SUPPLY,FABRICATE AND INSTALL SIGNAGE AND FENCING ON PNB DE

Item
1.0
1.1

1.2

2.0
2.1

2.2

3.0
3.1

3.2

4.0
4.1

5.0
5.1

6.0
6.1

6.2

7.0
7.1

7.2

SUPPLY,FABRICATE AND INSTALL SIGNAGE AND FENCING ON PNB DEVELOPMENT SDN. BHD. LAND BANK
Description
OLD LUNDERSTON
ADDITION
1.1.1 Extend Site Clearance work
1.1.2 Extend fencing work (0.13 KM)
1.1.3 To 1 construct additional Boom gate of 3 feet high x 10 feet wide
1.1.4 Modification of 2 boom gate
1.1.5 Additional 1 nos post for boom gate due to vandalism
OMISSION
1.2.1 Fencing (0.05 KM)
KOTA SERI LANGAT
ADDITION
2.1.1 Additional demarcation survey for the perimeter boundary and pegging (1.30 KM)
2.1.2 To provide as-built for additional demarcation survey upon completion
2.1.3 Clearance of bushes, big and small trees for 2m inside and 2m outside the fencing line (1.3 KM)
2.1.4 Fencing (1.3 KM)
2.1.5 To construct 2 additional Boom gate of 3 feet high x 10 feet wide
2.1.6 Modification of 3 boom gate
OMISSION
2.2.1 Clearance of bushes, big and small trees for 2m inside and 2m outside the fencing line (0.18 KM)
2.2.2 Fencing (0.25 KM)

SG WANGI ESTATE
ADDITION
3.1.1 To construct 1 additional Boom gate of 3 feet high x 10 feet wide
3.1.2 Modification of 1 boom gate
OMISSION
3.2.1 Clearance of bushes, big and small trees for 2m inside and 2m outside the fencing line (1.1 KM)
3.2.2 Fencing (1.16 KM)
SG MAHANG
ADDITION
4.1.1 Clearance of bushes, big and small trees for 2m inside and 2m outside the fencing line (0.95 KM)
SAUJANA IMPIAN
OMISSION
5.1.1 Fencing (0.02 KM)
KOTA BAYUEMAS
ADDITION
6.1.1 Demolish existing building and dumping off site
6.1.2 Modification of 1 boom gate
OMISSION
6.2.1 Fencing (0.20 KM)
BAYU LAKE HOMES
ADDITION
7.1.1 Clearance of bushes, big and small trees for 2m inside and 2m outside the fencing line (4.042 KM)
7.1.2 To construct 1 additional Boom gate of 3 feet high x 10 feet wide
OMISSION

7.2.1 Fencing (0.06 KM)