assumptions.
Executive Summary
This guidance is a further development of Sport
Englands initiative to respond to the economic
pressures faced by sports facility providers and
operators. It builds upon the previous advice
contained in Affordable Community Swimming
Pools (January 2012) and Affordable Sports Halls
(August 2012) for separate sports buildings. It
brings them together to form an Affordable Sports
Centre with a typical facility mix of swimming
pool, sports hall and health & fitness facilities. The
guidance highlights:
Business Plan
projections identify
performance within the
upper quartile of NBS
benchmarks.
The key findings
The Affordable indicative designs and cost plans
are based on the use of a rationalised traditional
building approach. Features that help drive down
costs include:
Potential uses
Contents
Introduction
Potential Income
Key issues
19
Overview
O
Table 1 - Income
O
Table 2 - Expenditure
O
Table 3 - Business plan
Potential management arrangements
Income generation
Programming
Expenditure
Staff cost
Utilities
Strategic Planning
Building Design
27
Overview
O
Table 4 - Elemental cost/m2 overview
O
Table 5 - Elemental cost breakdown
Procurement and Delivery
Building fabric
Procurement route
O
Single Stage Design and Build
Approach
O
Joint Strategy or a Split Approach
O
Separate Approach
Consultant team appointment
Structure
Contractor appointment
Services
BREEAM
29
Site plan
Ground floor plan
First floor plan
Appendix (separate)
Introduction
Key issues
Options
Courts
(badminton)
Equipment
storage
Dry changing
Swimming
pool(s)
Main pool
(lanes)
Secondary
pool
Wet changing
Buffer/
school/group
changing
Changing
places/ full
accessible
provision
Gym stations
50
100
100
100
Studio(s)
Changing
with
accessible
provision
Sports hall
Health +
fitness
Core facilities
Sports hall
The 4 court 34.5 x 20.0 x 7.5 m sports hall is to the
recommended Sport England dimensions along
with a sports equipment store of 12.5%. The larger
design options allow a 5 court 40.6 x 21.35 x 7.5 m
sports hall to be included in the economical
rectangular plan.
Swimming pool
Views up to gym
Views of feature
stair up to health
and fitness and to
sports hall
Entrance / foyer /
pool hall opened
up to main access
from both footpath
and car parking
Changing space
Dance studio(s)
Movement and dance studios are included in the
larger schemes in association with the health and
fitness areas. This can increase the range of offer
to the fitness members and a wider market.
Strategic Planning
There are many permutations of leisure centres
around the country that reflect the particular
demographics and pattern of existing facilities in a
locality. It is critical for the success of any sports
centre project that a strong project brief is created
based on clearly articulated needs and a strong
evidence base.
A clear understanding of what is required is crucial
to the long term success of any sports centre and
it is important that the project is developed in a
consistent and logical way.
Advice on how to plan the right sports centre to
suit the needs of a locality can be found on the
Sport England web site. Sport Englands Facilities
Planning Model (FPM) should be used to ascertain
the facilities required in any given location.
A simplified version of the FPM has been
developed with National Governing Bodies (NGBs)
and the Amateur Swimming Association to
determine specifically how to size the water space
and sports hall provision. These models are
discussed in the Affordable Sports Halls and
Affordable
Community
Swimming
Pool
documents. The 7 steps recommended to
developing the right sports hall or swimming pool
can also be applied on a larger scale to whole
leisure centres. The 7 steps are outlined below:
STRATEGIC CONSIDERATIONS
THE DECISION
Building Design
Efficient and effective design
Plant areas
Other areas.
% of GIFA
Mean
average
values
50
49.7%
40
30
21.1%
20
12.2%
11.3%
10
1.7%
Option 1
Option 2
Option 3
Option 4
Option 5
Design process
These include:
Design objectives
The key design objective is to produce compact
and efficient sports centre layouts that provide
elements in compliance with Sport England
guidance. Ancillary areas have been reviewed and
redesigned as necessary. The general objectives
of the Sport England guidance have been applied,
taking into account the likely requirements and
typical brief of operators and based on previous
feedback from those groups.
