers
on
various
topics
in
national
and
International seminar.
He is receiptant of following prestigious awards
a. Engineering Achievement Award by Institute of Engineers
b. Dr Biron Roy Trust Award by AeSI
c. Society of Defence Technology award.
He
was
also
core
member
of
team
which
received