Professional Documents
Culture Documents
Vertical Design of Ahmed Abdel Aziz Street: Project
Vertical Design of Ahmed Abdel Aziz Street: Project
College of Engineering
Department of Civil Engineering
Surveying (2)
Project:-
Vertical Design Of
Ahmed Abdel Aziz Street
Designed By:-
Submitted to:-
(2010 2011)
1- Introduction :
Route surveying is comprised of all survey operations required for
design and construction of engineering works such as highways, pipelines, canals, or
railroads. At Caltrans a route surveying system is generally associated with highway
design and construction.
A route surveying system usually contains four separate but interrelated
processes:
Works design
Construction of works
VERTICAL CURVES
In addition to horizontal curves that go to the right or left, roads also have vertical
curves that go up or down. Vertical curves at a crest or the top of a hill are called
summit curves, or over verticals. Vertical curves at the bottom of a hill or dip are
called sag curves, or under verticals.
GRADES
Vertical curves are used to connect stretches of road that go up or down at a
constant slope. These lines of constant slope are called grade tangents The rate of
slope is called the gradient, or simply the grade. (Do not confuse this use of the term
grade with other meanings, such as the design elevation of a finished surface at a
given point or the actual elevation of the existing ground at a given point.) Grades
that ascend in the direction of the stationing are designated as plus; those that
descend in the direction of the stationing are designated as minus. Grades are
measured in terms of percent; that is, the number of feet of rise or fall in a 100-foot
horizontal stretch of the road.
After the location of a road has been determined and the necessary fieldwork has
been obtained, the engineer designs or fixes (sets) the grades. A number of factors
are considered, including the intended use and importance of the road and the
existing topography. If a road is too steep, the comfort and safety of the users and
fuel consumption of the vehicles will be adversely affected; therefore, the design
criteria will specify maximum grades. Typical maximum grades are a 4-percent
desired maximum and a 6-percent absolute maximum for a primary road. (The 6
percent means, as indicated before, a 6-foot rise for each 100 feet ahead on the
road.) For a secondary road or a major street, the maximum grades might be a 5percent desired and an 8-percent absolute maximum; and for a tertiary road or a
secondary street, an 8-percent desired and a 10-percent (or perhaps a 12-percent)
absolute maximum. Conditions may sometimes demand that grades or ramps,
driveways, or short access streets go as high as 20 percent. The engineer must also
consider minimum grades. A Street with curb and gutter must have enough falls so
that the storm water will drain to the inlets; 0.5 percent is a typical minimum grade
for curb and gutter (that is, 1/2 foot minimum fall for each 100 feet ahead). For
roads with side ditches, the desired minimum grade might be 1 percent; but since
ditches may slope at a grade different from the pavement, a road may be designed
with a zero-percent grade. Zero-percent grades are not unusual, particularly through
plains or tidewater areas. Another factor considered in designing the finished profile
of a road is the earthwork balance; that is, the grades should be set so that all the
soil cut off of the hills may be economically hauled to fill in the low areas. In the
design of urban streets, the best use of the building sites next to the street will
generally be more important than seeking an earthwork balance.
2- Methodology:
1. First of all to make a longitudinal section you must marking all the points
which needed to be studied , by opening the tape for a fixed distance(20 m)
then mark the point "it is recommended that the distance between the
points be equal each other to make the calculation easier ".
2. After marking the points, setup the level in a suitable place "covers number
of points".
3. After leveling the level, take the reading of the staff to each point and
tabulate the readings.
4. If the level did not cover all of the points you must move it to another station
and continue taking the reading (Remark:- the first reading taken at every
instrument station called back sight (BS),the last reading taken at every
instrument station is called foresight(FS) , the point which take the two
reading is called turning point).
5. After we take all the measurements we make a table and calculate the
elevation of the points by rise and fall methods or by HI method.