Phased development
The previous Affordable Sports Halls (ASH)
review included the development of an indicative
design for a phased development with a
community swimming pool. (See page 19 of
ASH). The options illustrated could be adapted
for a phased project.
Views up to gym
Views of feature
stair up to health
and fitness and to
sports hall
Building layouts
10
Key
Option 1
Sports hall
Changing (+CH)
Health and fitness (+HF)
Swimming pool
Circulation / lifts
Reception zone / staff
Ps
Linking reception
and rationalised
changing and plant
areas for a 25m x 4
lane swimming
pool and 4 court
hall
E
Sc s
C Sc
Iv PH
SH
Sc
Pc
E
O
R
Plant
SH
Sports hall
Equipment store
Se
Sc
Ce
Community entrance
Fc
Fe
Fs
Fitness studio
Fv
Formal viewing
Circulation
Reception
Storage
Pc
PH
Pool hall
Plant
Ps
Iv
Informal viewing
Ce
Fe
S
Se
Option 2
O
Ps
Fs
S
Cc
Fc
Fc Fc
E
Sc s
C Sc
Iv PH
SH
Sc
Pc
E
O
R
Ce
Fs
Fs
Fe
S O Fc O
Option 3
Larger swimming pool
(25 m x 6 lane) and
health and tness
facilities
Se
P
Ps
S
P
Fc
Fc
E
Sc s
C Sc
Iv
PH
Pc
SH
Sc
E
O
R
Ce
P
S
Options 4 and 5
Options for a 25 m
x 6 or 8 lane pool
with secondary
pool. Options with
or without formal
spectator viewing.
Options for 4 or 5
court sports hall
Ps
S O Fc O
Fs
Fe
Se
Ps
Fs
Fc
Fc
Sc
Iv
PH
C Sc
Pc
Sc
O
R
SH
100 station health and
fitness and two studios
at first floor level plus
spectator viewing
P
Ce
S
Fs
Fv
Iv
Fs
S
S
Fe
11
S
Fe
Fc
Fc
Fc
General provision
Sanitary provision
Pool changing
Showers
Calculated numbers of
changing spaces for a
25m x 6 lane pool
(assuming an average
changing time of
13minutes/person)
3.0
32
4.0
(Marketplace
feedback for lane
swimming)
24
4.5
(Marketplace
feedback for aqua
aerobics)
21
Note:
Lockers
Spectator viewing
Location
The indicative design options have a footprint of
between 2358m2 and 3260m2 (see area schedule
in the Appendix) and will require additional space
for pathways, car parking and landscaping to suit
a particular site. The local planning requirement for
the number of car parking spaces will be a key
variable. The typical site plan for Option 4 shown
on page 15 would need an approximate overall area
of 8,000m2 8,500m2. The particular shape and
dimensions of a site are likely to create a number
of constraints that will affect the building and site
layout. These constraints should be considered
early in the project development process.
Access
Locations of services
Orientation
Geotechnical conditions.
Building fabric
Photovoltaic system
Services
Waste recycling.
Structure
The design is to take the buildings functional
requirements fully into account. The structural grid
is to be chosen to achieve the most efficiency in
terms of use and cost. Please refer to the ASH
and ACSP documents for details on the structure
proposed for the pool and sports hall.
BREEAM
The development is designed to be assessed under
the BREEAM criteria and achieve a minimum rating
of Very Good. The scheme to achieve a good
reduction in CO2 emissions in line with the current
building regulations and local planning requirements.
