The new CCC system has the following key points:
1. The CCC is issued by the Principal Submitting Person (PSP) like an architect or engineer, replacing the previous "qualified person". Building plans still need LA approval.
2. The CCC is only concerned with health, safety and essential services. Non-technical issues are resolved separately. It is also only issued once construction is completed per approved plans.
3. Six essential service departments like the water and electricity authorities must confirm works before the PSP issues the CCC to owners and developers, with a copy to the LA.
4. The CCC system aims to provide better protection for homebuyers by allowing vacant
The new CCC system has the following key points:
1. The CCC is issued by the Principal Submitting Person (PSP) like an architect or engineer, replacing the previous "qualified person". Building plans still need LA approval.
2. The CCC is only concerned with health, safety and essential services. Non-technical issues are resolved separately. It is also only issued once construction is completed per approved plans.
3. Six essential service departments like the water and electricity authorities must confirm works before the PSP issues the CCC to owners and developers, with a copy to the LA.
4. The CCC system aims to provide better protection for homebuyers by allowing vacant
The new CCC system has the following key points:
1. The CCC is issued by the Principal Submitting Person (PSP) like an architect or engineer, replacing the previous "qualified person". Building plans still need LA approval.
2. The CCC is only concerned with health, safety and essential services. Non-technical issues are resolved separately. It is also only issued once construction is completed per approved plans.
3. Six essential service departments like the water and electricity authorities must confirm works before the PSP issues the CCC to owners and developers, with a copy to the LA.
4. The CCC system aims to provide better protection for homebuyers by allowing vacant
THE CCC is issued by the Principal Submitting Person (PSP), who is a professional architect, professional engineer or a registered building draughtsman who submits building plans. These individuals, who were previously known as the qualified person, are now known as the Principal Submitting Person [PSP] under the amended Act. Building plans are still required to be submitted and get approved by LA LA are allow to inspect the site at any time and to issue a notice if there is a breach and issue a notice in writing to a PSP to stop issuance CCC if the breach is not rectified The issuance of CCC is restricted to only technical issues concerning health, safety and essential services. For the Non-technical issues will have to be resolved between the Owner and the Local Authorities at the planning and building plans approval stage THE CCC will only be issued after the building has been completed according to the building plan approval
Six essential services for issuance of CCC
Clearances for Six [6] essential services from the following authorities: it means that the department has confirm and accept the work. 1. Tenaga Nasional Berhad [TNB] - confirmation of electrical supply, 2. Water authorities [SYABAS, JBA, LAP, JAS etc] - confirmation of water supply, 3. Sewarage Services Department (Jabatan Perkhidmatan Pembetungan) [JPP] confirmation of connection to sewerage treatment plant or mains, 4. Department Safety and Health (Jabatan Kesihatan & Keselamatan Pekerja) [JKKP] - clearance from lifts and machinery department, 5. Fire and Rescue Department (Jabatan Perkhidmatan Bomba & Penyelamat) [Bomba] - clearances for active fire fighting systems and, 6. Roads & Drainage Department [PBTs Internal Departments or JKR].
The roles and responsibilities of PSP
Inform local authority of the commencement of construction works on site SUPERVISE construction works on the site
REPORTING if there is any breach of construction, explaining reasons for breach
and stating recovery actions in the event of a breach during construction ENSURING 21 forms G are completed Upon satisfactory completion of the Works and obtaining the six [6] essential services departments, then PSP issue the CCC to owners and developers and present a copy to the LA and the Professional Board
The benefits of the CCC system
VACANT Possession (VP) can be issued together with the CCC. This can overcome problems that are facing by the CFO where home buyers receive the house keys but cannot move in because the CFO has not been issued responsibility process in the matrix form, where actions can be taken on the responsible party in the event of failure in a building, hence the work quality will be ensured It seeks to provide better protection for house buyers, cut red tape or bureaucracy in local government and create a more efficient public delivery system.