Professional Documents
Culture Documents
Almost in every S/D Ash Cooler mobilising path job finds a good place
for itself. Finally in the last Boiler-2 S/D the repairing of path line carried
out in presence of the refractory people and it is now working well.
Boiler-1 annual O/H could not
be taken in its normal time (June-03) due to many reason and deferred
to 2nd Qtr of 03-04. Power assistance for smelter from grid are
subjected to healthy reservoir level in Hirakud Dam. Keeping all them
in view it was decided to take Boiler-1 for annual shutdown in Aug 1 st
week.
During the month of May-03 the Ash
Cooler were out of normal operation. Not a single Ash Cooler had RVF
in it and normal ash flow to ash Cooler was not taking place with
mobilising command. Slowly service airline operation became the
practice for ash evacuation. The condition further detoriated in the 3 rd
week of May-03. With low GCV coal, ash generation became high and
normal effort for bottom ashing was not enough to tackle the
increasing bed pressure. Loop seal draining was tried but not much
encouraging result could be achieved through this. As the output from
Boiler was not upto expectation, finally it was decided to take outage
on 20th May night owing to high bed pressure. Accordingly planning
was done and power assistance also obtained from grid.
In the night it was decided by the people present in
the shift to take a last chance with the Ash Cooler. Manpower
assistance taken from MMD and nos of pocking rod made. People