This review assumes the following items would be
incorporated to assist in attaining BREEAM credits:
14
95
94
93
92
91
90
89
88
87
86
85
84
83
82
81
80
Access to first
aid room
79
78
Service yard
Emergency
vehicle
parking
bay
Plant delivery
77
2
Chemical store
delivery
9
76
Staff parking
Emergency exit
75
Extent of 5 court hall option
74
58
Emergency exit
57
73
56
72
Emergency
exit
Emergency exit
71
15
55
70
54
69
53
68
52
67
51
66
50
65
49
64
48
63
47
62
46
61
45
44
Emergency
exit
Emergency exit
59
Emergency exit
bench
35
ENTRANCE
36
37
38
39
40
41
42
43
Raised pedestrian
crossing to act as
traffic claming
measure
NOTE
The 'Affordable' sports centre document is
not site specific and this drawing is
intended to illustrate the relationship of the
components required to produce a
satisfactory layout.
Drop
off
point
Motorcycle
parking
Assistance dog
rest area
60
Raised pedestrian
crossing to act as
traffic claming
measure
34
33
32
31
30
29
28
27
26
25
24
23
22
21
20
19
18
10
11
12
13
14
15
16
17
Raised pedestrian
crossing to act as
traffic claming
measure
Coach parking /
Drop off point
North
0
10m
Centre signage
Centre signage
15
Key
Staff area
Reception / circulation
First
aid
First aid
Main entrance
Sports hall
Health and fitness
Plant
Pool store / stores
Pool hall
Pool Tank
5 court option
Cl.St
Pool Store
Plant
Equipment
store
Wet Changing
Dry Changing (sports hall)
4 court option
D.Sh
Sh
W
L
Main pool
WC
Buffer changing
16
Protection guarding
V
L
Wet changing
Sh
Dry changing St
V Sh Sh Sh Sh D.Sh
Sh
Sh
D.Ch
/ WC
V Sh Sh Sh Sh D.Sh
L
DWC
Cl.St
WC
Dividing net
Sh
Sh
F/D
Secondary pool
CPF
FWC
D.Ch
/ WC
D.Sh
DWC
Unisex accessible WC
F/D
FWC
Female toilets
MWC
Male toilets
Locker
Sh
Shower
Vanity area
WC
Unisex toilet(s)
Cl.
Sh Sh
D.Ch/WC
Key views
F/D
DWC
F/D
W
MWC
Sh F/D
Cleaners store
Changing Places Facility
Sports hall
Cl. St
CPF
Office
Lift
Equipment
store
Lift
DWC
Reception
Vending
Lobby
16
10m
Key
Staff area / IT / Store
Circulation
Health and fitness
Plant
Stores
Pool hall spectator viewing
Void
Plant
Store
Exercise studio
Cl. St
Cleaners store
D.Ch/WC
D.Sh
DWC
Locker
Sh
Shower
Vanity area
WC
Unisex toilet(s)
Key views
Exercise studio
Store
17
Store
L
Staff
DWC
Store
Wc
Wc
Lift
D.Sh
Sh
Sh
Changing
Sh
Staff
D.Ch
/ WC
Lift
Cl.
