Professional Documents
Culture Documents
1. Please schedule every audit carefully and obtain, if necessary, your area manager
approval.
2. As per our Corporate Health Plan and general recommendations, each vessel / site /
3.
4.
5.
6.
2. Avoid as soon as possible expression instead of precise date (ex: Response due date:
18/03/2009 instead of Response due date: as soon as possible)
3. Mention all involved persons with their full name and position (ex: Organization
Representative: John Doe project doctor instead of, simply, John Doe or project
doctor.
4. Usually, the auditor mentions only non-conformities found. The auditee has the right and
duty to choose how to resolve all non-conformities. Therefore, when the auditor proposes
the corrective action and auditee agrees with, response due data should be the same
with CAR date.
5. About auditors:
1. I suggest that all Health Coordinators be involved in audits and attend recognized trainings
about how to make an audit according to OHSAS requirements.
Many thanks for those who already send me their Audit Plans for 2010,
Best regards,
Anar Mammadov, MD
SAIPEM HEALTH ADVISER
SAIPEM CONTRACTING NIGERIA LTD.
NEW OPERATIONAL BASE
Rumuolumeni, Port Harcourt
Rivers State, NIGERIA
Email:
Anar.Mammadov@saipem.eni.it
Mobile:
+234 803 9758891
Intersite Phone Co
+257