: 1625 KW
Steam inlet to Back pressure Turbine: 42 kg/sq cm press & 400 deg C
Steam outlet to Back pressure Turbine: 4.5 kg/sq cm press & 400 deg C
Steam inlet to condensing Turbine: 4 kg/sq cm press & 400 deg C
Steam outlet to condensing turbine: 0.1 ATA
Steam flow requirement: 20 T/Hr
Turbine speed
Generator speed
: 6500 RPM
: 1500 RPM
4. Lube oil low alarm and lube oil trip is not there.
5. Over speed trip mechanism is not there.
6. There is no document evidence for critical speed and minimum governor speed.
Job scope:
A new shut off valve to make and provide.
Governor system to be corrected
Overspeed trip, low LO alarm/ trip, High vibration alarm/trip to be provided.
After providing all these turbine to be run and to be loaded.