St
Wc
Wc
D.Sh
Sh
Sh
Changing
Sh
17
10m
Entrance elevation
Views up to gym
Main entrance
Pool hall
Long section
Fitness studio
18
Sports hall
Pool hall
Wet changing
Cross section
Buffer
changing
Equipment
store
Plant
Plant
Main entrance
Reception
Dry
Corridor
changing
Toilets
Wet changing
18
Potential Income
Overview
Table 1 - Income ()
800,000
700,000
600,000
500,000
400,000
300,000
200,000
Option 5
100,000
Option 3
Option 1
Key
Option 1
Option 2
Option 3
Option 4
Table 2 - Expenditure ()
Option 5
900,000
800,000
700,000
600,000
500,000
400,000
300,000
Option 5
Option 4
Option 3
200,000
100,000
-
Option 2
Option 1
19
An NPDO operator who will receive 80% mandatory rate relief from NNDR
Depreciation / capital costs / sinking funds and other below the line costs are excluded
Options 3, 4 and 5 include a 100 station health and fitness gym + 2 studios
Budget
BudgetSummary
Summary
Income
Income and Expenditure
Mature
Year (3)
Option 1
Mature
Year (3)
Option 2
Mature
Year (3)
Option 3
Mature
Year (3)
Option 4
Mature
Year (3)
Option 5
Income
Swimming Pool(s)
Sports Hall
Health and Fitness
Studios
Secondary spend
Other - miscellaneous
Total Income
Option 1
463,195
91,831
37,526
14,814
607,366
Option 2
430,204
86,200
375,493
19,998
58,988
24,272
995,156
Option 3
515,522
86,200
656,253
41,513
80,389
34,497
1,414,374
Option 4
621,903
86,200
656,253
41,513
100,075
37,649
1,543,592
Option 5
712,151
109,835
656,253
41,513
122,569
41,058
1,683,379
Operational Expenditure
Staffing
Premises
Administration
Supplies and Services
Other - miscellaneous
Total Expenditure
Option 1
411,798
175,560
38,750
30,163
12,224
668,495
Option 2
639,009
230,538
53,849
51,949
16,817
992,162
Option 3
782,118
299,299
71,747
59,629
21,534
1,234,327
Option 4
837,084
327,404
78,430
71,297
23,857
1,338,072
Option 5
889,578
374,759
88,522
85,619
27,445
1,465,923
Operational Profit/(Loss)
(61,129)
2,994
180,047
205,520
217,455
208,477
327,714
459,364
500,375
544,751
Throughput
20
Budget
BudgetDetail
Summary
Mature
Year (3)
Option 1
Mature
Year (3)
Option 2
Mature
Year (3)
Option 3
Mature
Year (3)
Option 4
Mature
Year (3)
Option 5
Swimming
Casual
Lessons
Schools
Clubs
Other
Swimming sub total
274,925
109,600
30,420
45,000
3,250
463,195
241,934
109,600
30,420
45,000
3,250
430,204
274,517
128,000
31,005
45,000
37,000
515,522
349,763
140,800
41,340
45,000
45,000
621,903
408,576
163,200
43,875
54,000
42,500
712,151
Sports Hall
Courses
Clubs
Schools
Pay and Play (casual)
Sports Hall sub total
23,739
24,000
9,728
34,364
91,831
23,739
24,000
9,728
28,733
86,200
23,739
24,000
9,728
28,733
86,200
23,739
24,000
9,728
28,733
86,200
23,739
30,000
12,160
43,936
109,835
326,993
48,500
375,493
574,253
82,000
656,253
574,253
82,000
656,253
574,253
82,000
656,253
Studio(s)
Classes/courses
General Hires (meetings)
Studio(s) sub total
13,123
6,875
19,998
23,638
17,875
41,513
23,638
17,875
41,513
23,638
17,875
41,513
Secondary spend
Merchandising
Vending
Secondary spend sub total
6,254
31,272
37,526
9,831
49,157
58,988
22,968
57,421
80,389
25,019
75,056
100,075
13,619
108,950
122,569
Miscellaneous income
14,814
24,272
34,497
37,649
41,058
Total Income
607,366
995,156
1,414,374
1,543,592
1,683,379
Income
Income
21
Mature
Year (3)
Option 1
Staffing
Direct Staff Costs
On-costs
Other Staff costs
Staffing Sub Total
324,000
67,260
