PANEL TEST REPORT

PROJECT
PANEL

DATE

FABRICAOTR :

TESTED AT :

ATTENDED BY :
(1)
(2)
(3)

PANEL PARTICULARS :
TYPE :
RATED VOLTAGE :

BUSBAR MATERIAL & SIZE :


EARTHING BUSBAR :
CONTROL VOLTAGE :

RATED CURRENT :

DIST. BETWEEN SUPPORTS :

RATED FREQUENCY :

DIST. BETWEEN BUSBAR :

TESTS :
1.

2.

PHYSICAL EXAMINATION :
- DIMENSION CHECK (L, B, H) - CHECK FOR PAINT DAMAGE H.V. TEST :
TEST VOLTAGE :

O.K.
O.K.

NOT O.K.
NOT O.K.

2.5 KV FOR 1 MINUTE BETWEEN PHASES R, Y, B, N & E


1.5 KV FOR 1 MINUTE BETWEEN PHASES & N/E
O.K.

3.

INSULATION RESISTANCE TEST :


MEGGER VOLTAGE

NOT O.K.

TYPE

1000 V DC.

:
RY

YB

MANUAL / MOTORISED
BR

RYB-N

RYBN-E

N-E

BEFORE HV
AFTER HV
4.

CIRCUIT WIRING :

O.K.

NOT O.K.

5.

INTERLOCKING :

O.K.

NOT O.K.

FABRICATION :
1.

MATERIAL :

2.

THICKNESS :
MAIN FRAME DOOR
-

3.

GAUGE
GAUGE

PAINT :
INTERIOR :
EXTERIOR :

4.

DOOR :

5.

OVERALL SIZE :

6.

NO. OF SECTIONS & SIZES :

7.

WEIGHT ( TOTAL ) :

8.

BASE CHANNEL :

9.

PROTECTION CLASS :

NO. OF I / C :

HINGED

(1)

SCREW TYPE

(2)

(3)

NO. OF O/G. :

REMARKS :

SPARES

DUMMY :

CHECK LIST :
DESCRIPTION :
1.

SWITCHGEAR SIZE & MAKE

2.

BUSBAR MATERIAL & SIZE

3.

TAILS / DROPPER SIZE


(1)
(2)
(3)

4.

CONNECTOR SIZE, POSITION & NO. OF SPARES

5.

OVERALL SIZE

6.

SPACE AVAILABLE ON SITE

7.

PAINTING

8.

TYPE OF DOOR

9.

EYE BOLT

10.

CT RATIO & METERS RANGES

11.

SWITCHGEAR SUITABILITY FOR TERMINATION

12.

GLAND PLATE

13.

TYPE OF BOLTS, NUTS & WASHERS

14.

ACCESSORIES COPERATING HANDLE, MANUALS ETC.

15.

METHOD OF INSTALLATION AT SITE

16.

EARTHING BUS SIZE

17.

CONTROL WIRING / LOGIC

18

PANEL ILLUMINATION

19

DRAWING POCKET

20

NAME PLATES

21

ELECTRICAL INTERLOCKING

22

MECHANICAL INTERLOCKING

23

BIMETALLIC LUGS/JOINTS FOR COMPOSITE BUSBAR PANELS

24

EXHAUST FAN / COOLING ARRANGEMENT

25

CUBICLE NOTATION ON BACK SIDE

26

MAIN BUSBAR SUPPORT INTERVAL 500 MM

27

APFCR WITH 3CT/1CT

REMARKS :

O.K. NOT O.K.

N
N
N

N
N
N