A. Collection Data's
Station
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Distance
0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300
320
340
360
380
400
22
23
24
25
SUM
BS
3.77
IS
FS
3.66
3.56
3.46
3.28
2.91
2.17
1.76
1.52
1.55
1.46
3.21
0.03
0.75
0.7
1.74
1.82
2.36
0.41
0.09
0.71
0.93
0.8
0.49
0.29
0.8
3.28
1.34
1.65
1.86
2.64
3.19
420
440
460
480
9.93
3.75
8.48
6.36
Checks:-
Fall
0.11
0.1
0.1
0.18
0.37
0.74
0.41
0.24
2.28
1.48
0.99
2.54
Rise
#.of BS = #.of FS (4 = 4)
BS FS Rise Fall RL Last RL First 1.45
0.08
0.54
0.92
0.93
0.31
0.21
0.78
0.55
0.56
4.91
RL
21.45
21.56
21.66
21.76
21.94
22.31
23.05
23.46
23.7
23.67
23.76
24.47
25.4
26.2
26.69
26.98
27.78
27.7
27.16
26.24
25.31
25
24.79
24.01
23.46
22.9
Notes
START
TB
TB/ISP
TB
BM
END
23.67 - 21.45
100% 1.26%
180
27.81 23.67
Slope 2
100% 2.76%
150
22.56 27.81
Slope 3
100% 3.5%
150
Slope 1 =
D. Design Level :
- Calculations
DLane po int DL g S
For example :
po int (5) DL5 DL g 1 S
21.4 (0.0126 100) 22.66 m
po int (12) DL12 DL g 2 S
23.67 (0.0276 60) 25.33 m
po int (5) DL20 DL g 3 S
27.81 (0.035 70) 25.36 m
GL DL () CUT
GL DL () FILL
For Example
Po int (5) 22.31 22.66 0.35m ( Fill )
Po int (21) 24.79 24.66 0.13m (Cut )
v2
Where:
2 g ( f i)
2- After knowing the length of the curve we calculate the distance between VPI and mid
point of the curve
A L
8
For Sag Curve:
0.015 40
0.075m
8
For Summit Curve:
0.0626 40
8
0.313m
19.44 2
204m
S 2 19.44 2.5
2 9.81(0.35 .0126)
Length of curve a.
b.
a.
b.
S LL
A S 2
S LL
1.22 .035 S
1.22 .035 S
S L L 2 S
A
0.015 204 2
74.67 m ( wrong )
L min 0m So L 40m
19.44 2
199.29m
S 2 19.44 2.5
2 9.81(0.35 0.0276)
Length of curve a.
b.
a.
b.
S LL
S LL
A S 2
2 he ho
S L L 2 S
0.0626 199.29 2
2 1.05 1.05
2
S L L 2 199.29
.0626
A
2
he ho
295.98m( wrong )
1.05
1.05
264.395m( wrong )
Form similarity of triangles we can find the other point of the vertical curve
Sag curve
VPI
VPT
VPC
20m
20m
X
5
X
Y
10
15
20 0.075
20
Remark: we apply the points on both sides of the vertical curve
Y
0.01875
0.0375
0.05625
0.075
VPI
VPC
VPT
20m
20m
X
5
X
Y
10
15
20 0.313
20
Remark: we apply the points on both sides of the vertical curve
Y
0.07825
0.1565
0.23475
0.313
Falling Gradients
-g
0
0
21.45
21.4
0.05
0
9
180
23.67
23.67
0
0
1
20
21.56
21.65
0
0.09
10
200
23.76
24.22
0
0.46
17
340
27.7
27.46
0.24
0
18
360
27.16
26.76
0.4
0
2
40
21.66
21.91
0
0.25
11
220
24.47
24.77
0
0.3
19
380
26.24
26.06
0.18
0
3
60
21.76
22.16
0
0.4
12
240
25.4
25.33
0.07
0
20
400
25.31
25.36
0
0.05
4
80
21.94
22.41
0
0.47
13
260
26.2
25.88
0.32
0
21
420
24.79
24.66
0.13
0
5
100
22.31
22.66
0
0.35
6
120
23.05
22.91
0.14
0
14
280
26.69
26.43
0.26
0
15
300
26.98
26.98
0
0
22
440
24.01
23.96
0.05
0
7
140
23.46
23.17
0.29
0
16
320
27.78
27.53
0.25
0
23
460
23.46
23.26
0.2
0
24
480
22.9
22.56
0.34
0
Cut 3.2 m
Fill 2.37 m
Cut Fill 3.2 2.37 0.83 m
5- Comments:
The length of the vertical curves (Sag & Summit) can not be measured from the
equations, the answers is not accepted because the design velocity we taken and other
factors not accurate, so we assume the length of curves (Sag & Summit) equal 40m as
the supervisor engineering. Other calculation approximately accurate.
6- Recommendations:
We should take the data's accurate such that (Design velocity, Friction coefficient of
road surface) in order to achieve the correct results and corrected design.
7- Maps:
The drawing is attached in the end of the project
8
160
23.7
23.42
0.28
0