20,538
411,798
503,000
104,290
31,719
639,009
616,000
127,610
38,508
782,118
659,500
136,310
41,274
837,084
701,000
144,610
43,968
889,578
Premises
Utilities (Gas/Electricity)
Water / Sewerage
Insurance
NNDR
Building Maintenance & Repairs
Equipment Purchase
Equipment Rental
Equipment Maintenance & Repairs
Maintenance Contracts
Chemicals
Trade Waste Collection
Premises sub total
91,200
9,120
11,400
11,400
22,800
6,840
2,280
2,280
6,840
7,980
3,420
175,560
119,760
11,976
14,970
14,970
29,940
8,982
2,994
2,994
8,982
10,479
4,491
230,538
155,480
15,548
19,435
19,435
38,870
11,661
3,887
3,887
11,661
13,605
5,831
299,299
170,080
17,008
21,260
21,260
42,520
12,756
4,252
4,252
12,756
14,882
6,378
327,404
194,680
19,468
24,335
24,335
48,670
14,601
4,867
4,867
14,601
17,035
7,301
374,759
9,110
2,280
3,420
2,280
3,420
4,560
4,560
4,560
4,560
38,750
14,927
2,994
4,491
2,994
4,491
5,988
5,988
5,988
5,988
53,849
21,216
3,887
5,831
3,887
5,831
7,774
7,774
7,774
7,774
71,747
23,154
4,252
6,378
4,252
6,378
8,504
8,504
8,504
8,504
78,430
25,251
4,867
7,301
4,867
7,301
9,734
9,734
9,734
9,734
88,522
5,700
18,763
5,700
30,163
7,485
29,494
14,970
51,949
9,718
40,194
9,718
59,629
10,630
50,037
10,630
71,297
12,168
61,284
12,168
85,619
Miscellaneous Expenditure/Contingency
12,224
16,817
21,534
23,857
27,445
668,495
992,162
1,234,327
1,338,072
1,465,923
(61,129)
2,994
180,047
205,520
217,455
Mature
Year (3)
Option 2
22
Mature
Year (3)
Option 3
Mature
Year (3)
Option 4
Mature
Year (3)
Option 5
Facility mix
Opening hours
Staffing levels
Income generation
Maximising the income generated is the key to
financial success for this type of facility because
with the exception of staffing, most costs are fixed.
When planning facilities, it is advisable to
investigate the supply and demand for health and
fitness within the catchment area. The number of
fitness stations (pieces of equipment) should be
related to the identified latent demand. Generally,
the greater the number of stations, the more
cost-effective the facility will be and the health and
fitness facilities will be presented as the core offer
for a membership scheme.
23
Programming
The operating philosophy will determine the
programme. Most local authorities will want to
encourage a balanced programme for both wet
and dry areas, which should include:
Staff cost
Casual use
Group activities
Club sessions
Special events
Utilities
Schools.
Expenditure
The other side of the financial equation is the cost
associated with operation. These can be
sub-divided into a number of categories including
staffing costs, premises related expenditure,
administrative costs, supplies and services and
miscellaneous costs. These can be generically
described as above the line costs because they
are directly related to the operation of the facilities.
There are often some additional below the line
costs depending on the operating method and
accounting protocols. These non-operational
costs can include a management fee, depreciation,
head office overheads or corporate re-charges
sinking funds etc. When planning new facilities,
these below the line costs must be considered
by local authorities.
24
Insurance
Refuse collection
Transport
Security
Uniforms
Licences
IT.
Intensity of use
Location.
Business plan
Location
Complementary facilities
Programme
Pricing.
