top
AUTOMATION PLAN
PROJECT KICK-OFF MEETING
FIELD SURVEY
FUNCTIONAL DESCRIPTION
DETAILED DESCRIPTION
ACCEPTANCE TEST PLAN & PROCEDURES
SYSTEM DEVELOPMENT
SYSTEM INTEGRATION TASK
FACTORY ACCEPTANCE TEST
SUPPORT SERVICES
DOCUMENTATION
Automation Plan
12/13/2006 3:33 PM
Explanation of Steps
2 of 12
http://www.matrixautomation.com/approach/appexpl.htm
12/13/2006 3:33 PM
Explanation of Steps
3 of 12
http://www.matrixautomation.com/approach/appexpl.htm
FIELD SURVEY
FUNCTIONAL DESCRIPTION
12/13/2006 3:33 PM
Explanation of Steps
4 of 12
http://www.matrixautomation.com/approach/appexpl.htm
DETAILED DESCRIPTION
12/13/2006 3:33 PM
Explanation of Steps
5 of 12
http://www.matrixautomation.com/approach/appexpl.htm
12/13/2006 3:33 PM
Explanation of Steps
6 of 12
http://www.matrixautomation.com/approach/appexpl.htm
SYSTEM DEVELOPMENT
12/13/2006 3:33 PM
Explanation of Steps
7 of 12
http://www.matrixautomation.com/approach/appexpl.htm
12/13/2006 3:33 PM
Explanation of Steps
8 of 12
http://www.matrixautomation.com/approach/appexpl.htm
12/13/2006 3:33 PM
Explanation of Steps
9 of 12
http://www.matrixautomation.com/approach/appexpl.htm
results.
If necessary, integrator engineers correct
any errors discovered and perform
regression tests to show correct system
performance.
Client and integrator jointly develop a
"punch" list of items, if any, which require
further action and/or correction before
shipment.
Return to Approach Overview
Back to top
SUPPORT SERVICE
12/13/2006 3:33 PM
Explanation of Steps
10 of 12
http://www.matrixautomation.com/approach/appexpl.htm
12/13/2006 3:33 PM
Explanation of Steps
11 of 12
http://www.matrixautomation.com/approach/appexpl.htm
DOCUMENTATION
12/13/2006 3:33 PM
Explanation of Steps
12 of 12
http://www.matrixautomation.com/approach/appexpl.htm
12/13/2006 3:33 PM