25
26
Capital Costs
Overview
An overview of the capital costs of the leisure
centre options is given in the following tables
derived from updated GIFA analysis of Affordable
Sports Halls and Affordable Community Swimming
Pools cost data and the area schedules in the
Appendix. It is based on the following main
assumptions:
VAT excluded
1,500
/m
1,000
500
OPTION 2
4 lane swimming pool
4 court sports hall
Medium health and fitness
Preliminaries
Building Sub-Total
Fittings
Element
Option 1
Option 2
Option 3
Option 4
Option 5
Key
Substructure
OPTION 4
6 lane swimming pool plus learner pool
4 court sports hall
Larger health and fitness
27
OPTION 1
OPTION 2
OPTION 3
OPTION 4
OPTION 5
2,280 m
Total Cost of
Element
Substructure
2,994 m
Cost per m2
Total Cost of
Element
3,887 m
Cost per m2
Total Cost of
Element
4,252 m
Cost per m2
Total Cost of
Element
4,867 m
Cost per
m2
Total Cost of
Element
Cost per
m2
396,000
174
449,000
150
486,131
125
553,919
130
620,755
128
285,000
125
373,000
125
459,000
118
494,000
116
575,000
118
71,000
24
127,000
33
147,000
35
189,000
39
270,000
118
270,000
90
292,328
75
333,092
78
373,282
77
137,000
46
152,000
39
152,000
36
152,000
31
Superstructure
Frame
Upper floors
Roof
Stairs
n/a
External walls
235,000
103
279,000
93
313,000
81
338,000
79
388,000
80
114,000
50
183,000
61
239,000
61
237,000
56
250,000
51
128,000
56
249,000
83
391,000
101
424,000
100
451,000
93
40,000
18
61,000
20
79,000
20
80,000
19
85,000
17
1 072 000
1,072,000
470
1 623 000
1,623,000
542
2 052 328
2,052,328
528
2 205 092
2,205,092
519
2 463 282
2,463,282
506
Wall finishes
128,000
56
149,000
50
167,000
43
180,000
42
205,000
42
Floor finishes
150,000
66
191,000
64
234,000
60
279,000
66
320,000
66
28,000
12
44,000
15
62,000
16
74,000
17
81,000
17
306,000
134
384,000
128
463,000
119
533,000
125
606,000
125
Fittings
238,000
104
275,000
92
287,000
74
301,000
71
380,000
78
32,000
14
40,000
13
42,000
11
43,000
10
47,000
10
Ceiling finishes
Services
Sanitary appliances
Disposal installations
Incl. below
Incl. below
Incl. below
Incl. below
Incl. below
M&E Installations
824,000
361
1,112,000
371
1,477,000
380
1,614,000
380
1,807,000
371
Specialist Installations
167,000
73
167,000
56
235,000
60
275,000
65
352,000
72
78,000
34
99,000
33
133,000
34
146,000
34
167,000
34
1,101,000
483
1,418,000
474
1,887,000
485
2,078,000
489
2,373,000
488
Building Sub-Total
3,113,000
1,365
4,149,000
1,386
5,175,459
1,331
5,671,011
1,334
6,443,037
1,324
Preliminaries
356,000
156
576,000
192
739,000
190
804,000
189
883,000
181
3,469,000
1,521
4,725,000
1,578
5,914,459
1,522
6,475,011
1,523
7,326,037
1,505
Contingencies
174,000
76
237,000
79
296,000
76
324,000
76
367,000
75
Professional Fees
365,000
160
497,000
166
622,000
160
680,000
160
770,000
158
250,000
110
250,000
84
275,000
71
275,000
65
300,000
62
100,000
44
100,000
33
100,000
26
100,000
24
100,000
21
43,000
19
43,000
14
43,000
11
43,000
10
54,000
11
932,000
409
1,127,000
376
1,336,000
344
1,422,000
334
1,591,000
327
4,401,000
1,930
5,852,000
1,955
7,250,459
1,865
7,897,011
1,857
8,917,037
1,832
28
Procurement route
The choice of procurement route is critical to the
success of any construction project. Every project
has unique requirements and therefore all viable
procurement options need to be appraised at the
beginning of the project.
Approach
Joint Strategy or a Split Approach
There are often two key project elements that need
to be procured to deliver a new leisure centre. The
first is the delivery of a new capital build project
and the second is procuring an operator to manage
and operate the new centre.
29
Contractor appointment
Again, where projects are developed under the
separate approach, there are a number of
Contractor Framework Agreements available to
public sector clients that should be considered in
a procurement evaluation process. As with the
Consultant appointments above, the importance
is to ensure the potential contractors have sports
and leisure expertise.
Some contractor frameworks also provide an
opportunity to involve a contractor earlier in the
design process and this should also be considered
during the procurement review process.
30
ID
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
Task Name
Start Up
Design Team Appointed
Start up meeting
Agree Procurement Strategy
Development of Brief
Sign off brief and procurement strategy
Duration
115 days?
0 days
0 days?
10 wks
10 wks
15 days
M1
M2
2
3
135 days
4 wks
4 wks
8 wks
4 wks
11 wks
2 wks
18
19
Planning
Consultations
Preparation of application
Submit application
Register application
Determination period (13 weeks)
Consent
Judicial review (12w/3m/90days)
185 days
6 days
10 days
0 days
5 days
13 wks
0 days
65 days
173 days
10 days
0 days
0 days
8 wks
2 wks
3 wks
0 days
8 wks
0 days
4 wks
10 days
8 days
4 wks
0 days
Construction
Design development / Contractor lead in
Construction (56 weeks)
Works completion
Fit out
350 days
10 wks
56 wks
0 days
4 wks
M6
M7
M8
M9
M10
M11
M12
M13
Design
Feasibility study (RIBA stages A-B)
Client sign off of Stage B
Develop design to Stage C (8 weeks)
Client sign off of Stage C
Develop design to Stage D+/ E (10 weeks)
Client sign off Tender design
Operation
M5
9
10
11
12
13
14
Project Float
M4
24/07
27/07
80 days
30 days
30 days
30 days
30 days
30 days
30 days
80 days
M3
16
21
26
27
28
29
27/11
30
31
32
05/03
33
35
36
37
13/11
38
13/11
39
40
42
12/02
43
44
09/04
45
46
47
48
51
52
4 wks
0 days
31
ID
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
Task Name
M14
M15
M16
M17
M18
M19
M20
M21
M22
M23
M24
M25
M26
M27
M28
M29
M30
Start Up
Design Team Appointed
Start up meeting
Agree Procurement Strategy
Development of Brief
Sign off brief and procurement strategy
Surveys & Investigations
Topographical survey
Tree survey
Ecological survey
Drainage survey
Utilities assessments
Transport assessment
Environmental & geotechnical desk study / SI
Design
Feasibility study (RIBA stages A-B)
Client sign off of Stage B
Develop design to Stage C (8 weeks)
Client sign off of Stage C
Develop design to Stage D+/ E (10 weeks)
Client sign off Tender design
Planning
Consultations
Preparation of application
Submit application
Register application
Determination period (13 weeks)
Consent
Judicial review (12w/3m/90days)
Procurement of Contractor (via Restricted Procedure)
Develop Memorandum of Information (MoI)
Publish OJEU
Press Release
Pre-Qualification Questionnaire (37 days)
Evaluation of responses
Prepare Employer's Requirements / tender documents
Issue Tender documents
ITT - Restricted Procedure
Tenders due back
Tender clarifications
Submit Tender Report & Approval
OJEU 'Alcatel' stand down
Agree Contract Documents
Appoint Contractor
Construction
Design development / Contractor lead in
Construction (56 weeks)
Works completion
Fit out
53
54
05/10
Project Float
59
Operation
32
30/11
Guide
htp:/www.sportenga
l nd.org/factiles-pa
l nnn
i g/toosl-gud
i ance/desg
i n-and-cost-gud
i ance/user-gud
i e/
http://www.sportengland.org/facilities-planning/tools-guidance/design-and-cost-guidance/
Issue Tracker:
001 Initial Publication: July 2013
Sport England
3rd Floor Victoria House
Bloomsbury Square
London
WC1B 4SE
ISBN 978-1-86078-261-9
Sport England, July 2013
Further Information:
To find out more about Sport England and to get the latest news and information about our various
initiatives and programmes, please go to www.sportengland.org
July Revision 001
33